ILLINOIS DEPARTMENT OF TRANSPORTATION PAGE: 1 06/12/08 10:12:04 U N I T P R I C E T A B U L A T I O N O F B I D S LETTING DATE: 01/18/2008 LETTING TYPE: SCHEDULED CONTRACT NUMBER: 83905 LETTING ITEM NUMBER: 065 RESPONSIBLE DISTRICT: 01 BIDS LOCKED: Y SECTION: 06-00047-00-LS COUNTY: COOK ESTIMATE: STATE JOB NUMBER: C-91-005-07 MUNICIPALITY: HARWOOD HEIGHTS PROJECT NUMBER: CMM-M-TE-00D1/695/000 -------------------------- SUMMARY OF CONTRACTOR BIDS -------------------------- "AS READ" SUMMATION SUMMATION OF NBR BIDR CONTR COMB ITEM CONTR BIDDER OF BIDDER CALCULATED LOW BIDR CALC BLANK NBR BIDDER NAME GROUP COMB GRP NBR GROUP TOTAL PRICE EXTENSIONS EXTENSIONS BID EXTENSION DIFF BIDS 3315 A. Lamp Concrete Contractors, Inc. NO ALT 2,968,369.05 * 2,686,669.05 2,968,369.05 281,700.00+ 1 3702 Martam Construction Incorporated NO ALT 3,245,825.25 3,245,825.25 3,245,825.25 * **** TOTAL GROUP NO ALT PAY ITEMS FOR THIS CONTRACT = 147 ---------------------- DETAIL CONTRACTOR BIDS ---------------------- ITEM NBR ITEM DESCRIPTION UNIT OF UNIT BIDDER CALCULATED BIDR CALC BIDR NBR BIDDER NAME QUANTITY MEASURE PRICE EXTENSION EXTENSION EXTENSION DIFF B2000766 T-AMEL X GF AB SF 6' 11.000 EACH 3315 A. Lamp Concrete Contractors, Inc. 600.0000 6,600.00 6,600.00 3702 Martam Construction Incorporated 400.0000 4,400.00 4,400.00 B2001266 T-CORNUS ALT CL 6' 8.000 EACH 3315 A. Lamp Concrete Contractors, Inc. 600.0000 4,800.00 4,800.00 3702 Martam Construction Incorporated 300.0000 2,400.00 2,400.00 C2C09918 S-SPIREA X BUM GF 18C 68.000 EACH 3315 A. Lamp Concrete Contractors, Inc. 65.0000 4,420.00 4,420.00 3702 Martam Construction Incorporated 44.0000 2,992.00 2,992.00 C2007918 S-ROSA MEIPITAC 18 32.000 EACH 3315 A. Lamp Concrete Contractors, Inc. 55.0000 1,760.00 1,760.00 3702 Martam Construction Incorporated 50.0000 1,600.00 1,600.00 C2012772 S-VIBURN PRUN 6' 4.000 EACH 3315 A. Lamp Concrete Contractors, Inc. 500.0000 2,000.00 2,000.00 3702 Martam Construction Incorporated 380.0000 1,520.00 1,520.00 D20010S4 E-JUNIP HOR WIL 18S 7.000 EACH 3315 A. Lamp Concrete Contractors, Inc. 85.0000 595.00 595.00 3702 Martam Construction Incorporated 66.0000 462.00 462.00 D2001215 E-JUNIP SAB BDM 15 2.000 EACH 3315 A. Lamp Concrete Contractors, Inc. 85.0000 170.00 170.00 3702 Martam Construction Incorporated 58.0000 116.00 116.00 D2003424 E-TAXUS X MED BN 2' 20.000 EACH 3315 A. Lamp Concrete Contractors, Inc. 95.0000 1,900.00 1,900.00 3702 Martam Construction Incorporated 84.0000 1,680.00 1,680.00 XX000959 TRASH RECEPTACLES 7.000 EACH 3315 A. Lamp Concrete Contractors, Inc. 1,312.0000 9,184.00 9,184.00 3702 Martam Construction Incorporated 1,200.0000 8,400.00 8,400.00 XX001011 BICYCLE RACKS 19.000 EACH 3315 A. Lamp Concrete Contractors, Inc. 687.0000 13,053.00 13,053.00 3702 Martam Construction Incorporated 550.0000 10,450.00 10,450.00 XX003711 BUS SHELTER REMOVAL 1.000 EACH 3315 A. Lamp Concrete Contractors, Inc. 2,000.0000 2,000.00 2,000.00 3702 Martam Construction Incorporated 1,500.0000 1,500.00 1,500.00 XX004144 DRINKING FOUNTAIN 1.000 EACH 3315 A. Lamp Concrete Contractors, Inc. 7,500.0000 7,500.00 7,500.00 3702 Martam Construction Incorporated 13,800.0000 13,800.00 13,800.00 XX005283 BRICK PAVER CROSSWALK 6,154.000 SQ FT 3315 A. Lamp Concrete Contractors, Inc. 14.0000 86,156.00 86,156.00 3702 Martam Construction Incorporated 38.0000 233,852.00 233,852.00 XX005762 T-CARP CAROL 1-3/4 25.000 EACH 3315 A. Lamp Concrete Contractors, Inc. 450.0000 11,250.00 11,250.00 3702 Martam Construction Incorporated 430.0000 10,750.00 10,750.00 XX006392 CL D PATCH 6" SPECIAL 60.000 SQ YD 3315 A. Lamp Concrete Contractors, Inc. 75.0000 4,500.00 4,500.00 3702 Martam Construction Incorporated 115.0000 6,900.00 6,900.00 XX006471 SS 1 WAT MN SDR-21 12 236.000 FOOT 3315 A. Lamp Concrete Contractors, Inc. 85.0000 20,060.00 20,060.00 3702 Martam Construction Incorporated 144.0000 33,984.00 33,984.00 XX007207 BUS SHELTER PLATFORM 10.000 EACH 3315 A. Lamp Concrete Contractors, Inc. 1,500.0000 15,000.00 15,000.00 3702 Martam Construction Incorporated 1,800.0000 18,000.00 18,000.00 XX007208 LT P COM IN PLACE F1 45.000 EACH 3315 A. Lamp Concrete Contractors, Inc. * 3702 Martam Construction Incorporated 1.0000 45.00 45.00 XX007209 SKATEBOARD DETERRENT 595.000 FOOT 3315 A. Lamp Concrete Contractors, Inc. 13.3500 7,943.25 7,943.25 3702 Martam Construction Incorporated 21.0000 12,495.00 12,495.00 XX007210 T-TILIA CORDATA 2 7.000 EACH 3315 A. Lamp Concrete Contractors, Inc. 600.0000 4,200.00 4,200.00 3702 Martam Construction Incorporated 430.0000 3,010.00 3,010.00 XX007211 UD 1 40 #10 NEUT GND 440.000 FOOT 3315 A. Lamp Concrete Contractors, Inc. 6.0000 2,640.00 2,640.00 3702 Martam Construction Incorporated 4.5000 1,980.00 1,980.00 XX007212 UD 6/C 1/C #6 XLP 1.5 3,550.000 FOOT 3315 A. Lamp Concrete Contractors, Inc. 10.4000 36,920.00 36,920.00 3702 Martam Construction Incorporated 13.0000 46,150.00 46,150.00 XX007213 UD 7/C 2/C #6 XLP 1.5 1,780.000 FOOT 3315 A. Lamp Concrete Contractors, Inc. 11.4000 20,292.00 20,292.00 3702 Martam Construction Incorporated 16.0000 28,480.00 28,480.00 XX007214 UTILITY MANHOLE 2.000 EACH 3315 A. Lamp Concrete Contractors, Inc. 4,200.0000 8,400.00 8,400.00 3702 Martam Construction Incorporated 4,800.0000 9,600.00 9,600.00 XX007215 CONCRETE PLANTER WALL 1,252.000 CU YD 3315 A. Lamp Concrete Contractors, Inc. 250.0000 31,300.00 313,000.00 281,700.00+ 3702 Martam Construction Incorporated 1.0000 1,252.00 1,252.00 XX007216 LIGHTING UNIT COMP F1 45.000 EACH 3315 A. Lamp Concrete Contractors, Inc. 5,500.0000 247,500.00 247,500.00 3702 Martam Construction Incorporated 6,800.0000 306,000.00 306,000.00 X0300635 PLANTER 33.000 EACH 3315 A. Lamp Concrete Contractors, Inc. 1,322.0000 43,626.00 43,626.00 3702 Martam Construction Incorporated 2,300.0000 75,900.00 75,900.00 X0301407 PERENNIAL PLT-GAL POT 13.000 UNIT 3315 A. Lamp Concrete Contractors, Inc. 85.0000 1,105.00 1,105.00 3702 Martam Construction Incorporated 2,420.0000 31,460.00 31,460.00 X0301787 WATER CONTROL STR TA 1.000 EACH 3315 A. Lamp Concrete Contractors, Inc. 7,500.0000 7,500.00 7,500.00 3702 Martam Construction Incorporated 12,000.0000 12,000.00 12,000.00 X0320169 EXPOSED AGG SURF SPL 6,103.000 SQ FT 3315 A. Lamp Concrete Contractors, Inc. 10.0000 61,030.00 61,030.00 3702 Martam Construction Incorporated 14.0000 85,442.00 85,442.00 X0323426 SED CONT DR ST INL CL 55.000 EACH 3315 A. Lamp Concrete Contractors, Inc. 75.0000 4,125.00 4,125.00 3702 Martam Construction Incorporated 75.0000 4,125.00 4,125.00 X0444100 BENCHES 33.000 EACH 3315 A. Lamp Concrete Contractors, Inc. 1,320.0000 43,560.00 43,560.00 3702 Martam Construction Incorporated 2,500.0000 82,500.00 82,500.00 X0540000 BRICK PAVERS 11,471.000 SQ FT 3315 A. Lamp Concrete Contractors, Inc. 12.0000 137,652.00 137,652.00 3702 Martam Construction Incorporated 15.0000 172,065.00 172,065.00 X4067107 POL LB MM IL4.75 N50 480.000 TON 3315 A. Lamp Concrete Contractors, Inc. 120.0000 57,600.00 57,600.00 3702 Martam Construction Incorporated 116.0000 55,680.00 55,680.00 X6028300 INLETS REMOVED SPL 10.000 EACH 3315 A. Lamp Concrete Contractors, Inc. 650.0000 6,500.00 6,500.00 3702 Martam Construction Incorporated 650.0000 6,500.00 6,500.00 X8950200 REBUILD EX HANDHOLE 4.000 EACH 3315 A. Lamp Concrete Contractors, Inc. 1,500.0000 6,000.00 6,000.00 3702 Martam Construction Incorporated 3,700.0000 14,800.00 14,800.00 Z0013798 CONSTRUCTION LAYOUT 1.000 L SUM 3315 A. Lamp Concrete Contractors, Inc. 75,000.0000 75,000.00 75,000.00 3702 Martam Construction Incorporated 30,000.0000 30,000.00 30,000.00 Z0076600 TRAINEES 1,000.000 HOUR 3315 A. Lamp Concrete Contractors, Inc. 0.8000 800.00 800.00 3702 Martam Construction Incorporated 0.8000 800.00 800.00 20100110 TREE REMOV 6-15 119.000 UNIT 3315 A. Lamp Concrete Contractors, Inc. 25.0000 2,975.00 2,975.00 3702 Martam Construction Incorporated 30.0000 3,570.00 3,570.00 20100210 TREE REMOV OVER 15 36.000 UNIT 3315 A. Lamp Concrete Contractors, Inc. 30.0000 1,080.00 1,080.00 3702 Martam Construction Incorporated 40.0000 1,440.00 1,440.00 20101100 TREE TRUNK PROTECTION 5.000 EACH 3315 A. Lamp Concrete Contractors, Inc. 350.0000 1,750.00 1,750.00 3702 Martam Construction Incorporated 125.0000 625.00 625.00 20101200 TREE ROOT PRUNING 10.000 EACH 3315 A. Lamp Concrete Contractors, Inc. 200.0000 2,000.00 2,000.00 3702 Martam Construction Incorporated 135.0000 1,350.00 1,350.00 20200100 EARTH EXCAVATION 2,190.000 CU YD 3315 A. Lamp Concrete Contractors, Inc. 36.0000 78,840.00 78,840.00 3702 Martam Construction Incorporated 63.0000 137,970.00 137,970.00 20201200 REM & DISP UNS MATL 337.000 CU YD 3315 A. Lamp Concrete Contractors, Inc. 35.0000 11,795.00 11,795.00 3702 Martam Construction Incorporated 63.0000 21,231.00 21,231.00 20700420 POROUS GRAN EMB SUBGR 337.000 CU YD 3315 A. Lamp Concrete Contractors, Inc. 35.0000 11,795.00 11,795.00 3702 Martam Construction Incorporated 46.0000 15,502.00 15,502.00 20800250 TRENCH BACKFILL SPL 930.000 CU YD 3315 A. Lamp Concrete Contractors, Inc. 32.0000 29,760.00 29,760.00 3702 Martam Construction Incorporated 46.0000 42,780.00 42,780.00 21101615 TOPSOIL F & P 4 898.000 SQ YD 3315 A. Lamp Concrete Contractors, Inc. 2.0000 1,796.00 1,796.00 3702 Martam Construction Incorporated 7.5000 6,735.00 6,735.00 25000400 NITROGEN FERT NUTR 12.000 POUND 3315 A. Lamp Concrete Contractors, Inc. 1.0000 12.00 12.00 3702 Martam Construction Incorporated 4.0000 48.00 48.00 25000500 PHOSPHORUS FERT NUTR 12.000 POUND 3315 A. Lamp Concrete Contractors, Inc. 1.0000 12.00 12.00 3702 Martam Construction Incorporated 4.0000 48.00 48.00 25000600 POTASSIUM FERT NUTR 12.000 POUND 3315 A. Lamp Concrete Contractors, Inc. 1.0000 12.00 12.00 3702 Martam Construction Incorporated 4.0000 48.00 48.00 25100105 MULCH METHOD 1 .100 ACRE 3315 A. Lamp Concrete Contractors, Inc. 10,000.0000 1,000.00 1,000.00 3702 Martam Construction Incorporated 8,000.0000 800.00 800.00 25200110 SODDING SALT TOLERANT 928.000 SQ YD 3315 A. Lamp Concrete Contractors, Inc. 11.0000 10,208.00 10,208.00 3702 Martam Construction Incorporated 11.0000 10,208.00 10,208.00 25200200 SUPPLE WATERING 5.000 UNIT 3315 A. Lamp Concrete Contractors, Inc. 1.0000 5.00 5.00 3702 Martam Construction Incorporated 1.0000 5.00 5.00 28000510 INLET FILTERS 55.000 EACH 3315 A. Lamp Concrete Contractors, Inc. 225.0000 12,375.00 12,375.00 3702 Martam Construction Incorporated 250.0000 13,750.00 13,750.00 31101200 SUB GRAN MAT B 4 1,061.000 SQ YD 3315 A. Lamp Concrete Contractors, Inc. 5.0000 5,305.00 5,305.00 3702 Martam Construction Incorporated 10.0000 10,610.00 10,610.00 35101400 AGG BASE CSE B 114.000 TON 3315 A. Lamp Concrete Contractors, Inc. 20.0000 2,280.00 2,280.00 3702 Martam Construction Incorporated 52.0000 5,928.00 5,928.00 35300400 PCC BSE CSE 9 1,773.000 SQ YD 3315 A. Lamp Concrete Contractors, Inc. 65.0000 115,245.00 115,245.00 3702 Martam Construction Incorporated 59.0000 104,607.00 104,607.00 40201000 AGGREGATE-TEMP ACCESS 500.000 TON 3315 A. Lamp Concrete Contractors, Inc. 15.0000 7,500.00 7,500.00 3702 Martam Construction Incorporated 33.0000 16,500.00 16,500.00 40600100 BIT MATLS PR CT 1,289.000 GALLON 3315 A. Lamp Concrete Contractors, Inc. 3.0000 3,867.00 3,867.00 3702 Martam Construction Incorporated 2.0000 2,578.00 2,578.00 40600300 AGG PR CT 26.000 TON 3315 A. Lamp Concrete Contractors, Inc. 1.0000 26.00 26.00 3702 Martam Construction Incorporated 1.0000 26.00 26.00 40603080 HMA BC IL-19.0 N50 20.000 TON 3315 A. Lamp Concrete Contractors, Inc. 70.0000 1,400.00 1,400.00 3702 Martam Construction Incorporated 220.0000 4,400.00 4,400.00 40603085 HMA BC IL-19.0 N70 229.000 TON 3315 A. Lamp Concrete Contractors, Inc. 75.0000 17,175.00 17,175.00 3702 Martam Construction Incorporated 110.0000 25,190.00 25,190.00 40603310 HMA SC "C" N50 20.000 TON 3315 A. Lamp Concrete Contractors, Inc. 100.0000 2,000.00 2,000.00 3702 Martam Construction Incorporated 225.0000 4,500.00 4,500.00 40603340 HMA SC "D" N70 1,112.000 TON 3315 A. Lamp Concrete Contractors, Inc. 80.0000 88,960.00 88,960.00 3702 Martam Construction Incorporated 81.0000 90,072.00 90,072.00 42300500 PCC DRIVEWAY PAVT 9 524.000 SQ YD 3315 A. Lamp Concrete Contractors, Inc. 65.0000 34,060.00 34,060.00 3702 Martam Construction Incorporated 58.0000 30,392.00 30,392.00 42400430 PC CONC SIDEWALK 5 SP 24,270.000 SQ FT 3315 A. Lamp Concrete Contractors, Inc. 6.0000 145,620.00 145,620.00 3702 Martam Construction Incorporated 7.0000 169,890.00 169,890.00 44000100 PAVEMENT REM 790.000 SQ YD 3315 A. Lamp Concrete Contractors, Inc. 10.0000 7,900.00 7,900.00 3702 Martam Construction Incorporated 26.0000 20,540.00 20,540.00 44000157 HMA SURF REM 2 10,363.000 SQ YD 3315 A. Lamp Concrete Contractors, Inc. 3.0000 31,089.00 31,089.00 3702 Martam Construction Incorporated 3.5000 36,270.50 36,270.50 44000200 DRIVE PAVEMENT REM 2,045.000 SQ YD 3315 A. Lamp Concrete Contractors, Inc. 10.0000 20,450.00 20,450.00 3702 Martam Construction Incorporated 12.0000 24,540.00 24,540.00 44000500 COMB CURB GUTTER REM 3,839.000 FOOT 3315 A. Lamp Concrete Contractors, Inc. 3.5000 13,436.50 13,436.50 3702 Martam Construction Incorporated 10.0000 38,390.00 38,390.00 44000600 SIDEWALK REM 9,315.000 SQ FT 3315 A. Lamp Concrete Contractors, Inc. 1.2000 11,178.00 11,178.00 3702 Martam Construction Incorporated 2.0000 18,630.00 18,630.00 44002212 HMA RM OV PATCH 3 318.000 SQ YD 3315 A. Lamp Concrete Contractors, Inc. 6.0000 1,908.00 1,908.00 3702 Martam Construction Incorporated 12.0000 3,816.00 3,816.00 44200948 CL B PATCH T1 9 23.000 SQ YD 3315 A. Lamp Concrete Contractors, Inc. 150.0000 3,450.00 3,450.00 3702 Martam Construction Incorporated 188.0000 4,324.00 4,324.00 44200956 CL B PATCH T2 9 65.000 SQ YD 3315 A. Lamp Concrete Contractors, Inc. 135.0000 8,775.00 8,775.00 3702 Martam Construction Incorporated 152.0000 9,880.00 9,880.00 44200962 CL B PATCH T3 9 79.000 SQ YD 3315 A. Lamp Concrete Contractors, Inc. 90.0000 7,110.00 7,110.00 3702 Martam Construction Incorporated 110.0000 8,690.00 8,690.00 44200964 CL B PATCH T4 9 151.000 SQ YD 3315 A. Lamp Concrete Contractors, Inc. 85.0000 12,835.00 12,835.00 3702 Martam Construction Incorporated 94.0000 14,194.00 14,194.00 55019500 SS 1 RCP CL 4 12 826.000 FOOT 3315 A. Lamp Concrete Contractors, Inc. 45.0000 37,170.00 37,170.00 3702 Martam Construction Incorporated 47.0000 38,822.00 38,822.00 55019600 SS 1 RCP CL 4 15 15.000 FOOT 3315 A. Lamp Concrete Contractors, Inc. 50.0000 750.00 750.00 3702 Martam Construction Incorporated 55.0000 825.00 825.00 55019700 SS 1 RCP CL 4 18 66.000 FOOT 3315 A. Lamp Concrete Contractors, Inc. 65.0000 4,290.00 4,290.00 3702 Martam Construction Incorporated 67.0000 4,422.00 4,422.00 55019900 SS 1 RCP CL 4 24 91.000 FOOT 3315 A. Lamp Concrete Contractors, Inc. 80.0000 7,280.00 7,280.00 3702 Martam Construction Incorporated 98.0000 8,918.00 8,918.00 55020300 SS 1 RCP CL 3 36 197.000 FOOT 3315 A. Lamp Concrete Contractors, Inc. 90.0000 17,730.00 17,730.00 3702 Martam Construction Incorporated 116.0000 22,852.00 22,852.00 55100400 STORM SEWER REM 10 135.000 FOOT 3315 A. Lamp Concrete Contractors, Inc. 10.0000 1,350.00 1,350.00 3702 Martam Construction Incorporated 6.0000 810.00 810.00 55100500 STORM SEWER REM 12 6.000 FOOT 3315 A. Lamp Concrete Contractors, Inc. 10.0000 60.00 60.00 3702 Martam Construction Incorporated 10.0000 60.00 60.00 60107600 PIPE UNDERDRAINS 4 200.000 FOOT 3315 A. Lamp Concrete Contractors, Inc. 25.0000 5,000.00 5,000.00 3702 Martam Construction Incorporated 25.0000 5,000.00 5,000.00 60200105 CB TA 4 DIA T1F OL 2.000 EACH 3315 A. Lamp Concrete Contractors, Inc. 1,750.0000 3,500.00 3,500.00 3702 Martam Construction Incorporated 3,000.0000 6,000.00 6,000.00 60201105 CB TA 4 DIA T11F&G 18.000 EACH 3315 A. Lamp Concrete Contractors, Inc. 1,800.0000 32,400.00 32,400.00 3702 Martam Construction Incorporated 3,000.0000 54,000.00 54,000.00 60201110 CB TA 4 DIA T11V F&G 5.000 EACH 3315 A. Lamp Concrete Contractors, Inc. 1,800.0000 9,000.00 9,000.00 3702 Martam Construction Incorporated 3,000.0000 15,000.00 15,000.00 60204805 CB TA 5 DIA T11F&G 6.000 EACH 3315 A. Lamp Concrete Contractors, Inc. 2,500.0000 15,000.00 15,000.00 3702 Martam Construction Incorporated 3,880.0000 23,280.00 23,280.00 60207905 CB TC T11F&G 15.000 EACH 3315 A. Lamp Concrete Contractors, Inc. 1,200.0000 18,000.00 18,000.00 3702 Martam Construction Incorporated 1,400.0000 21,000.00 21,000.00 60207915 CB TC T11V F&G 2.000 EACH 3315 A. Lamp Concrete Contractors, Inc. 1,250.0000 2,500.00 2,500.00 3702 Martam Construction Incorporated 1,400.0000 2,800.00 2,800.00 60218400 MAN TA 4 DIA T1F CL 6.000 EACH 3315 A. Lamp Concrete Contractors, Inc. 2,250.0000 13,500.00 13,500.00 3702 Martam Construction Incorporated 2,800.0000 16,800.00 16,800.00 60221100 MAN TA 5 DIA T1F CL 11.000 EACH 3315 A. Lamp Concrete Contractors, Inc. 3,000.0000 33,000.00 33,000.00 3702 Martam Construction Incorporated 5,300.0000 58,300.00 58,300.00 60223800 MAN TA 6 DIA T1F CL 1.000 EACH 3315 A. Lamp Concrete Contractors, Inc. 5,000.0000 5,000.00 5,000.00 3702 Martam Construction Incorporated 6,600.0000 6,600.00 6,600.00 60250200 CB ADJUST 3.000 EACH 3315 A. Lamp Concrete Contractors, Inc. 250.0000 750.00 750.00 3702 Martam Construction Incorporated 700.0000 2,100.00 2,100.00 60250500 CB ADJ NEW T1F CL 1.000 EACH 3315 A. Lamp Concrete Contractors, Inc. 450.0000 450.00 450.00 3702 Martam Construction Incorporated 900.0000 900.00 900.00 60255500 MAN ADJUST 19.000 EACH 3315 A. Lamp Concrete Contractors, Inc. 350.0000 6,650.00 6,650.00 3702 Martam Construction Incorporated 550.0000 10,450.00 10,450.00 60255800 MAN ADJ NEW T1F CL 5.000 EACH 3315 A. Lamp Concrete Contractors, Inc. 500.0000 2,500.00 2,500.00 3702 Martam Construction Incorporated 800.0000 4,000.00 4,000.00 60260100 INLETS ADJUST 3.000 EACH 3315 A. Lamp Concrete Contractors, Inc. 250.0000 750.00 750.00 3702 Martam Construction Incorporated 500.0000 1,500.00 1,500.00 60265700 VV ADJUST 10.000 EACH 3315 A. Lamp Concrete Contractors, Inc. 300.0000 3,000.00 3,000.00 3702 Martam Construction Incorporated 500.0000 5,000.00 5,000.00 60500040 REMOV MANHOLES 4.000 EACH 3315 A. Lamp Concrete Contractors, Inc. 350.0000 1,400.00 1,400.00 3702 Martam Construction Incorporated 250.0000 1,000.00 1,000.00 60500050 REMOV CATCH BAS 4.000 EACH 3315 A. Lamp Concrete Contractors, Inc. 250.0000 1,000.00 1,000.00 3702 Martam Construction Incorporated 250.0000 1,000.00 1,000.00 60603800 COMB CC&G TB6.12 3,818.000 FOOT 3315 A. Lamp Concrete Contractors, Inc. 15.5000 59,179.00 59,179.00 3702 Martam Construction Incorporated 20.0000 76,360.00 76,360.00 66900200 NON SPL WASTE DISPOSL 50.000 CU YD 3315 A. Lamp Concrete Contractors, Inc. 200.0000 10,000.00 10,000.00 3702 Martam Construction Incorporated 211.0000 10,550.00 10,550.00 66900400 SPL WAST GRD WAT DISP 275.000 GALLON 3315 A. Lamp Concrete Contractors, Inc. 6.0000 1,650.00 1,650.00 3702 Martam Construction Incorporated 15.0000 4,125.00 4,125.00 66900450 SPL WASTE PLNS/REPORT 1.000 L SUM 3315 A. Lamp Concrete Contractors, Inc. 10,000.0000 10,000.00 10,000.00 3702 Martam Construction Incorporated 14,000.0000 14,000.00 14,000.00 66900530 SOIL DISPOSAL ANALY 3.000 EACH 3315 A. Lamp Concrete Contractors, Inc. 3,500.0000 10,500.00 10,500.00 3702 Martam Construction Incorporated 1,300.0000 3,900.00 3,900.00 66901000 BACKFILL PLUGS 30.000 CU YD 3315 A. Lamp Concrete Contractors, Inc. 175.0000 5,250.00 5,250.00 3702 Martam Construction Incorporated 223.0000 6,690.00 6,690.00 67000400 ENGR FIELD OFFICE A 7.000 CAL MO 3315 A. Lamp Concrete Contractors, Inc. 1,500.0000 10,500.00 10,500.00 3702 Martam Construction Incorporated 2,500.0000 17,500.00 17,500.00 67100100 MOBILIZATION 1.000 L SUM 3315 A. Lamp Concrete Contractors, Inc. 105,000.0000 105,000.00 105,000.00 3702 Martam Construction Incorporated 200,000.0000 200,000.00 200,000.00 70102620 TR CONT & PROT 701501 1.000 L SUM 3315 A. Lamp Concrete Contractors, Inc. 2,500.0000 2,500.00 2,500.00 3702 Martam Construction Incorporated 1.0000 1.00 1.00 70102622 TR CONT & PROT 701502 1.000 L SUM 3315 A. Lamp Concrete Contractors, Inc. 2,500.0000 2,500.00 2,500.00 3702 Martam Construction Incorporated 1.0000 1.00 1.00 70102625 TR CONT & PROT 701606 1.000 L SUM 3315 A. Lamp Concrete Contractors, Inc. 86,000.0000 86,000.00 86,000.00 3702 Martam Construction Incorporated 140,000.0000 140,000.00 140,000.00 70102632 TR CONT & PROT 701602 1.000 L SUM 3315 A. Lamp Concrete Contractors, Inc. 120,000.0000 120,000.00 120,000.00 3702 Martam Construction Incorporated 1.0000 1.00 1.00 70102635 TR CONT & PROT 701701 1.000 L SUM 3315 A. Lamp Concrete Contractors, Inc. 2,500.0000 2,500.00 2,500.00 3702 Martam Construction Incorporated 1.0000 1.00 1.00 70102640 TR CONT & PROT 701801 1.000 L SUM 3315 A. Lamp Concrete Contractors, Inc. 6,500.0000 6,500.00 6,500.00 3702 Martam Construction Incorporated 1.0000 1.00 1.00 70300220 TEMP PVT MK LINE 4 13,091.000 FOOT 3315 A. Lamp Concrete Contractors, Inc. 0.4000 5,236.40 5,236.40 3702 Martam Construction Incorporated 0.2500 3,272.75 3,272.75 70301000 WORK ZONE PAVT MK REM 4,364.000 SQ FT 3315 A. Lamp Concrete Contractors, Inc. 1.3000 5,673.20 5,673.20 3702 Martam Construction Incorporated 0.8000 3,491.20 3,491.20 72000100 SIGN PANEL T1 58.000 SQ FT 3315 A. Lamp Concrete Contractors, Inc. 20.0000 1,160.00 1,160.00 3702 Martam Construction Incorporated 20.0000 1,160.00 1,160.00 72900100 METAL POST TY A 88.000 FOOT 3315 A. Lamp Concrete Contractors, Inc. 12.0000 1,056.00 1,056.00 3702 Martam Construction Incorporated 13.0000 1,144.00 1,144.00 78000100 THPL PVT MK LTR & SYM 265.000 SQ FT 3315 A. Lamp Concrete Contractors, Inc. 5.0000 1,325.00 1,325.00 3702 Martam Construction Incorporated 4.5000 1,192.50 1,192.50 78000200 THPL PVT MK LINE 4 10,798.000 FOOT 3315 A. Lamp Concrete Contractors, Inc. 0.8500 9,178.30 9,178.30 3702 Martam Construction Incorporated 0.8500 9,178.30 9,178.30 78000400 THPL PVT MK LINE 6 2,293.000 FOOT 3315 A. Lamp Concrete Contractors, Inc. 1.3000 2,980.90 2,980.90 3702 Martam Construction Incorporated 1.5000 3,439.50 3,439.50 78000600 THPL PVT MK LINE 12 64.000 FOOT 3315 A. Lamp Concrete Contractors, Inc. 6.0000 384.00 384.00 3702 Martam Construction Incorporated 3.0000 192.00 192.00 78000650 THPL PVT MK LINE 24 176.000 FOOT 3315 A. Lamp Concrete Contractors, Inc. 7.0000 1,232.00 1,232.00 3702 Martam Construction Incorporated 6.0000 1,056.00 1,056.00 78100100 RAISED REFL PAVT MKR 120.000 EACH 3315 A. Lamp Concrete Contractors, Inc. 50.0000 6,000.00 6,000.00 3702 Martam Construction Incorporated 41.0000 4,920.00 4,920.00 78300200 RAISED REF PVT MK REM 120.000 EACH 3315 A. Lamp Concrete Contractors, Inc. 15.0000 1,800.00 1,800.00 3702 Martam Construction Incorporated 12.0000 1,440.00 1,440.00 80400100 ELECT SERV INSTALL 1.000 EACH 3315 A. Lamp Concrete Contractors, Inc. 5,000.0000 5,000.00 5,000.00 3702 Martam Construction Incorporated 1,500.0000 1,500.00 1,500.00 81017510 CON T 1 CNC 110.000 FOOT 3315 A. Lamp Concrete Contractors, Inc. 4.0000 440.00 440.00 3702 Martam Construction Incorporated 3.0000 330.00 330.00 81017520 CON T 1 1/2 CNC 2,935.000 FOOT 3315 A. Lamp Concrete Contractors, Inc. 4.0000 11,740.00 11,740.00 3702 Martam Construction Incorporated 3.0000 8,805.00 8,805.00 81017525 CON T 2 CNC 300.000 FOOT 3315 A. Lamp Concrete Contractors, Inc. 5.0000 1,500.00 1,500.00 3702 Martam Construction Incorporated 4.0000 1,200.00 1,200.00 81017545 CON T 4 CNC 1,390.000 FOOT 3315 A. Lamp Concrete Contractors, Inc. 8.0000 11,120.00 11,120.00 3702 Martam Construction Incorporated 6.0000 8,340.00 8,340.00 81017555 CON T 5 CNC 1,740.000 FOOT 3315 A. Lamp Concrete Contractors, Inc. 12.0000 20,880.00 20,880.00 3702 Martam Construction Incorporated 8.0000 13,920.00 13,920.00 81018600 CON P 2 1/2 GALVS 455.000 FOOT 3315 A. Lamp Concrete Contractors, Inc. 16.0000 7,280.00 7,280.00 3702 Martam Construction Incorporated 28.0000 12,740.00 12,740.00 81018900 CON P 4 GALVS 100.000 FOOT 3315 A. Lamp Concrete Contractors, Inc. 30.0000 3,000.00 3,000.00 3702 Martam Construction Incorporated 38.0000 3,800.00 3,800.00 81022400 CON ENC C 5 PVC 300.000 FOOT 3315 A. Lamp Concrete Contractors, Inc. 45.0000 13,500.00 13,500.00 3702 Martam Construction Incorporated 30.0000 9,000.00 9,000.00 81028050 CON B&P CNC 1 1/2 1,100.000 FOOT 3315 A. Lamp Concrete Contractors, Inc. 8.0000 8,800.00 8,800.00 3702 Martam Construction Incorporated 10.0000 11,000.00 11,000.00 81028060 CON B&P CNC 2 100.000 FOOT 3315 A. Lamp Concrete Contractors, Inc. 18.0000 1,800.00 1,800.00 3702 Martam Construction Incorporated 11.0000 1,100.00 1,100.00 81400730 HANDHOLE C CONC 8.000 EACH 3315 A. Lamp Concrete Contractors, Inc. 600.0000 4,800.00 4,800.00 3702 Martam Construction Incorporated 1,200.0000 9,600.00 9,600.00 81900200 TR & BKFIL F ELECT WK 10,605.000 FOOT 3315 A. Lamp Concrete Contractors, Inc. 10.7000 113,473.50 113,473.50 3702 Martam Construction Incorporated 3.5000 37,117.50 37,117.50 82500560 LT CONT CBRCS 200-480 1.000 EACH 3315 A. Lamp Concrete Contractors, Inc. 12,000.0000 12,000.00 12,000.00 3702 Martam Construction Incorporated 7,500.0000 7,500.00 7,500.00 83600200 LIGHT POLE FDN 24D 360.000 FOOT 3315 A. Lamp Concrete Contractors, Inc. 165.0000 59,400.00 59,400.00 3702 Martam Construction Incorporated 155.0000 55,800.00 55,800.00 84200600 REM EX LT U NO SALV 6.000 EACH 3315 A. Lamp Concrete Contractors, Inc. 410.0000 2,460.00 2,460.00 3702 Martam Construction Incorporated 400.0000 2,400.00 2,400.00 84200700 LIGHTING FDN REMOV 6.000 EACH 3315 A. Lamp Concrete Contractors, Inc. 300.0000 1,800.00 1,800.00 3702 Martam Construction Incorporated 400.0000 2,400.00 2,400.00 84500110 REMOV LIGHTING CONTR 1.000 EACH 3315 A. Lamp Concrete Contractors, Inc. 1,000.0000 1,000.00 1,000.00 3702 Martam Construction Incorporated 400.0000 400.00 400.00 84500120 REMOV ELECT SERV INST 1.000 EACH 3315 A. Lamp Concrete Contractors, Inc. 1,000.0000 1,000.00 1,000.00 3702 Martam Construction Incorporated 250.0000 250.00 250.00 88600600 DET LOOP REPL 400.000 FOOT 3315 A. Lamp Concrete Contractors, Inc. 33.0000 13,200.00 13,200.00 3702 Martam Construction Incorporated 25.0000 10,000.00 10,000.00 88800100 PED PUSH-BUTTON 1.000 EACH 3315 A. Lamp Concrete Contractors, Inc. 715.0000 715.00 715.00 3702 Martam Construction Incorporated 400.0000 400.00 400.00 * - PAY ITEM UNIT PRICE AND/OR BIDDER TOTAL PRICE WAS OMITTED