|

IL
Route 59 Reconstruction Project
Project Photos
2010
Photos
April 2010
click on photo to enlarge
|
|
|
Both directions of IL 59 traffic use the NB pavement constructed in September 2009 while the new pavement for the southbound IL 59 is constructed-North view. |
|
|
|
The SB IL 59 approach roadway north of the DuPage River is constructed-North view |
|
|
|
The pavement for SB IL 59 was constructed over an 18 hour period ending at the DuPage River Bridge-South view |
|
|
|
|
Both directions of IL 59 traffic use the NB pavement constructed in September 2009 while the new pavement for the southbound IL 59 is constructed-South view |
|
|
|
Dowel bar assemblies are secured at locations of pavement joints prior to placing concrete-North view |
|
|
|
Dump trucks deliver concrete to the paving train-South view |
|
|
|
|
New pavement completed for the SB IL 59 traffic lanes-South view |
|
|
|
Crane mats help trucks move into position for delivery of concrete-North view |
|
|
|
Truck prepares to dump concrete onto belt of the paving placer/spreader |
|
|
|
|
The texture/cure machine follows the slipform paver-North view |
|
|
|
A white spray cure is applied to the concrete after diagonal tines-North view |
|
|
|
The slipform paver finishes the new concrete pavement for SB IL 59-Northwest view |
|
|
|
|
The texture/cure machine applies an Astroturf drag, diagonal tining, and white spray cure to the new concrete pavement-West view |
|
|
|
Lighting mounted on the paving equipment allowed work to start at 8pm and continue through the night-South view |
|
|
|
Placer/spreader accepts concrete from end dump trucks, conveys material to the grade and the spreads the material to the desired width and strikes it off-Southeast view |
|
|
|
|
Placer/spreader accepts concrete from end dump trucks, conveys material to the grade and the spreads the material to the desired width and strikes it off-Southeast view |
|
|
March 2010
click on photo to enlarge
|
|
|
Bolted splice connections between girder sections will be completed over SB I-55- Southeast view |
|
|
|
All girder sections in place over NB I-55-South view |
|
|
|
Bridge girders completed over I-55-Northwest view |
|
|
|
|
Work platforms are place outside of the exterior girders-Southeast view |
|
|
|
Girder sections set over NB I-55-Northeast view |
|
|
|
All girder sections in place over NB I-55-Southeast view |
|
|
|
|
Girder sections will be erected over SB I-55 and connected to the in-place girders-South view |
|
|
|
Girder sections cantilever over SB I-55-West view |
|
|
|
Girder sections set over NB I-55-Southeast view |
|
|
|
|
Formwork for the reinforced concrete bridge deck is supported by the bridge girders |
|
|
|
Protective shielding is placed between the girders for safety. Southeast view |
|
|
|
Top view of a bolted splice connection |
|
|
|
|
Dual Manitowoc M-80 cranes prepare to lift 61 ton twin girder sections of new IL 59 bridge over NB I-55. Work is done overnight during low traffic volume hours |
|
|
|
Dual Manitowoc M-80 crane lifting 213ft. long twin girder section of new IL 59 bridge over NB I-55. State Police assisted with full closure of NB I-55 traffic while the girder sections were lifted into place-North view |
|
|
|
Dual Manitowoc M-80 crane lifting 213ft. long twin girder section of new IL 59 bridge over NB I-55 |
|
|
|
|
Manitowoc M-80 crane swings 12.5 ton girder section into position over SB I-55. Work is done overnight during low traffic volume hours-South view |
|
|
|
Dual Manitowoc M-80 cranes set 61 ton twin girder sections of new IL 59 bridge over NB I-55-North view |
|
|
|
Manitowoc M-80 crane positions 12.5 ton girder section into place to make connection over SB I-55-South view |
|
|
|
|
Crew installs bolt for splice connection over SB I-55-South view |
|
|
|
Workers install formwork for the reinforced concrete bridge deck. Southeast view |
|
|
|
Individual bridge girders are connected together with cross frames- Northwest view |
|
|
|
|
Cross-frames provide stability to the steel girder bridge-Northwest view |
|
|
|