History
This project
started in response to a feasibility study that was initiated by
the City of Collinsville that was completed in July of 2004. A
feasibility study is conducted to determine if a highway
improvement warrants further study. This initial feasibility
study reviewed existing and planned land uses, existing and
projected traffic volumes, and the network transportation as a
whole. Results of this study and its public involvement effort
concluded that the IL Route 159 corridor warranted additional
study.
If you would
like to review the completed IL Route 159 Feasibility Study,
please
click here. (35MB)
In August 2005,
the Illinois Department of Transportation began a Location and
Environment Study (Phase I). This phase of the project involved
evaluation of potential alternatives to address congestion and
safety issues within the corridor. Potential alternatives were
evaluated based on environmental impacts, residential and
commercial impacts, improvements to the transportation system,
and feedback from the public. There was extensive input from the
public during this phase through Community Advisory Group
meetings, stake holder meetings, and Public Involvement
Meetings.
The IL Route
159 Location and Environment Study (Phase I) was completed in
January of 2009. If you would like to review the approved IL 159
Project Report, please
click here (text only). To view a full copy of the final
report, please contact:
Illinois Department of Transportation
Attn: Ms. Candace Sauermann
1102 Eastport Plaza Drive
Collinsville, Illinois 62234
Aerial Exhibits
of each of the three sections (South, Central, and North) of the
project have been created.
To view the South Section exhibit, please
click here. (16MB)
To view the Central Section exhibit, please
click here. (11MB)
To view the North Section exhibit, please
click here. (21MB)
What’s Next?
Portions of the
IL Route 159 project have moved to Phase III, i.e. construction
has begun. Phases II and III (design and construction
respectively) of this project were divided into three
sections-South, Central, and North. The South Section
construction plans (S. Morrison to north of Church Street) and
the Central Section construction plans (north of Church Street
to north of E. Johnson Street) have been awarded and
construction has begun. Building demolition and utility
relocations are underway, and roadway construction began in the
Fall of 2010.

Demolition at UMB Bank

Construction of new box culvert south of Cherokee Street

Installation of new water line south of Catsup Bottle
To view a copy
of the final plans and specifications for the South Section,
please
click here.
To view a copy
of the final plans and specifications for the Central Section,
please
click here.
The preparation of the final design and construction bid
documents for the North Section (north of E. Johnson Street to
Kinloch Avenue) is continuing. While the land acquisition
process continues for the North Section, construction funding
for the North Section has not been secured in the Governor's FY
2012-2017 Proposed Highway Improvement Program.
|