PROJECT OVERVIEW

The Illinois Department of Transportation will construct a full interchange for the Interstate 57 overpass at Interstate 294. The overall Interstate 57/294 Interchange Project will consist of 11 separate contracts. Preliminary work will begin this fall with construction of the overpass ending in 2012. The Interstate 57/294 Project will be funded with a mix of state and federal dollars. Future contracts will be dependent on federal approval and funding from the Federal Highway Administration.

CONTRACT #1

Contract #1 calls for removing and replacing the northbound and southbound Interstate 57 bridges over Interstate 294. In addition, Interstate 57 will be widened to accommodate the traffic movements of the future interchange. Preliminary work starts in the fall of 2010 with completion anticipated in 2012. The first contract will be constructed with State-only funds.

Contractor: Lorig Construction Company
Contract #: 60J27
Cost: $27,936,000.32
County: Cook
Start date: November, 2010
End date: September, 2012
Description: - Reconstruction of the I-57 over I-294 bridge
- Pavement widening
- Resurfacing

 


 
 
 
 
 
 

 