ILLINOIS DEPARTMENT OF TRANSPORTATION PAGE: 1 09/17/04 13:00:24 U N I T P R I C E T A B U L A T I O N O F B I D S LETTING DATE: 07/30/2004 LETTING TYPE: SCHEDULED CONTRACT NUMBER: 62584 LETTING ITEM NUMBER: 001 RESPONSIBLE DISTRICT: 01 BIDS LOCKED: Y SECTION: (2323.6-2P&2324.6-1P)K COUNTY: COOK ESTIMATE: -------------------------- SUMMARY OF CONTRACTOR BIDS -------------------------- "AS READ" SUMMATION SUMMATION OF NBR BIDR CONTR COMB ITEM CONTR BIDDER OF BIDDER CALCULATED LOW BIDR CALC BLANK NBR BIDDER NAME GROUP COMB GRP NBR GROUP TOTAL PRICE EXTENSIONS EXTENSIONS BID EXTENSION DIFF BIDS 0346 Bartlett Bituminous Asphalt, L.L.C. NO ALT 4,704,211.48 4,704,211.48 4,704,211.48 0801 Capitol Cement Co., Inc. NO ALT 6,256,707.36 6,256,707.36 6,256,707.36 3069 K-Five Construction Corporation NO ALT 4,679,654.77 * 4,679,654.77 4,679,654.77 * 3505 Lorig Construction Company NO ALT 4,997,050.05 4,997,050.05 4,997,050.05 **** TOTAL GROUP NO ALT PAY ITEMS FOR THIS CONTRACT = 181 ---------------------- DETAIL CONTRACTOR BIDS ---------------------- ITEM NBR ITEM DESCRIPTION UNIT OF UNIT BIDDER CALCULATED BIDR CALC BIDR NBR BIDDER NAME QUANTITY MEASURE PRICE EXTENSION EXTENSION EXTENSION DIFF X0320815 SLEEPER SLAB 40.000 FOOT 0346 Bartlett Bituminous Asphalt, L.L.C. 240.0000 9,600.00 9,600.00 0801 Capitol Cement Co., Inc. 200.0000 8,000.00 8,000.00 3069 K-Five Construction Corporation 235.0000 9,400.00 9,400.00 3505 Lorig Construction Company 235.0000 9,400.00 9,400.00 X0322256 TEMP INFO SIGNING 786.000 SQ FT 0346 Bartlett Bituminous Asphalt, L.L.C. 25.0000 19,650.00 19,650.00 0801 Capitol Cement Co., Inc. 22.0000 17,292.00 17,292.00 3069 K-Five Construction Corporation 25.0000 19,650.00 19,650.00 3505 Lorig Construction Company 23.0000 18,078.00 18,078.00 X0322433 LT TOWER SERVICE PAD 1.000 EACH 0346 Bartlett Bituminous Asphalt, L.L.C. 8,500.0000 8,500.00 8,500.00 0801 Capitol Cement Co., Inc. 2,500.0000 2,500.00 2,500.00 3069 K-Five Construction Corporation 2,775.0000 2,775.00 2,775.00 3505 Lorig Construction Company 3,500.0000 3,500.00 3,500.00 X0323160 VIDEO INSP OF SS 500.000 FOOT 0346 Bartlett Bituminous Asphalt, L.L.C. 3.0000 1,500.00 1,500.00 0801 Capitol Cement Co., Inc. 15.0000 7,500.00 7,500.00 3069 K-Five Construction Corporation 4.0000 2,000.00 2,000.00 3505 Lorig Construction Company 4.0000 2,000.00 2,000.00 X0323426 SED CONT DR ST INL CL 40.000 EACH 0346 Bartlett Bituminous Asphalt, L.L.C. 100.0000 4,000.00 4,000.00 0801 Capitol Cement Co., Inc. 150.0000 6,000.00 6,000.00 3069 K-Five Construction Corporation 55.0000 2,200.00 2,200.00 3505 Lorig Construction Company 55.0000 2,200.00 2,200.00 X0323900 CONC FDN TY 1 1.000 FOOT 0346 Bartlett Bituminous Asphalt, L.L.C. 5,229.5300 5,229.53 5,229.53 0801 Capitol Cement Co., Inc. 4,375.7000 4,375.70 4,375.70 3069 K-Five Construction Corporation 4,800.0000 4,800.00 4,800.00 3505 Lorig Construction Company 5,000.0000 5,000.00 5,000.00 X0323907 COMMUNICATIONS VAULT 2.000 EACH 0346 Bartlett Bituminous Asphalt, L.L.C. 4,194.3800 8,388.76 8,388.76 0801 Capitol Cement Co., Inc. 3,509.0000 7,018.00 7,018.00 3069 K-Five Construction Corporation 3,900.0000 7,800.00 7,800.00 3505 Lorig Construction Company 4,000.0000 8,000.00 8,000.00 X0324159 WHITEWASH CONC PAVT 2,518.000 SQ YD 0346 Bartlett Bituminous Asphalt, L.L.C. 0.7000 1,762.60 1,762.60 0801 Capitol Cement Co., Inc. 2.0000 5,036.00 5,036.00 3069 K-Five Construction Corporation 1.8500 4,658.30 4,658.30 3505 Lorig Construction Company 0.9000 2,266.20 2,266.20 X0324469 CON EN RC 2-4 CNC 53.000 FOOT 0346 Bartlett Bituminous Asphalt, L.L.C. 53.0000 2,809.00 2,809.00 0801 Capitol Cement Co., Inc. 81.0000 4,293.00 4,293.00 3069 K-Five Construction Corporation 90.0000 4,770.00 4,770.00 3505 Lorig Construction Company 85.0000 4,505.00 4,505.00 X0324470 CON EN RC 3-4 CNC 155.000 FOOT 0346 Bartlett Bituminous Asphalt, L.L.C. 71.0000 11,005.00 11,005.00 0801 Capitol Cement Co., Inc. 72.3000 11,206.50 11,206.50 3069 K-Five Construction Corporation 80.0000 12,400.00 12,400.00 3505 Lorig Construction Company 75.0000 11,625.00 11,625.00 X0324472 CON EN RC 5-4 CNC 99.000 FOOT 0346 Bartlett Bituminous Asphalt, L.L.C. 65.0000 6,435.00 6,435.00 0801 Capitol Cement Co., Inc. 90.2000 8,929.80 8,929.80 3069 K-Five Construction Corporation 100.0000 9,900.00 9,900.00 3505 Lorig Construction Company 95.0000 9,405.00 9,405.00 X0324506 CON EN RC 2-2 RGC 72.000 FOOT 0346 Bartlett Bituminous Asphalt, L.L.C. 47.0000 3,384.00 3,384.00 0801 Capitol Cement Co., Inc. 80.0000 5,760.00 5,760.00 3069 K-Five Construction Corporation 88.0000 6,336.00 6,336.00 3505 Lorig Construction Company 83.0000 5,976.00 5,976.00 X0324638 LT SERV PAD/WALL 3'6" 3.000 EACH 0346 Bartlett Bituminous Asphalt, L.L.C. 11,000.0000 33,000.00 33,000.00 0801 Capitol Cement Co., Inc. 2,500.0000 7,500.00 7,500.00 3069 K-Five Construction Corporation 8,300.0000 24,900.00 24,900.00 3505 Lorig Construction Company 6,500.0000 19,500.00 19,500.00 X0324639 LT SERV PAD/WALL 5'0" 1.000 EACH 0346 Bartlett Bituminous Asphalt, L.L.C. 17,500.0000 17,500.00 17,500.00 0801 Capitol Cement Co., Inc. 5,000.0000 5,000.00 5,000.00 3069 K-Five Construction Corporation 10,500.0000 10,500.00 10,500.00 3505 Lorig Construction Company 9,000.0000 9,000.00 9,000.00 X0324640 FLUTED KNEEWALL 74.500 FOOT 0346 Bartlett Bituminous Asphalt, L.L.C. 164.7600 12,274.62 12,274.62 0801 Capitol Cement Co., Inc. 300.0000 22,350.00 22,350.00 3069 K-Five Construction Corporation 288.0000 21,456.00 21,456.00 3505 Lorig Construction Company 175.0000 13,037.50 13,037.50 X0324642 CON EN RC 1-3 RGC 28.000 FOOT 0346 Bartlett Bituminous Asphalt, L.L.C. 72.3200 2,024.96 2,024.96 0801 Capitol Cement Co., Inc. 60.5000 1,694.00 1,694.00 3069 K-Five Construction Corporation 67.0000 1,876.00 1,876.00 3505 Lorig Construction Company 65.0000 1,820.00 1,820.00 X0324644 CON EN RC 3 PVC 80.000 FOOT 0346 Bartlett Bituminous Asphalt, L.L.C. 63.2300 5,058.40 5,058.40 0801 Capitol Cement Co., Inc. 52.9000 4,232.00 4,232.00 3069 K-Five Construction Corporation 59.0000 4,720.00 4,720.00 3505 Lorig Construction Company 55.0000 4,400.00 4,400.00 X0324645 CON T 4 CNC 284.000 FOOT 0346 Bartlett Bituminous Asphalt, L.L.C. 30.9600 8,792.64 8,792.64 0801 Capitol Cement Co., Inc. 25.9000 7,355.60 7,355.60 3069 K-Five Construction Corporation 29.0000 8,236.00 8,236.00 3505 Lorig Construction Company 28.0000 7,952.00 7,952.00 X0324697 SOIL STABILIZERS 123,230.000 POUND 0346 Bartlett Bituminous Asphalt, L.L.C. 0.0100 1,232.30 1,232.30 0801 Capitol Cement Co., Inc. 0.6500 80,099.50 80,099.50 3069 K-Five Construction Corporation 0.5000 61,615.00 61,615.00 3505 Lorig Construction Company 0.7000 86,261.00 86,261.00 X0324698 APPLY DUST SUP AGENTS .200 UNIT 0346 Bartlett Bituminous Asphalt, L.L.C. 100,000.0000 20,000.00 20,000.00 0801 Capitol Cement Co., Inc. 5,000.0000 1,000.00 1,000.00 3069 K-Five Construction Corporation 5,500.0000 1,100.00 1,100.00 3505 Lorig Construction Company 20,000.0000 4,000.00 4,000.00 X0712400 TEMP PAVEMENT 9,384.000 SQ YD 0346 Bartlett Bituminous Asphalt, L.L.C. 34.9000 327,501.60 327,501.60 0801 Capitol Cement Co., Inc. 50.0000 469,200.00 469,200.00 3069 K-Five Construction Corporation 50.0000 469,200.00 469,200.00 3505 Lorig Construction Company 36.0000 337,824.00 337,824.00 X4066426 BC SC SUPER "D" N70 582.000 TON 0346 Bartlett Bituminous Asphalt, L.L.C. 57.0000 33,174.00 33,174.00 0801 Capitol Cement Co., Inc. 50.5000 29,391.00 29,391.00 3069 K-Five Construction Corporation 55.0000 32,010.00 32,010.00 3505 Lorig Construction Company 52.0000 30,264.00 30,264.00 X4066770 LEV BIND MM SUPER N70 582.000 TON 0346 Bartlett Bituminous Asphalt, L.L.C. 58.0000 33,756.00 33,756.00 0801 Capitol Cement Co., Inc. 50.5000 29,391.00 29,391.00 3069 K-Five Construction Corporation 54.0000 31,428.00 31,428.00 3505 Lorig Construction Company 53.0000 30,846.00 30,846.00 X4832450 PCC SHOULDERS 11 SPL 696.000 SQ YD 0346 Bartlett Bituminous Asphalt, L.L.C. 55.0000 38,280.00 38,280.00 0801 Capitol Cement Co., Inc. 65.0000 45,240.00 45,240.00 3069 K-Five Construction Corporation 60.0000 41,760.00 41,760.00 3505 Lorig Construction Company 55.0000 38,280.00 38,280.00 X6061001 COMB CC&G TM4.48 264.000 FOOT 0346 Bartlett Bituminous Asphalt, L.L.C. 27.0000 7,128.00 7,128.00 0801 Capitol Cement Co., Inc. 50.0000 13,200.00 13,200.00 3069 K-Five Construction Corporation 25.0000 6,600.00 6,600.00 3505 Lorig Construction Company 15.0000 3,960.00 3,960.00 X6063401 COMB CC&G TM4.12 2,295.000 FOOT 0346 Bartlett Bituminous Asphalt, L.L.C. 11.7800 27,035.10 27,035.10 0801 Capitol Cement Co., Inc. 20.0000 45,900.00 45,900.00 3069 K-Five Construction Corporation 12.0000 27,540.00 27,540.00 3505 Lorig Construction Company 10.0000 22,950.00 22,950.00 X6063600 COMB CC&G TM4.24 2,422.000 FOOT 0346 Bartlett Bituminous Asphalt, L.L.C. 10.0000 24,220.00 24,220.00 0801 Capitol Cement Co., Inc. 25.0000 60,550.00 60,550.00 3069 K-Five Construction Corporation 14.0000 33,908.00 33,908.00 3505 Lorig Construction Company 11.0000 26,642.00 26,642.00 X6065740 CONC MED SURF 5 MOD 5,907.000 SQ FT 0346 Bartlett Bituminous Asphalt, L.L.C. 4.2000 24,809.40 24,809.40 0801 Capitol Cement Co., Inc. 8.0000 47,256.00 47,256.00 3069 K-Five Construction Corporation 6.0000 35,442.00 35,442.00 3505 Lorig Construction Company 5.1000 30,125.70 30,125.70 X7011015 TR C-PROT EXPRESSWAYS 1.000 L SUM 0346 Bartlett Bituminous Asphalt, L.L.C. 55,000.0000 55,000.00 55,000.00 0801 Capitol Cement Co., Inc. 488,000.0000 488,000.00 488,000.00 3069 K-Five Construction Corporation 50,000.0000 50,000.00 50,000.00 3505 Lorig Construction Company 60,000.0000 60,000.00 60,000.00 X7013820 TR CONT SURVEIL EXPWY 444.000 CAL DA 0346 Bartlett Bituminous Asphalt, L.L.C. 625.0000 277,500.00 277,500.00 0801 Capitol Cement Co., Inc. 400.0000 177,600.00 177,600.00 3069 K-Five Construction Corporation 665.0000 295,260.00 295,260.00 3505 Lorig Construction Company 600.0000 266,400.00 266,400.00 X7015000 CHANGEABLE MESSAGE SN 16.000 CAL MO 0346 Bartlett Bituminous Asphalt, L.L.C. 2,000.0000 32,000.00 32,000.00 0801 Capitol Cement Co., Inc. 2,200.0000 35,200.00 35,200.00 3069 K-Five Construction Corporation 2,450.0000 39,200.00 39,200.00 3505 Lorig Construction Company 2,200.0000 35,200.00 35,200.00 X7040600 FUR TEMP CONC BARRIER 900.000 FOOT 0346 Bartlett Bituminous Asphalt, L.L.C. 35.0000 31,500.00 31,500.00 0801 Capitol Cement Co., Inc. 25.0000 22,500.00 22,500.00 3069 K-Five Construction Corporation 29.0000 26,100.00 26,100.00 3505 Lorig Construction Company 24.0000 21,600.00 21,600.00 X7330110 OSS WALKWAY CANT TA 16.500 FOOT 0346 Bartlett Bituminous Asphalt, L.L.C. 415.0000 6,847.50 6,847.50 0801 Capitol Cement Co., Inc. 200.0000 3,300.00 3,300.00 3069 K-Five Construction Corporation 222.0000 3,663.00 3,663.00 3505 Lorig Construction Company 225.0000 3,712.50 3,712.50 Z0008236 DRIL SHAFT/SOIL 36 265.000 FOOT 0346 Bartlett Bituminous Asphalt, L.L.C. 95.0000 25,175.00 25,175.00 0801 Capitol Cement Co., Inc. 400.0000 106,000.00 106,000.00 3069 K-Five Construction Corporation 250.0000 66,250.00 66,250.00 3505 Lorig Construction Company 250.0000 66,250.00 66,250.00 Z0008244 DRIL SHAFT/SOIL 44 91.500 FOOT 0346 Bartlett Bituminous Asphalt, L.L.C. 270.0000 24,705.00 24,705.00 0801 Capitol Cement Co., Inc. 500.0000 45,750.00 45,750.00 3069 K-Five Construction Corporation 472.0000 43,188.00 43,188.00 3505 Lorig Construction Company 325.0000 29,737.50 29,737.50 Z0013798 CONSTRUCTION LAYOUT 1.000 L SUM 0346 Bartlett Bituminous Asphalt, L.L.C. 125,000.0000 125,000.00 125,000.00 0801 Capitol Cement Co., Inc. 75,000.0000 75,000.00 75,000.00 3069 K-Five Construction Corporation 75,000.0000 75,000.00 75,000.00 3505 Lorig Construction Company 100,000.0000 100,000.00 100,000.00 Z0013825 CONTR LOW-STRENG MATL 61.000 CU YD 0346 Bartlett Bituminous Asphalt, L.L.C. 175.0000 10,675.00 10,675.00 0801 Capitol Cement Co., Inc. 75.0000 4,575.00 4,575.00 3069 K-Five Construction Corporation 166.0000 10,126.00 10,126.00 3505 Lorig Construction Company 175.0000 10,675.00 10,675.00 Z0017400 DRAIN UTIL STR ADJ 4.000 EACH 0346 Bartlett Bituminous Asphalt, L.L.C. 277.5400 1,110.16 1,110.16 0801 Capitol Cement Co., Inc. 450.0000 1,800.00 1,800.00 3069 K-Five Construction Corporation 445.0000 1,780.00 1,780.00 3505 Lorig Construction Company 425.0000 1,700.00 1,700.00 Z0018500 DRAINAGE STR CLEANED 53.000 EACH 0346 Bartlett Bituminous Asphalt, L.L.C. 233.0900 12,353.77 12,353.77 0801 Capitol Cement Co., Inc. 500.0000 26,500.00 26,500.00 3069 K-Five Construction Corporation 215.0000 11,395.00 11,395.00 3505 Lorig Construction Company 400.0000 21,200.00 21,200.00 Z0030070 IMP ATTEN SU NAR TL3 2.000 EACH 0346 Bartlett Bituminous Asphalt, L.L.C. 40,100.0000 80,200.00 80,200.00 0801 Capitol Cement Co., Inc. 34,400.0000 68,800.00 68,800.00 3069 K-Five Construction Corporation 37,800.0000 75,600.00 75,600.00 3505 Lorig Construction Company 36,000.0000 72,000.00 72,000.00 Z0030250 IMP ATTN TEMP NRD TL3 1.000 EACH 0346 Bartlett Bituminous Asphalt, L.L.C. 4,200.0000 4,200.00 4,200.00 0801 Capitol Cement Co., Inc. 3,600.0000 3,600.00 3,600.00 3069 K-Five Construction Corporation 4,000.0000 4,000.00 4,000.00 3505 Lorig Construction Company 4,000.0000 4,000.00 4,000.00 Z0048665 RR PROT LIABILITY INS 1.000 L SUM 0346 Bartlett Bituminous Asphalt, L.L.C. 9,500.0000 9,500.00 9,500.00 0801 Capitol Cement Co., Inc. 25,000.0000 25,000.00 25,000.00 3069 K-Five Construction Corporation 4,700.0000 4,700.00 4,700.00 3505 Lorig Construction Company 7,000.0000 7,000.00 7,000.00 Z0076600 TRAINEES 2,000.000 HOUR 0346 Bartlett Bituminous Asphalt, L.L.C. 0.8000 1,600.00 1,600.00 0801 Capitol Cement Co., Inc. 0.8000 1,600.00 1,600.00 3069 K-Five Construction Corporation 0.8000 1,600.00 1,600.00 3505 Lorig Construction Company 0.8000 1,600.00 1,600.00 20100110 TREE REMOV 6-15 522.000 UNIT 0346 Bartlett Bituminous Asphalt, L.L.C. 25.0000 13,050.00 13,050.00 0801 Capitol Cement Co., Inc. 10.2500 5,350.50 5,350.50 3069 K-Five Construction Corporation 11.0000 5,742.00 5,742.00 3505 Lorig Construction Company 14.0000 7,308.00 7,308.00 20100210 TREE REMOV OVER 15 484.000 UNIT 0346 Bartlett Bituminous Asphalt, L.L.C. 25.0000 12,100.00 12,100.00 0801 Capitol Cement Co., Inc. 12.2500 5,929.00 5,929.00 3069 K-Five Construction Corporation 13.5000 6,534.00 6,534.00 3505 Lorig Construction Company 17.0000 8,228.00 8,228.00 20101000 TEMPORARY FENCE 160.000 FOOT 0346 Bartlett Bituminous Asphalt, L.L.C. 3.0000 480.00 480.00 0801 Capitol Cement Co., Inc. 3.0000 480.00 480.00 3069 K-Five Construction Corporation 2.0000 320.00 320.00 3505 Lorig Construction Company 8.0000 1,280.00 1,280.00 20200100 EARTH EXCAVATION 14,023.000 CU YD 0346 Bartlett Bituminous Asphalt, L.L.C. 17.5000 245,402.50 245,402.50 0801 Capitol Cement Co., Inc. 33.0000 462,759.00 462,759.00 3069 K-Five Construction Corporation 22.0000 308,506.00 308,506.00 3505 Lorig Construction Company 19.0000 266,437.00 266,437.00 20201200 REM & DISP UNS MATL 4,843.000 CU YD 0346 Bartlett Bituminous Asphalt, L.L.C. 25.0000 121,075.00 121,075.00 0801 Capitol Cement Co., Inc. 35.0000 169,505.00 169,505.00 3069 K-Five Construction Corporation 25.0000 121,075.00 121,075.00 3505 Lorig Construction Company 19.0000 92,017.00 92,017.00 20700220 POROUS GRAN EMBANK 489.000 CU YD 0346 Bartlett Bituminous Asphalt, L.L.C. 41.8000 20,440.20 20,440.20 0801 Capitol Cement Co., Inc. 49.0000 23,961.00 23,961.00 3069 K-Five Construction Corporation 70.0000 34,230.00 34,230.00 3505 Lorig Construction Company 38.0000 18,582.00 18,582.00 20800150 TRENCH BACKFILL 111.000 CU YD 0346 Bartlett Bituminous Asphalt, L.L.C. 27.4400 3,045.84 3,045.84 0801 Capitol Cement Co., Inc. 50.0000 5,550.00 5,550.00 3069 K-Five Construction Corporation 11.0000 1,221.00 1,221.00 3505 Lorig Construction Company 11.0000 1,221.00 1,221.00 21001000 GEOTECH FAB F/GR STAB 5,006.000 SQ YD 0346 Bartlett Bituminous Asphalt, L.L.C. 1.2300 6,157.38 6,157.38 0801 Capitol Cement Co., Inc. 4.0000 20,024.00 20,024.00 3069 K-Five Construction Corporation 1.0000 5,006.00 5,006.00 3505 Lorig Construction Company 3.0000 15,018.00 15,018.00 21101615 TOPSOIL F & P 4 19,939.000 SQ YD 0346 Bartlett Bituminous Asphalt, L.L.C. 3.5000 69,786.50 69,786.50 0801 Capitol Cement Co., Inc. 3.3500 66,795.65 66,795.65 3069 K-Five Construction Corporation 2.5000 49,847.50 49,847.50 3505 Lorig Construction Company 4.0000 79,756.00 79,756.00 21301052 EXPLOR TRENCH 52 550.000 FOOT 0346 Bartlett Bituminous Asphalt, L.L.C. 35.0000 19,250.00 19,250.00 0801 Capitol Cement Co., Inc. 30.0000 16,500.00 16,500.00 3069 K-Five Construction Corporation 22.0000 12,100.00 12,100.00 3505 Lorig Construction Company 22.0000 12,100.00 12,100.00 25000210 SEEDING CL 2A 4.250 ACRE 0346 Bartlett Bituminous Asphalt, L.L.C. 1,434.3900 6,096.16 6,096.16 0801 Capitol Cement Co., Inc. 1,790.0000 7,607.50 7,607.50 3069 K-Five Construction Corporation 2,000.0000 8,500.00 8,500.00 3505 Lorig Construction Company 2,000.0000 8,500.00 8,500.00 25000400 NITROGEN FERT NUTR 371.000 POUND 0346 Bartlett Bituminous Asphalt, L.L.C. 1.7900 664.09 664.09 0801 Capitol Cement Co., Inc. 0.7500 278.25 278.25 3069 K-Five Construction Corporation 0.8000 296.80 296.80 3505 Lorig Construction Company 1.0000 371.00 371.00 25000500 PHOSPHORUS FERT NUTR 371.000 POUND 0346 Bartlett Bituminous Asphalt, L.L.C. 1.7900 664.09 664.09 0801 Capitol Cement Co., Inc. 0.7500 278.25 278.25 3069 K-Five Construction Corporation 0.8000 296.80 296.80 3505 Lorig Construction Company 1.0000 371.00 371.00 25000600 POTASSIUM FERT NUTR 371.000 POUND 0346 Bartlett Bituminous Asphalt, L.L.C. 1.7900 664.09 664.09 0801 Capitol Cement Co., Inc. 0.7500 278.25 278.25 3069 K-Five Construction Corporation 0.8000 296.80 296.80 3505 Lorig Construction Company 1.0000 371.00 371.00 25000750 MOWING 9.000 ACRE 0346 Bartlett Bituminous Asphalt, L.L.C. 59.7700 537.93 537.93 0801 Capitol Cement Co., Inc. 150.0000 1,350.00 1,350.00 3069 K-Five Construction Corporation 165.0000 1,485.00 1,485.00 3505 Lorig Construction Company 175.0000 1,575.00 1,575.00 25100630 EROSION CONTR BLANKET 19,939.000 SQ YD 0346 Bartlett Bituminous Asphalt, L.L.C. 1.3100 26,120.09 26,120.09 0801 Capitol Cement Co., Inc. 0.9000 17,945.10 17,945.10 3069 K-Five Construction Corporation 1.0000 19,939.00 19,939.00 3505 Lorig Construction Company 1.0000 19,939.00 19,939.00 28000250 TEMP EROS CONTR SEED 412.000 POUND 0346 Bartlett Bituminous Asphalt, L.L.C. 4.7800 1,969.36 1,969.36 0801 Capitol Cement Co., Inc. 5.3500 2,204.20 2,204.20 3069 K-Five Construction Corporation 6.0000 2,472.00 2,472.00 3505 Lorig Construction Company 1.0000 412.00 412.00 28000400 PERIMETER EROS BAR 4,156.000 FOOT 0346 Bartlett Bituminous Asphalt, L.L.C. 2.8700 11,927.72 11,927.72 0801 Capitol Cement Co., Inc. 3.0000 12,468.00 12,468.00 3069 K-Five Construction Corporation 2.7500 11,429.00 11,429.00 3505 Lorig Construction Company 2.5000 10,390.00 10,390.00 28000510 INLET FILTERS 40.000 EACH 0346 Bartlett Bituminous Asphalt, L.L.C. 239.0600 9,562.40 9,562.40 0801 Capitol Cement Co., Inc. 150.0000 6,000.00 6,000.00 3069 K-Five Construction Corporation 165.0000 6,600.00 6,600.00 3505 Lorig Construction Company 175.0000 7,000.00 7,000.00 31101400 SUB GRAN MAT B 6 4,311.000 SQ YD 0346 Bartlett Bituminous Asphalt, L.L.C. 7.5000 32,332.50 32,332.50 0801 Capitol Cement Co., Inc. 7.0000 30,177.00 30,177.00 3069 K-Five Construction Corporation 6.0000 25,866.00 25,866.00 3505 Lorig Construction Company 8.0000 34,488.00 34,488.00 31101860 SUB GRAN MAT B 24 4,138.000 SQ YD 0346 Bartlett Bituminous Asphalt, L.L.C. 14.7100 60,869.98 60,869.98 0801 Capitol Cement Co., Inc. 25.0000 103,450.00 103,450.00 3069 K-Five Construction Corporation 20.0000 82,760.00 82,760.00 3505 Lorig Construction Company 20.0000 82,760.00 82,760.00 31200100 STAB SUB-BASE 4 2,518.000 SQ YD 0346 Bartlett Bituminous Asphalt, L.L.C. 11.4300 28,780.74 28,780.74 0801 Capitol Cement Co., Inc. 17.2500 43,435.50 43,435.50 3069 K-Five Construction Corporation 15.0000 37,770.00 37,770.00 3505 Lorig Construction Company 18.0000 45,324.00 45,324.00 35300400 PCC BSE CSE 9 3,364.000 SQ YD 0346 Bartlett Bituminous Asphalt, L.L.C. 35.0000 117,740.00 117,740.00 0801 Capitol Cement Co., Inc. 46.0000 154,744.00 154,744.00 3069 K-Five Construction Corporation 34.0000 114,376.00 114,376.00 3505 Lorig Construction Company 50.0000 168,200.00 168,200.00 40600200 BIT MATLS PR CT 5.000 TON 0346 Bartlett Bituminous Asphalt, L.L.C. 200.0000 1,000.00 1,000.00 0801 Capitol Cement Co., Inc. 225.0000 1,125.00 1,125.00 3069 K-Five Construction Corporation 185.0000 925.00 925.00 3505 Lorig Construction Company 235.0000 1,175.00 1,175.00 42000521 PCC PVT 11 JOINTED 2,518.000 SQ YD 0346 Bartlett Bituminous Asphalt, L.L.C. 44.0000 110,792.00 110,792.00 0801 Capitol Cement Co., Inc. 65.0000 163,670.00 163,670.00 3069 K-Five Construction Corporation 52.0000 130,936.00 130,936.00 3505 Lorig Construction Company 45.0000 113,310.00 113,310.00 42001300 PROTECTIVE COAT 6,567.000 SQ YD 0346 Bartlett Bituminous Asphalt, L.L.C. 0.0100 65.67 65.67 0801 Capitol Cement Co., Inc. 2.0000 13,134.00 13,134.00 3069 K-Five Construction Corporation 0.1000 656.70 656.70 3505 Lorig Construction Company 0.4500 2,955.15 2,955.15 44000006 BIT SURF REM 1 1/2 2,223.000 SQ YD 0346 Bartlett Bituminous Asphalt, L.L.C. 3.5400 7,869.42 7,869.42 0801 Capitol Cement Co., Inc. 3.0000 6,669.00 6,669.00 3069 K-Five Construction Corporation 4.0000 8,892.00 8,892.00 3505 Lorig Construction Company 3.5000 7,780.50 7,780.50 44000009 BIT SURF REM 3 3,559.000 SQ YD 0346 Bartlett Bituminous Asphalt, L.L.C. 4.5000 16,015.50 16,015.50 0801 Capitol Cement Co., Inc. 4.2500 15,125.75 15,125.75 3069 K-Five Construction Corporation 5.0000 17,795.00 17,795.00 3505 Lorig Construction Company 4.5000 16,015.50 16,015.50 44000100 PAVEMENT REM 8,227.000 SQ YD 0346 Bartlett Bituminous Asphalt, L.L.C. 10.0000 82,270.00 82,270.00 0801 Capitol Cement Co., Inc. 25.0000 205,675.00 205,675.00 3069 K-Five Construction Corporation 10.0000 82,270.00 82,270.00 3505 Lorig Construction Company 13.0000 106,951.00 106,951.00 44000500 COMB CURB GUTTER REM 16,470.000 FOOT 0346 Bartlett Bituminous Asphalt, L.L.C. 2.7700 45,621.90 45,621.90 0801 Capitol Cement Co., Inc. 5.0000 82,350.00 82,350.00 3069 K-Five Construction Corporation 10.0000 164,700.00 164,700.00 3505 Lorig Construction Company 3.2500 53,527.50 53,527.50 44004250 PAVED SHLD REMOVAL 6,089.000 SQ YD 0346 Bartlett Bituminous Asphalt, L.L.C. 7.1500 43,536.35 43,536.35 0801 Capitol Cement Co., Inc. 12.0000 73,068.00 73,068.00 3069 K-Five Construction Corporation 9.0000 54,801.00 54,801.00 3505 Lorig Construction Company 11.0000 66,979.00 66,979.00 44201349 CL C PATCH T1 10 12.000 SQ YD 0346 Bartlett Bituminous Asphalt, L.L.C. 250.0000 3,000.00 3,000.00 0801 Capitol Cement Co., Inc. 175.0000 2,100.00 2,100.00 3069 K-Five Construction Corporation 160.0000 1,920.00 1,920.00 3505 Lorig Construction Company 100.0000 1,200.00 1,200.00 44201385 CL C PATCH T1 13 30.000 SQ YD 0346 Bartlett Bituminous Asphalt, L.L.C. 100.0000 3,000.00 3,000.00 0801 Capitol Cement Co., Inc. 175.0000 5,250.00 5,250.00 3069 K-Five Construction Corporation 160.0000 4,800.00 4,800.00 3505 Lorig Construction Company 100.0000 3,000.00 3,000.00 44201389 CL C PATCH T2 13 45.000 SQ YD 0346 Bartlett Bituminous Asphalt, L.L.C. 100.0000 4,500.00 4,500.00 0801 Capitol Cement Co., Inc. 175.0000 7,875.00 7,875.00 3069 K-Five Construction Corporation 159.0000 7,155.00 7,155.00 3505 Lorig Construction Company 105.0000 4,725.00 4,725.00 44213200 SAW CUTS 294.000 FOOT 0346 Bartlett Bituminous Asphalt, L.L.C. 3.0000 882.00 882.00 0801 Capitol Cement Co., Inc. 5.0000 1,470.00 1,470.00 3069 K-Five Construction Corporation 3.2500 955.50 955.50 3505 Lorig Construction Company 4.0000 1,176.00 1,176.00 44300200 STRIP REF CR CON TR 2,933.000 FOOT 0346 Bartlett Bituminous Asphalt, L.L.C. 1.2000 3,519.60 3,519.60 0801 Capitol Cement Co., Inc. 2.0000 5,866.00 5,866.00 3069 K-Five Construction Corporation 0.7500 2,199.75 2,199.75 3505 Lorig Construction Company 1.0000 2,933.00 2,933.00 48202400 BIT SHLD SUPER 6 214.000 SQ YD 0346 Bartlett Bituminous Asphalt, L.L.C. 14.0000 2,996.00 2,996.00 0801 Capitol Cement Co., Inc. 44.5000 9,523.00 9,523.00 3069 K-Five Construction Corporation 38.0000 8,132.00 8,132.00 3505 Lorig Construction Company 45.0000 9,630.00 9,630.00 50100300 REM EXIST STRUCT N1 1.000 EACH 0346 Bartlett Bituminous Asphalt, L.L.C. 120,000.0000 120,000.00 120,000.00 0801 Capitol Cement Co., Inc. 160,000.0000 160,000.00 160,000.00 3069 K-Five Construction Corporation 25,000.0000 25,000.00 25,000.00 3505 Lorig Construction Company 200,000.0000 200,000.00 200,000.00 50100400 REM EXIST STRUCT N2 1.000 EACH 0346 Bartlett Bituminous Asphalt, L.L.C. 135,000.0000 135,000.00 135,000.00 0801 Capitol Cement Co., Inc. 185,000.0000 185,000.00 185,000.00 3069 K-Five Construction Corporation 100,000.0000 100,000.00 100,000.00 3505 Lorig Construction Company 133,000.0000 133,000.00 133,000.00 50102400 CONC REM 292.000 CU YD 0346 Bartlett Bituminous Asphalt, L.L.C. 350.0000 102,200.00 102,200.00 0801 Capitol Cement Co., Inc. 250.0000 73,000.00 73,000.00 3069 K-Five Construction Corporation 360.0000 105,120.00 105,120.00 3505 Lorig Construction Company 375.0000 109,500.00 109,500.00 50200100 STRUCTURE EXCAVATION 971.000 CU YD 0346 Bartlett Bituminous Asphalt, L.L.C. 45.0000 43,695.00 43,695.00 0801 Capitol Cement Co., Inc. 40.0000 38,840.00 38,840.00 3069 K-Five Construction Corporation 30.0000 29,130.00 29,130.00 3505 Lorig Construction Company 25.0000 24,275.00 24,275.00 50300225 CONC STRUCT 341.000 CU YD 0346 Bartlett Bituminous Asphalt, L.L.C. 650.0000 221,650.00 221,650.00 0801 Capitol Cement Co., Inc. 500.0000 170,500.00 170,500.00 3069 K-Five Construction Corporation 650.0000 221,650.00 221,650.00 3505 Lorig Construction Company 650.0000 221,650.00 221,650.00 50300255 CONC SUP-STR 156.000 CU YD 0346 Bartlett Bituminous Asphalt, L.L.C. 675.0000 105,300.00 105,300.00 0801 Capitol Cement Co., Inc. 800.0000 124,800.00 124,800.00 3069 K-Five Construction Corporation 725.0000 113,100.00 113,100.00 3505 Lorig Construction Company 750.0000 117,000.00 117,000.00 50300300 PROTECTIVE COAT 661.000 SQ YD 0346 Bartlett Bituminous Asphalt, L.L.C. 1.2000 793.20 793.20 0801 Capitol Cement Co., Inc. 10.0000 6,610.00 6,610.00 3069 K-Five Construction Corporation 1.5000 991.50 991.50 3505 Lorig Construction Company 1.0000 661.00 661.00 50300510 RUSTICATION FINISH 5,766.000 SQ FT 0346 Bartlett Bituminous Asphalt, L.L.C. 3.0000 17,298.00 17,298.00 0801 Capitol Cement Co., Inc. 5.0000 28,830.00 28,830.00 3069 K-Five Construction Corporation 4.0000 23,064.00 23,064.00 3505 Lorig Construction Company 5.7000 32,866.20 32,866.20 50800105 REINFORCEMENT BARS 21,050.000 POUND 0346 Bartlett Bituminous Asphalt, L.L.C. 1.0800 22,734.00 22,734.00 0801 Capitol Cement Co., Inc. 1.0500 22,102.50 22,102.50 3069 K-Five Construction Corporation 1.0000 21,050.00 21,050.00 3505 Lorig Construction Company 0.8000 16,840.00 16,840.00 50800205 REINF BARS, EPOXY CTD 71,540.000 POUND 0346 Bartlett Bituminous Asphalt, L.L.C. 1.1500 82,271.00 82,271.00 0801 Capitol Cement Co., Inc. 1.2500 89,425.00 89,425.00 3069 K-Five Construction Corporation 1.2000 85,848.00 85,848.00 3505 Lorig Construction Company 0.9500 67,963.00 67,963.00 51205200 TEMP SHT PILING 6,735.000 SQ FT 0346 Bartlett Bituminous Asphalt, L.L.C. 0.0100 67.35 67.35 0801 Capitol Cement Co., Inc. 0.1000 673.50 673.50 3069 K-Five Construction Corporation 1.0000 6,735.00 6,735.00 3505 Lorig Construction Company 3.0000 20,205.00 20,205.00 550A0040 STORM SEW CL A 1 10 339.000 FOOT 0346 Bartlett Bituminous Asphalt, L.L.C. 34.0000 11,526.00 11,526.00 0801 Capitol Cement Co., Inc. 55.0000 18,645.00 18,645.00 3069 K-Five Construction Corporation 67.0000 22,713.00 22,713.00 3505 Lorig Construction Company 72.0000 24,408.00 24,408.00 550A0050 STORM SEW CL A 1 12 497.000 FOOT 0346 Bartlett Bituminous Asphalt, L.L.C. 40.0000 19,880.00 19,880.00 0801 Capitol Cement Co., Inc. 65.0000 32,305.00 32,305.00 3069 K-Five Construction Corporation 77.0000 38,269.00 38,269.00 3505 Lorig Construction Company 80.0000 39,760.00 39,760.00 55100300 STORM SEWER REM 8 345.000 FOOT 0346 Bartlett Bituminous Asphalt, L.L.C. 11.8700 4,095.15 4,095.15 0801 Capitol Cement Co., Inc. 12.0000 4,140.00 4,140.00 3069 K-Five Construction Corporation 16.0000 5,520.00 5,520.00 3505 Lorig Construction Company 18.0000 6,210.00 6,210.00 55100400 STORM SEWER REM 10 27.000 FOOT 0346 Bartlett Bituminous Asphalt, L.L.C. 11.5200 311.04 311.04 0801 Capitol Cement Co., Inc. 12.0000 324.00 324.00 3069 K-Five Construction Corporation 22.0000 594.00 594.00 3505 Lorig Construction Company 22.0000 594.00 594.00 55100500 STORM SEWER REM 12 39.000 FOOT 0346 Bartlett Bituminous Asphalt, L.L.C. 11.9100 464.49 464.49 0801 Capitol Cement Co., Inc. 12.0000 468.00 468.00 3069 K-Five Construction Corporation 20.0000 780.00 780.00 3505 Lorig Construction Company 22.0000 858.00 858.00 60107700 PIPE UNDERDRAINS 6 3,788.000 FOOT 0346 Bartlett Bituminous Asphalt, L.L.C. 10.0000 37,880.00 37,880.00 0801 Capitol Cement Co., Inc. 40.0000 151,520.00 151,520.00 3069 K-Five Construction Corporation 15.0000 56,820.00 56,820.00 3505 Lorig Construction Company 15.0000 56,820.00 56,820.00 60109582 P UNDR FOR STRUCT 6 120.000 FOOT 0346 Bartlett Bituminous Asphalt, L.L.C. 20.1000 2,412.00 2,412.00 0801 Capitol Cement Co., Inc. 23.0000 2,760.00 2,760.00 3069 K-Five Construction Corporation 25.0000 3,000.00 3,000.00 3505 Lorig Construction Company 28.0000 3,360.00 3,360.00 60109584 P UNDR FOR STRUCT 8 344.000 FOOT 0346 Bartlett Bituminous Asphalt, L.L.C. 21.8600 7,519.84 7,519.84 0801 Capitol Cement Co., Inc. 25.0000 8,600.00 8,600.00 3069 K-Five Construction Corporation 26.0000 8,944.00 8,944.00 3505 Lorig Construction Company 29.0000 9,976.00 9,976.00 60200105 CB TA 4 DIA T1F OL 1.000 EACH 0346 Bartlett Bituminous Asphalt, L.L.C. 1,550.0000 1,550.00 1,550.00 0801 Capitol Cement Co., Inc. 2,750.0000 2,750.00 2,750.00 3069 K-Five Construction Corporation 2,000.0000 2,000.00 2,000.00 3505 Lorig Construction Company 2,200.0000 2,200.00 2,200.00 60201310 CB TA 4 DIA T20F&G 7.000 EACH 0346 Bartlett Bituminous Asphalt, L.L.C. 1,600.0000 11,200.00 11,200.00 0801 Capitol Cement Co., Inc. 2,750.0000 19,250.00 19,250.00 3069 K-Five Construction Corporation 2,200.0000 15,400.00 15,400.00 3505 Lorig Construction Company 2,200.0000 15,400.00 15,400.00 60213800 RD CB 4 DIA T1F OL 12.000 EACH 0346 Bartlett Bituminous Asphalt, L.L.C. 1,500.0000 18,000.00 18,000.00 0801 Capitol Cement Co., Inc. 2,750.0000 33,000.00 33,000.00 3069 K-Five Construction Corporation 2,200.0000 26,400.00 26,400.00 3505 Lorig Construction Company 2,200.0000 26,400.00 26,400.00 60234200 INLETS TA T1F OL 18.000 EACH 0346 Bartlett Bituminous Asphalt, L.L.C. 930.0000 16,740.00 16,740.00 0801 Capitol Cement Co., Inc. 1,750.0000 31,500.00 31,500.00 3069 K-Five Construction Corporation 775.0000 13,950.00 13,950.00 3505 Lorig Construction Company 800.0000 14,400.00 14,400.00 60250300 CB ADJUST SPL 10.000 EACH 0346 Bartlett Bituminous Asphalt, L.L.C. 650.0000 6,500.00 6,500.00 0801 Capitol Cement Co., Inc. 575.0000 5,750.00 5,750.00 3069 K-Five Construction Corporation 665.0000 6,650.00 6,650.00 3505 Lorig Construction Company 700.0000 7,000.00 7,000.00 60250400 CB ADJ NEW T1F OL 8.000 EACH 0346 Bartlett Bituminous Asphalt, L.L.C. 500.0000 4,000.00 4,000.00 0801 Capitol Cement Co., Inc. 575.0000 4,600.00 4,600.00 3069 K-Five Construction Corporation 650.0000 5,200.00 5,200.00 3505 Lorig Construction Company 725.0000 5,800.00 5,800.00 60255700 MAN ADJ NEW T1F OL 3.000 EACH 0346 Bartlett Bituminous Asphalt, L.L.C. 500.0000 1,500.00 1,500.00 0801 Capitol Cement Co., Inc. 575.0000 1,725.00 1,725.00 3069 K-Five Construction Corporation 700.0000 2,100.00 2,100.00 3505 Lorig Construction Company 725.0000 2,175.00 2,175.00 60255800 MAN ADJ NEW T1F CL 15.000 EACH 0346 Bartlett Bituminous Asphalt, L.L.C. 500.0000 7,500.00 7,500.00 0801 Capitol Cement Co., Inc. 575.0000 8,625.00 8,625.00 3069 K-Five Construction Corporation 700.0000 10,500.00 10,500.00 3505 Lorig Construction Company 700.0000 10,500.00 10,500.00 60260300 INLETS ADJ NEW T1F OL 8.000 EACH 0346 Bartlett Bituminous Asphalt, L.L.C. 500.0000 4,000.00 4,000.00 0801 Capitol Cement Co., Inc. 575.0000 4,600.00 4,600.00 3069 K-Five Construction Corporation 600.0000 4,800.00 4,800.00 3505 Lorig Construction Company 575.0000 4,600.00 4,600.00 60500040 REMOV MANHOLES 1.000 EACH 0346 Bartlett Bituminous Asphalt, L.L.C. 450.0000 450.00 450.00 0801 Capitol Cement Co., Inc. 400.0000 400.00 400.00 3069 K-Five Construction Corporation 320.0000 320.00 320.00 3505 Lorig Construction Company 400.0000 400.00 400.00 60500050 REMOV CATCH BAS 6.000 EACH 0346 Bartlett Bituminous Asphalt, L.L.C. 350.0000 2,100.00 2,100.00 0801 Capitol Cement Co., Inc. 300.0000 1,800.00 1,800.00 3069 K-Five Construction Corporation 330.0000 1,980.00 1,980.00 3505 Lorig Construction Company 400.0000 2,400.00 2,400.00 60500060 REMOV INLETS 19.000 EACH 0346 Bartlett Bituminous Asphalt, L.L.C. 300.0000 5,700.00 5,700.00 0801 Capitol Cement Co., Inc. 200.0000 3,800.00 3,800.00 3069 K-Five Construction Corporation 90.0000 1,710.00 1,710.00 3505 Lorig Construction Company 100.0000 1,900.00 1,900.00 60500205 FILL CATCH BAS 1.000 EACH 0346 Bartlett Bituminous Asphalt, L.L.C. 375.0000 375.00 375.00 0801 Capitol Cement Co., Inc. 200.0000 200.00 200.00 3069 K-Five Construction Corporation 260.0000 260.00 260.00 3505 Lorig Construction Company 400.0000 400.00 400.00 60500305 FILL INLETS 10.000 EACH 0346 Bartlett Bituminous Asphalt, L.L.C. 350.0000 3,500.00 3,500.00 0801 Capitol Cement Co., Inc. 150.0000 1,500.00 1,500.00 3069 K-Five Construction Corporation 55.0000 550.00 550.00 3505 Lorig Construction Company 60.0000 600.00 600.00 60603800 COMB CC&G TB6.12 3,088.000 FOOT 0346 Bartlett Bituminous Asphalt, L.L.C. 10.8300 33,443.04 33,443.04 0801 Capitol Cement Co., Inc. 18.0000 55,584.00 55,584.00 3069 K-Five Construction Corporation 13.0000 40,144.00 40,144.00 3505 Lorig Construction Company 12.0000 37,056.00 37,056.00 63000000 SPBGR TY A 425.000 FOOT 0346 Bartlett Bituminous Asphalt, L.L.C. 17.9300 7,620.25 7,620.25 0801 Capitol Cement Co., Inc. 15.0000 6,375.00 6,375.00 3069 K-Five Construction Corporation 15.0000 6,375.00 6,375.00 3505 Lorig Construction Company 16.0000 6,800.00 6,800.00 63100045 TRAF BAR TERM T2 2.000 EACH 0346 Bartlett Bituminous Asphalt, L.L.C. 549.8500 1,099.70 1,099.70 0801 Capitol Cement Co., Inc. 460.0000 920.00 920.00 3069 K-Five Construction Corporation 475.0000 950.00 950.00 3505 Lorig Construction Company 1,000.0000 2,000.00 2,000.00 63100085 TRAF BAR TERM T6 1.000 EACH 0346 Bartlett Bituminous Asphalt, L.L.C. 1,912.5100 1,912.51 1,912.51 0801 Capitol Cement Co., Inc. 1,600.0000 1,600.00 1,600.00 3069 K-Five Construction Corporation 1,750.0000 1,750.00 1,750.00 3505 Lorig Construction Company 1,900.0000 1,900.00 1,900.00 63100167 TR BAR TRM T1 SPL TAN 3.000 EACH 0346 Bartlett Bituminous Asphalt, L.L.C. 2,749.2400 8,247.72 8,247.72 0801 Capitol Cement Co., Inc. 2,300.0000 6,900.00 6,900.00 3069 K-Five Construction Corporation 2,500.0000 7,500.00 7,500.00 3505 Lorig Construction Company 2,900.0000 8,700.00 8,700.00 63200310 GUARDRAIL REMOV 220.000 FOOT 0346 Bartlett Bituminous Asphalt, L.L.C. 2.6900 591.80 591.80 0801 Capitol Cement Co., Inc. 2.2500 495.00 495.00 3069 K-Five Construction Corporation 2.2500 495.00 495.00 3505 Lorig Construction Company 2.5000 550.00 550.00 63700600 CONC BAR SIN FACE SPL 1,018.000 FOOT 0346 Bartlett Bituminous Asphalt, L.L.C. 73.8800 75,209.84 75,209.84 0801 Capitol Cement Co., Inc. 80.0000 81,440.00 81,440.00 3069 K-Five Construction Corporation 75.0000 76,350.00 76,350.00 3505 Lorig Construction Company 55.0000 55,990.00 55,990.00 66400105 CH LK FENCE 4 3,303.000 FOOT 0346 Bartlett Bituminous Asphalt, L.L.C. 14.3400 47,365.02 47,365.02 0801 Capitol Cement Co., Inc. 12.0000 39,636.00 39,636.00 3069 K-Five Construction Corporation 13.0000 42,939.00 42,939.00 3505 Lorig Construction Company 14.0000 46,242.00 46,242.00 66400905 CH LK GATE 4X6 SINGL 2.000 EACH 0346 Bartlett Bituminous Asphalt, L.L.C. 812.8200 1,625.64 1,625.64 0801 Capitol Cement Co., Inc. 680.0000 1,360.00 1,360.00 3069 K-Five Construction Corporation 750.0000 1,500.00 1,500.00 3505 Lorig Construction Company 700.0000 1,400.00 1,400.00 66410200 CH LK FENCE SPL 1,170.000 FOOT 0346 Bartlett Bituminous Asphalt, L.L.C. 38.2500 44,752.50 44,752.50 0801 Capitol Cement Co., Inc. 32.0000 37,440.00 37,440.00 3069 K-Five Construction Corporation 35.0000 40,950.00 40,950.00 3505 Lorig Construction Company 35.0000 40,950.00 40,950.00 66410300 CH LK FENCE REMOV 3,467.000 FOOT 0346 Bartlett Bituminous Asphalt, L.L.C. 5.9800 20,732.66 20,732.66 0801 Capitol Cement Co., Inc. 5.0000 17,335.00 17,335.00 3069 K-Five Construction Corporation 5.0000 17,335.00 17,335.00 3505 Lorig Construction Company 6.0000 20,802.00 20,802.00 66410700 CH LK GATES SPL 2.000 EACH 0346 Bartlett Bituminous Asphalt, L.L.C. 8,128.1900 16,256.38 16,256.38 0801 Capitol Cement Co., Inc. 6,800.0000 13,600.00 13,600.00 3069 K-Five Construction Corporation 6,800.0000 13,600.00 13,600.00 3505 Lorig Construction Company 7,000.0000 14,000.00 14,000.00 66900200 NON SPL WASTE DISPOSL 170.000 CU YD 0346 Bartlett Bituminous Asphalt, L.L.C. 85.0000 14,450.00 14,450.00 0801 Capitol Cement Co., Inc. 110.0000 18,700.00 18,700.00 3069 K-Five Construction Corporation 122.0000 20,740.00 20,740.00 3505 Lorig Construction Company 60.0000 10,200.00 10,200.00 66900450 SPL WASTE PLNS/REPORT 1.000 L SUM 0346 Bartlett Bituminous Asphalt, L.L.C. 5,500.0000 5,500.00 5,500.00 0801 Capitol Cement Co., Inc. 6,000.0000 6,000.00 6,000.00 3069 K-Five Construction Corporation 6,600.0000 6,600.00 6,600.00 3505 Lorig Construction Company 3,000.0000 3,000.00 3,000.00 66900530 SOIL DISPOSAL ANALY 1.000 EACH 0346 Bartlett Bituminous Asphalt, L.L.C. 1,200.0000 1,200.00 1,200.00 0801 Capitol Cement Co., Inc. 1,200.0000 1,200.00 1,200.00 3069 K-Five Construction Corporation 1,330.0000 1,330.00 1,330.00 3505 Lorig Construction Company 2,200.0000 2,200.00 2,200.00 67000600 ENGR FIELD LAB 18.000 CAL MO 0346 Bartlett Bituminous Asphalt, L.L.C. 600.0000 10,800.00 10,800.00 0801 Capitol Cement Co., Inc. 2,000.0000 36,000.00 36,000.00 3069 K-Five Construction Corporation 250.0000 4,500.00 4,500.00 3505 Lorig Construction Company 600.0000 10,800.00 10,800.00 67100100 MOBILIZATION 1.000 L SUM 0346 Bartlett Bituminous Asphalt, L.L.C. 275,000.0000 275,000.00 275,000.00 0801 Capitol Cement Co., Inc. 350,000.0000 350,000.00 350,000.00 3069 K-Five Construction Corporation 59,000.0000 59,000.00 59,000.00 3505 Lorig Construction Company 220,000.0000 220,000.00 220,000.00 70101800 TRAF CONT & PROT SPL 1.000 L SUM 0346 Bartlett Bituminous Asphalt, L.L.C. 25,000.0000 25,000.00 25,000.00 0801 Capitol Cement Co., Inc. 100,000.0000 100,000.00 100,000.00 3069 K-Five Construction Corporation 24,000.0000 24,000.00 24,000.00 3505 Lorig Construction Company 150,000.0000 150,000.00 150,000.00 70300210 TEMP PVT MK LTR & SYM 226.000 SQ FT 0346 Bartlett Bituminous Asphalt, L.L.C. 1.2000 271.20 271.20 0801 Capitol Cement Co., Inc. 1.0000 226.00 226.00 3069 K-Five Construction Corporation 1.0000 226.00 226.00 3505 Lorig Construction Company 1.0000 226.00 226.00 70300220 TEMP PVT MK LINE 4 10,063.000 FOOT 0346 Bartlett Bituminous Asphalt, L.L.C. 0.2200 2,213.86 2,213.86 0801 Capitol Cement Co., Inc. 0.1800 1,811.34 1,811.34 3069 K-Five Construction Corporation 0.1800 1,811.34 1,811.34 3505 Lorig Construction Company 0.2500 2,515.75 2,515.75 70300240 TEMP PVT MK LINE 6 3,388.000 FOOT 0346 Bartlett Bituminous Asphalt, L.L.C. 0.3200 1,084.16 1,084.16 0801 Capitol Cement Co., Inc. 0.2700 914.76 914.76 3069 K-Five Construction Corporation 0.3000 1,016.40 1,016.40 3505 Lorig Construction Company 0.3000 1,016.40 1,016.40 70300250 TEMP PVT MK LINE 8 664.000 FOOT 0346 Bartlett Bituminous Asphalt, L.L.C. 0.4800 318.72 318.72 0801 Capitol Cement Co., Inc. 0.4000 265.60 265.60 3069 K-Five Construction Corporation 0.4000 265.60 265.60 3505 Lorig Construction Company 0.5000 332.00 332.00 70300260 TEMP PVT MK LINE 12 136.000 FOOT 0346 Bartlett Bituminous Asphalt, L.L.C. 1.2000 163.20 163.20 0801 Capitol Cement Co., Inc. 0.5500 74.80 74.80 3069 K-Five Construction Corporation 1.0000 136.00 136.00 3505 Lorig Construction Company 2.2500 306.00 306.00 70300280 TEMP PVT MK LINE 24 76.000 FOOT 0346 Bartlett Bituminous Asphalt, L.L.C. 1.2000 91.20 91.20 0801 Capitol Cement Co., Inc. 1.0000 76.00 76.00 3069 K-Five Construction Corporation 1.0000 76.00 76.00 3505 Lorig Construction Company 1.0000 76.00 76.00 70301000 WORK ZONE PAVT MK REM 12,312.000 SQ FT 0346 Bartlett Bituminous Asphalt, L.L.C. 1.2000 14,774.40 14,774.40 0801 Capitol Cement Co., Inc. 1.0000 12,312.00 12,312.00 3069 K-Five Construction Corporation 1.0000 12,312.00 12,312.00 3505 Lorig Construction Company 1.0000 12,312.00 12,312.00 70400100 TEMP CONC BARRIER 5,420.000 FOOT 0346 Bartlett Bituminous Asphalt, L.L.C. 2.8600 15,501.20 15,501.20 0801 Capitol Cement Co., Inc. 26.0000 140,920.00 140,920.00 3069 K-Five Construction Corporation 14.0000 75,880.00 75,880.00 3505 Lorig Construction Company 22.0000 119,240.00 119,240.00 72000200 SIGN PANEL T2 24.000 SQ FT 0346 Bartlett Bituminous Asphalt, L.L.C. 181.6900 4,360.56 4,360.56 0801 Capitol Cement Co., Inc. 26.5000 636.00 636.00 3069 K-Five Construction Corporation 29.0000 696.00 696.00 3505 Lorig Construction Company 28.0000 672.00 672.00 72000300 SIGN PANEL T3 113.000 SQ FT 0346 Bartlett Bituminous Asphalt, L.L.C. 59.7700 6,754.01 6,754.01 0801 Capitol Cement Co., Inc. 21.0000 2,373.00 2,373.00 3069 K-Five Construction Corporation 23.0000 2,599.00 2,599.00 3505 Lorig Construction Company 22.0000 2,486.00 2,486.00 72300100 INSTALL EX SIGN PANEL 105.000 SQ FT 0346 Bartlett Bituminous Asphalt, L.L.C. 32.2700 3,388.35 3,388.35 0801 Capitol Cement Co., Inc. 13.0000 1,365.00 1,365.00 3069 K-Five Construction Corporation 13.0000 1,365.00 1,365.00 3505 Lorig Construction Company 17.0000 1,785.00 1,785.00 72400200 REMOV SIN PAN ASSY TB 5.000 EACH 0346 Bartlett Bituminous Asphalt, L.L.C. 537.8900 2,689.45 2,689.45 0801 Capitol Cement Co., Inc. 175.0000 875.00 875.00 3069 K-Five Construction Corporation 190.0000 950.00 950.00 3505 Lorig Construction Company 200.0000 1,000.00 1,000.00 72400320 REMOV SIGN PANEL T2 12.000 SQ FT 0346 Bartlett Bituminous Asphalt, L.L.C. 109.9700 1,319.64 1,319.64 0801 Capitol Cement Co., Inc. 10.0000 120.00 120.00 3069 K-Five Construction Corporation 11.0000 132.00 132.00 3505 Lorig Construction Company 12.0000 144.00 144.00 72400500 RELOC SIN PAN ASSY TA 18.000 EACH 0346 Bartlett Bituminous Asphalt, L.L.C. 896.4900 16,136.82 16,136.82 0801 Capitol Cement Co., Inc. 300.0000 5,400.00 5,400.00 3069 K-Five Construction Corporation 310.0000 5,580.00 5,580.00 3505 Lorig Construction Company 325.0000 5,850.00 5,850.00 72400600 RELOC SIN PAN ASSY TB 10.000 EACH 0346 Bartlett Bituminous Asphalt, L.L.C. 896.4900 8,964.90 8,964.90 0801 Capitol Cement Co., Inc. 310.0000 3,100.00 3,100.00 3069 K-Five Construction Corporation 330.0000 3,300.00 3,300.00 3505 Lorig Construction Company 325.0000 3,250.00 3,250.00 72800100 TELES STL SIN SUPPORT 42.000 FOOT 0346 Bartlett Bituminous Asphalt, L.L.C. 71.7200 3,012.24 3,012.24 0801 Capitol Cement Co., Inc. 15.0000 630.00 630.00 3069 K-Five Construction Corporation 16.0000 672.00 672.00 3505 Lorig Construction Company 18.0000 756.00 756.00 72900200 METAL POST TY B 52.000 FOOT 0346 Bartlett Bituminous Asphalt, L.L.C. 71.7200 3,729.44 3,729.44 0801 Capitol Cement Co., Inc. 10.0000 520.00 520.00 3069 K-Five Construction Corporation 11.0000 572.00 572.00 3505 Lorig Construction Company 11.0000 572.00 572.00 73000100 WOOD SIN SUPPORT 463.000 FOOT 0346 Bartlett Bituminous Asphalt, L.L.C. 98.0200 45,383.26 45,383.26 0801 Capitol Cement Co., Inc. 15.2500 7,060.75 7,060.75 3069 K-Five Construction Corporation 15.0000 6,945.00 6,945.00 3505 Lorig Construction Company 18.0000 8,334.00 8,334.00 73100100 BASE TEL STL SIN SUPP 3.000 EACH 0346 Bartlett Bituminous Asphalt, L.L.C. 896.4900 2,689.47 2,689.47 0801 Capitol Cement Co., Inc. 150.0000 450.00 450.00 3069 K-Five Construction Corporation 150.0000 450.00 450.00 3505 Lorig Construction Company 175.0000 525.00 525.00 73200100 CONC FDN-WOOD SN SUPP 4.000 EACH 0346 Bartlett Bituminous Asphalt, L.L.C. 717.1900 2,868.76 2,868.76 0801 Capitol Cement Co., Inc. 215.0000 860.00 860.00 3069 K-Five Construction Corporation 220.0000 880.00 880.00 3505 Lorig Construction Company 225.0000 900.00 900.00 73302210 OSS CANT 3CA 3-0X7-0 37.500 FOOT 0346 Bartlett Bituminous Asphalt, L.L.C. 2,151.5800 80,684.25 80,684.25 0801 Capitol Cement Co., Inc. 650.0000 24,375.00 24,375.00 3069 K-Five Construction Corporation 700.0000 26,250.00 26,250.00 3505 Lorig Construction Company 700.0000 26,250.00 26,250.00 73400200 DRILL SHAFT CONC FDN 13.800 CU YD 0346 Bartlett Bituminous Asphalt, L.L.C. 2,390.6400 32,990.83 32,990.83 0801 Capitol Cement Co., Inc. 1,225.0000 16,905.00 16,905.00 3069 K-Five Construction Corporation 1,300.0000 17,940.00 17,940.00 3505 Lorig Construction Company 1,300.0000 17,940.00 17,940.00 73600200 REMOV OH SIN STR-CANT 1.000 EACH 0346 Bartlett Bituminous Asphalt, L.L.C. 10,000.0000 10,000.00 10,000.00 0801 Capitol Cement Co., Inc. 4,212.0000 4,212.00 4,212.00 3069 K-Five Construction Corporation 4,600.0000 4,600.00 4,600.00 3505 Lorig Construction Company 5,000.0000 5,000.00 5,000.00 73700300 REM CONC FDN-OVHD 1.000 EACH 0346 Bartlett Bituminous Asphalt, L.L.C. 3,000.0000 3,000.00 3,000.00 0801 Capitol Cement Co., Inc. 3,800.0000 3,800.00 3,800.00 3069 K-Five Construction Corporation 4,000.0000 4,000.00 4,000.00 3505 Lorig Construction Company 4,000.0000 4,000.00 4,000.00 78000100 THPL PVT MK LTR & SYM 126.000 SQ FT 0346 Bartlett Bituminous Asphalt, L.L.C. 2.8700 361.62 361.62 0801 Capitol Cement Co., Inc. 2.4000 302.40 302.40 3069 K-Five Construction Corporation 2.5000 315.00 315.00 3505 Lorig Construction Company 9.0000 1,134.00 1,134.00 78000200 THPL PVT MK LINE 4 2,079.000 FOOT 0346 Bartlett Bituminous Asphalt, L.L.C. 0.5000 1,039.50 1,039.50 0801 Capitol Cement Co., Inc. 0.4200 873.18 873.18 3069 K-Five Construction Corporation 0.4200 873.18 873.18 3505 Lorig Construction Company 0.4500 935.55 935.55 78000400 THPL PVT MK LINE 6 484.000 FOOT 0346 Bartlett Bituminous Asphalt, L.L.C. 0.7700 372.68 372.68 0801 Capitol Cement Co., Inc. 0.6400 309.76 309.76 3069 K-Five Construction Corporation 0.6500 314.60 314.60 3505 Lorig Construction Company 0.7000 338.80 338.80 78000500 THPL PVT MK LINE 8 664.000 FOOT 0346 Bartlett Bituminous Asphalt, L.L.C. 1.0200 677.28 677.28 0801 Capitol Cement Co., Inc. 0.8500 564.40 564.40 3069 K-Five Construction Corporation 0.8500 564.40 564.40 3505 Lorig Construction Company 2.5000 1,660.00 1,660.00 78000600 THPL PVT MK LINE 12 136.000 FOOT 0346 Bartlett Bituminous Asphalt, L.L.C. 2.8700 390.32 390.32 0801 Capitol Cement Co., Inc. 2.4000 326.40 326.40 3069 K-Five Construction Corporation 2.5000 340.00 340.00 3505 Lorig Construction Company 4.5000 612.00 612.00 78000650 THPL PVT MK LINE 24 76.000 FOOT 0346 Bartlett Bituminous Asphalt, L.L.C. 5.3800 408.88 408.88 0801 Capitol Cement Co., Inc. 4.5000 342.00 342.00 3069 K-Five Construction Corporation 4.5000 342.00 342.00 3505 Lorig Construction Company 9.0000 684.00 684.00 78003110 PREF PL PM TB LINE 4 2,833.000 FOOT 0346 Bartlett Bituminous Asphalt, L.L.C. 3.2900 9,320.57 9,320.57 0801 Capitol Cement Co., Inc. 2.7500 7,790.75 7,790.75 3069 K-Five Construction Corporation 2.7500 7,790.75 7,790.75 3505 Lorig Construction Company 4.5000 12,748.50 12,748.50 78008200 POLYUREA PM T1 LTR-SY 222.000 SQ FT 0346 Bartlett Bituminous Asphalt, L.L.C. 7.6500 1,698.30 1,698.30 0801 Capitol Cement Co., Inc. 6.4000 1,420.80 1,420.80 3069 K-Five Construction Corporation 6.5000 1,443.00 1,443.00 3505 Lorig Construction Company 6.5000 1,443.00 1,443.00 78008210 POLYUREA PM T1 LN 4 16,751.000 FOOT 0346 Bartlett Bituminous Asphalt, L.L.C. 0.9400 15,745.94 15,745.94 0801 Capitol Cement Co., Inc. 0.7900 13,233.29 13,233.29 3069 K-Five Construction Corporation 0.8000 13,400.80 13,400.80 3505 Lorig Construction Company 0.7000 11,725.70 11,725.70 78008220 POLYUREA PM T1 LN 5 8,586.000 FOOT 0346 Bartlett Bituminous Asphalt, L.L.C. 1.1700 10,045.62 10,045.62 0801 Capitol Cement Co., Inc. 0.9800 8,414.28 8,414.28 3069 K-Five Construction Corporation 1.0000 8,586.00 8,586.00 3505 Lorig Construction Company 0.8000 6,868.80 6,868.80 78008240 POLYUREA PM T1 LN 8 8,088.000 FOOT 0346 Bartlett Bituminous Asphalt, L.L.C. 1.7900 14,477.52 14,477.52 0801 Capitol Cement Co., Inc. 1.5000 12,132.00 12,132.00 3069 K-Five Construction Corporation 1.5000 12,132.00 12,132.00 3505 Lorig Construction Company 1.8000 14,558.40 14,558.40 78008250 POLYUREA PM T1 LN 12 833.000 FOOT 0346 Bartlett Bituminous Asphalt, L.L.C. 6.1000 5,081.30 5,081.30 0801 Capitol Cement Co., Inc. 5.1000 4,248.30 4,248.30 3069 K-Five Construction Corporation 5.2500 4,373.25 4,373.25 3505 Lorig Construction Company 3.2500 2,707.25 2,707.25 78100100 RAISED REFL PAVT MKR 20.000 EACH 0346 Bartlett Bituminous Asphalt, L.L.C. 85.0000 1,700.00 1,700.00 0801 Capitol Cement Co., Inc. 72.0000 1,440.00 1,440.00 3069 K-Five Construction Corporation 72.0000 1,440.00 1,440.00 3505 Lorig Construction Company 100.0000 2,000.00 2,000.00 78200100 MONODIR PRIS BAR REFL 108.000 EACH 0346 Bartlett Bituminous Asphalt, L.L.C. 8.3700 903.96 903.96 0801 Capitol Cement Co., Inc. 7.0000 756.00 756.00 3069 K-Five Construction Corporation 7.0000 756.00 756.00 3505 Lorig Construction Company 8.0000 864.00 864.00 78200410 GUARDRAIL MKR TYPE A 15.000 EACH 0346 Bartlett Bituminous Asphalt, L.L.C. 16.7300 250.95 250.95 0801 Capitol Cement Co., Inc. 14.0000 210.00 210.00 3069 K-Five Construction Corporation 10.0000 150.00 150.00 3505 Lorig Construction Company 15.0000 225.00 225.00 78201000 TERMINAL MARKER - DA 3.000 EACH 0346 Bartlett Bituminous Asphalt, L.L.C. 59.7700 179.31 179.31 0801 Capitol Cement Co., Inc. 50.0000 150.00 150.00 3069 K-Five Construction Corporation 40.0000 120.00 120.00 3505 Lorig Construction Company 55.0000 165.00 165.00 78300100 PAVT MARKING REMOVAL 6,430.000 SQ FT 0346 Bartlett Bituminous Asphalt, L.L.C. 1.2000 7,716.00 7,716.00 0801 Capitol Cement Co., Inc. 1.0000 6,430.00 6,430.00 3069 K-Five Construction Corporation 1.0000 6,430.00 6,430.00 3505 Lorig Construction Company 1.1000 7,073.00 7,073.00 80700140 GROUND ROD 5/8 X 10 52.000 EACH 0346 Bartlett Bituminous Asphalt, L.L.C. 130.2900 6,775.08 6,775.08 0801 Capitol Cement Co., Inc. 109.0000 5,668.00 5,668.00 3069 K-Five Construction Corporation 110.0000 5,720.00 5,720.00 3505 Lorig Construction Company 125.0000 6,500.00 6,500.00 81000600 CON T 2 GALVS 414.000 FOOT 0346 Bartlett Bituminous Asphalt, L.L.C. 11.7100 4,847.94 4,847.94 0801 Capitol Cement Co., Inc. 9.8000 4,057.20 4,057.20 3069 K-Five Construction Corporation 10.0000 4,140.00 4,140.00 3505 Lorig Construction Company 10.0000 4,140.00 4,140.00 81000800 CON T 3 GALVS 68.000 FOOT 0346 Bartlett Bituminous Asphalt, L.L.C. 17.2100 1,170.28 1,170.28 0801 Capitol Cement Co., Inc. 14.4000 979.20 979.20 3069 K-Five Construction Corporation 15.0000 1,020.00 1,020.00 3505 Lorig Construction Company 15.0000 1,020.00 1,020.00 81012800 CON T 3 PVC 7.000 FOOT 0346 Bartlett Bituminous Asphalt, L.L.C. 12.7900 89.53 89.53 0801 Capitol Cement Co., Inc. 10.7000 74.90 74.90 3069 K-Five Construction Corporation 11.0000 77.00 77.00 3505 Lorig Construction Company 11.0000 77.00 77.00 81018900 CON P 4 GALVS 100.000 FOOT 0346 Bartlett Bituminous Asphalt, L.L.C. 24.3800 2,438.00 2,438.00 0801 Capitol Cement Co., Inc. 20.4000 2,040.00 2,040.00 3069 K-Five Construction Corporation 22.0000 2,200.00 2,200.00 3505 Lorig Construction Company 22.0000 2,200.00 2,200.00 81400200 HD HANDHOLE 3.000 EACH 0346 Bartlett Bituminous Asphalt, L.L.C. 2,600.0000 7,800.00 7,800.00 0801 Capitol Cement Co., Inc. 2,599.0000 7,797.00 7,797.00 3069 K-Five Construction Corporation 2,800.0000 8,400.00 8,400.00 3505 Lorig Construction Company 2,800.0000 8,400.00 8,400.00 81400205 HD HANDHOLE SPL 2.000 EACH 0346 Bartlett Bituminous Asphalt, L.L.C. 3,300.0000 6,600.00 6,600.00 0801 Capitol Cement Co., Inc. 3,264.0000 6,528.00 6,528.00 3069 K-Five Construction Corporation 3,600.0000 7,200.00 7,200.00 3505 Lorig Construction Company 3,400.0000 6,800.00 6,800.00 81500200 TR & BKFIL F ELECT WK 717.000 FOOT 0346 Bartlett Bituminous Asphalt, L.L.C. 3.5000 2,509.50 2,509.50 0801 Capitol Cement Co., Inc. 0.4000 286.80 286.80 3069 K-Five Construction Corporation 0.4000 286.80 286.80 3505 Lorig Construction Company 0.4500 322.65 322.65 83700250 LT TOWER FDN 44D 402.000 FOOT 0346 Bartlett Bituminous Asphalt, L.L.C. 500.0000 201,000.00 201,000.00 0801 Capitol Cement Co., Inc. 338.2000 135,956.40 135,956.40 3069 K-Five Construction Corporation 365.0000 146,730.00 146,730.00 3505 Lorig Construction Company 375.0000 150,750.00 150,750.00