
|
Viaduct Reconstruction Complete
As of September 2, 2011, 159th Viaduct Reconstruction is complete. 159th Street is now open between the Tristate Tollway (I-294) and Halsted St. (IL Rt. 1) in Harvey, IL. |
* Please note all businesses in the work zone will be
open during construction
This site will provide useful information throughout the reconstruction
process, as the Illinois Department of Transportation (IDOT) is committed to
keeping you informed with up-to-date information on the 159th Street Viaduct
Reconstruction in Harvey, IL.
IDOT will reconstruct the viaduct that carries Metra and Canadian National
Railroad over 159th St. in Harvey, IL. The project is generally between Halsted
(IL Rt. 1) and Park Ave. Some parts of the current viaduct were constructed in
the early 1900’s and there is only sufficient room for one lane of traffic in
each direction under the viaduct in its current configuration.
This major improvement will reconstruct the two main railroad bridges over 159th
St. to allow for two through lanes of traffic in each direction under the
railroad along with left turn lanes. This is the major local route connecting
Interstate 294 with Interstate 94 through the towns of Harvey and South Holland.
When complete, a famous south suburban bottleneck will be eliminated. The
project will provide significant congestion relief and reduce travel times along
this local route. This project will be completed along with a roadway project
that will widen and improve 159th St. from I-294 to east of Halsted St.
Click
here for 159th Street Roadway Reconstruction website.
This project will take approximately 32 months to complete due to extensive
coordination with two railroads (Metra & Canadian National Railroad). Work will
require a shut-down of 159th Street and detour of traffic for 20 months
beginning in September 2009. The detour will route traffic down Dixie Hwy to
Sibley to Halsted St and back to 159th. The detour route is 4.9 miles.
Click
here for Map of Detour Route.
Progress Report

General Contractor:
Walsh Construction Corporation
|
|
20 Sub-contractors will be on this project including:
K-Five Construction Ricci Welch Mosley Construction* K & K Iron Works MA Steel Erectors*
Aldridge Electric
* Minority Business Enterprise
|
|
|
|
|
Project Information:
Letting: June 13th, 2008
Project Cost: Approximately $38.4 million
Construction start: October, 2008
Construction end: May, 2011
|
|
Job Specific Information:
1096 Tons of Structural Steel
10,500 Cubic Yards of Concrete will be used in the construction of the
Railroad Bridges and Foundations. This is more than 1000 loads of concrete
delivered to the jobsite. 10,500 Cubic Yards of Concrete is equivalent to
2,121,000 gallons of Concrete.
1,725,000 pounds of Epoxy Coated Rebar
1.3 miles of Railroad Track
20,060 square yards of new Portland Concrete Cement Pavement
Construction on Metra Electric facilities
|
Project Photos
(click on pictures for larger version)
Newsletter
Press Releases
September 3, 2009
September 10, 2009 - Southtown Star Newspaper
September 11, 2009 - Chicago Tribune IDOT Construction Zones
IDOT's new website provides up to date information on all current active
construction contracts, including those funded through the American Recovery and
Reinvestment Act of 2009, after contract execution.
Other Project Links
If you are a small business and are interested in work on road
construction projects with IDOT,
click here for information on IDOT’s Disadvantaged Business Enterprise program.
If you have a specific project-related question, you can submit your
question by visiting IDOT’s website
http://www.dot.il.gov/contact.html, and fill out the email form and you
will receive a prompt response.
Please note this site is currently under construction and we
appreciate your patience while we continue to update this website. Check
back periodically for website updates. The Illinois Department of
Transportation continues to look forward to your input and support
throughout this project.
|