Illinois Department of Transportation, Ann L. Schneider, Acting Secretary
Loading
Patrick J. Quinn, Governor
Traveling PublicMapsProjectsRoad ClosuresNewsDoing BusinessLetting & BiddingCareers@IDOTGeneral Info

IL Route 59 Reconstruction Project

Project Photos

2010 Photos

April 2010

click on photo to enlarge

Both directions of IL 59 traffic use the NB pavement constructed in September 2009 while the new pavement for the southbound IL 59 is constructed-North view.

The SB IL 59 approach roadway north of the DuPage River is constructed-North view

The pavement for SB IL 59 was constructed over an 18 hour period ending at the DuPage River Bridge-South view

Both directions of IL 59 traffic use the NB pavement constructed in September 2009 while the new pavement for the southbound IL 59 is constructed-South view

Dowel bar assemblies are secured at locations of pavement joints prior to placing concrete-North view

Dump trucks deliver concrete to the paving train-South view

New pavement completed for the SB IL 59 traffic lanes-South view

Crane mats help trucks move into position for delivery of concrete-North view

Truck prepares to dump concrete onto belt of the paving placer/spreader

The texture/cure machine follows the slipform paver-North view

A white spray cure is applied to the concrete after diagonal tines-North view

The slipform paver finishes the new concrete pavement for SB IL 59-Northwest view

The texture/cure machine applies an Astroturf drag, diagonal tining, and white spray cure to the new concrete pavement-West view

Lighting mounted on the paving equipment allowed work to start at 8pm and continue through the night-South view

Placer/spreader accepts concrete from end dump trucks, conveys material to the grade and the spreads the material to the desired width and strikes it off-Southeast view

Placer/spreader accepts concrete from end dump trucks, conveys material to the grade and the spreads the material to the desired width and strikes it off-Southeast view

 

March 2010

click on photo to enlarge

Bolted splice connections between girder sections will be completed over SB I-55- Southeast view

All girder sections in place over NB I-55-South view

Bridge girders completed over I-55-Northwest view

Work platforms are place outside of the exterior girders-Southeast view

Girder sections set over NB I-55-Northeast view

All girder sections in place over NB I-55-Southeast view

Girder sections will be erected over SB I-55 and connected to the in-place girders-South view

Girder sections cantilever over SB I-55-West view

Girder sections set over NB I-55-Southeast view

Formwork for the reinforced concrete bridge deck is supported by the bridge girders

Protective shielding is placed between the girders for safety. Southeast view

Top view of a bolted splice connection

Dual Manitowoc M-80 cranes prepare to lift 61 ton twin girder sections of new IL 59 bridge over NB I-55. Work is done overnight during low traffic volume hours

Dual Manitowoc M-80 crane lifting 213ft. long twin girder section of new IL 59 bridge over NB I-55. State Police assisted with full closure of NB I-55 traffic while the girder sections were lifted into place-North view

Dual Manitowoc M-80 crane lifting 213ft. long twin girder section of new IL 59 bridge over NB I-55

Manitowoc M-80 crane swings 12.5 ton girder section into position over SB I-55. Work is done overnight during low traffic volume hours-South view

Dual Manitowoc M-80 cranes set 61 ton twin girder sections of new IL 59 bridge over NB I-55-North view

Manitowoc M-80 crane positions 12.5 ton girder section into place to make connection over SB I-55-South view

Crew installs bolt for splice connection over SB I-55-South view

Workers install formwork for the reinforced concrete bridge deck. Southeast view

Individual bridge girders are connected together with cross frames- Northwest view

Cross-frames provide stability to the steel girder bridge-Northwest view

 

IDOT Privacy Statement | Illinois Privacy Information | Kids Privacy | Web Accessibility  | FOIA