| WHAT IS AN EXPERIMENTAL
FEATURE?
As defined in the Federal-Aid Highway Program Manual
(Vol. 6-4-2-4), an Experimental Feature Project is a
federal-aid highway construction project incorporating
one or more Experimental Features. Generally, an
Experimental Feature is defined as a material, process,
method, equipment item, traffic operational device, or
other feature which: (1) has not yet been sufficiently
tested under actual field and operational conditions to
merit acceptance without reservations in normal highway
construction; or (2) has been accepted, but needs to be
compared with alternative acceptable features to
determine relative merits and cost effectiveness. One or
both of these criteria serve as the basis for whether or
not the Experimental Feature is justified for inclusion
into the ongoing States program, and can gain federal
approval.
Construction Memorandum No. 00-2 “Construction
Projects Incorporating Experimental Features” (Appendix
10A) provides additional information.
OBJECTIVES OF EXPERIMENTAL
FEATURE PROGRAM
The objectives of the Federal Experimental Feature
Program are: (1) to actively encourage state highway
agencies to evaluate new or innovative technology, or
alternatives to standard technology, under actual
construction and operating conditions; and (2) to
provide a mechanism for the widespread dissemination and
application of the results of these evaluations.
HOW TO INITIATE AN
EXPERIMENTAL FEATURE
An Experimental Feature may be initiated by a
District, Central Office, or Local Agency. Experimental
Features are generally included and approved in a
project, before the project is advertised for bids. For
an Experimental Feature to be authorized or approved for
inclusion in a federal-aid project, an Experimental
Feature Work Plan must be prepared and submitted to the
Federal Highway Administration (FHWA) for approval. The
Work Plan shall be submitted through the Bureau of
Materials and Physical Research (BMPR) prior to the
submission of the Preliminary Studies and Engineering
(PS&E). BMPR will then forward the Work Plan to the FHWA
with a formal request for approval of the Experimental
Feature. The BMPR acts as liaison in submitting
Experimental Features, and insuring uniformity in
reporting to FHWA. The submitting agency is responsible
for meeting work and reporting requirements in the Work
Plan. Existing policy permits the inclusion of
Experimental Features in construction projects which are
already in progress, by submitting a change order. In
such cases, the preparation of an Experimental Feature
Work Plan, as outlined below, will be required and must
be submitted to the BMPR for forwarding to FHWA.
REQUIRED WORK PLAN
The Work Plan shall contain or reflect the following
significant items:
Objective
- The objectives of the Experimental Feature in terms
of the purpose, how the results might be utilized, the
economic benefits (e.g. saving in time, money, and
lives), and finally how the results of the experiment
may be implemented and applied to other construction
projects.
Supporting Research
- Reference should be made to any specific research,
past experience, reports, etc. on the subject, which
supports the basic concept of the Experimental
Feature being suggested.
Plan of Study and Evaluation
- The plan of the study, as well as the evaluation
process should be detailed.
A control section shall be provided in all approved
Experimental Feature Projects, unless the nature of
the experiment is such that a control section would
serve no purpose.
Inspection and Reporting
- This should include the frequency of inspections (at
least once a year), and the reporting anticipated
during and after construction.
Method of Construction
- The methods or means of constructing the
Experimental Feature, as well as the materials,
process, technique, and/or equipment necessary to
the project (which is a departure from normal
construction procedures) should be discussed.
Estimated Cost
- The estimated additional cost of the Experimental
Feature should be defined on a per unit basis, if
possible. Due to the experimental nature, higher
costs are normally anticipated; but the Experimental
Feature should not be excluded for that reason.
Additional costs could include such things as
personnel, test equipment, travel, and cost of
producing a final report. These additional costs are
borne by the originating agency.
Estimated Time to Complete Evaluation
- The estimated time or duration necessary to complete
all aspects of the evaluation should be defined in
the initial Work Plan. Included should be estimated
construction time, performance observation time
frame, and final report completion date.
Attachments
- Attachments could include responsible agency with
contact information, supporting research,
specifications, plan sheets, special provisions,
etc.
Although assistance during the preparation of the
Work Plan is available from the BMPR, the responsibility
of preparing the Work Plan, conducting the inspections,
and writing the final report is with the initiating
Bureau, District, or Local Agency.
CHANGES TO INITIAL WORK PLAN
Because even small changes in an Experimental Feature
can jeopardize valid research results; all changes
involving Experimental Features in a project must have
prior FHWA approval, regardless of whether they are
major or minor changes. The request for the change
should state clearly what effect the proposed change is
expected to have on the research, and be submitted to
the BMPR.
APPROVAL SUBMITTAL TO FHWA
The BMPR’s Research Coordination Engineer will submit
all required correspondence to FHWA. Appendix 10B is an
example submittal letter containing the required
information. It should be noted, that three copies of
the Work Plan and any associated material; such as, plan
sheets, section maps, special provision, etc. should be
enclosed. Also note, the District who initiated the
project or the District where the project is located is
to be sent copies. A copy is also sent to the Project
Development and Implementation Section Chief, in the
Bureau of Design and Environment.
FHWA FORM 1461 REPORTING
Initial Reporting
- Once FHWA approval is received, the BMPR will submit
the initial FHWA Form 1461 to FHWA with copies going
to the same people as noted in the Approval
Submittal letter to FHWA.
Annual Reporting
- FHWA requires that Form 1461 be prepared annually
for each Experimental Feature, and be submitted to
FHWA in October of each year by BMPR’s Engineer of
Physical Research. The person or Bureau responsible
for monitoring the Experimental Feature is expected
to visually inspect the installation, prior to
completion of the annual report. BMPR’s Engineer of
Products Evaluation coordinates the annual
monitoring.
Special Reporting
- Form 1461 will be used periodically to update the
status if and when appropriate information of
interest on the Experimental Feature develops.
Final Reporting
- A Form 1461 shall be completed and submitted
concurrently with the final report.
The initiating agency is responsible for completing
the initial and final Forms 1461. The annual update is
the responsibility of the District, Bureau, or Local
Agency monitoring the project. All Form 1461 submittals
to the FHWA are the responsibility of BMPR’s Research
Coordination Engineer.
FINAL REPORT
The field testing and evaluation can range from very
simple to complex, depending on the Experimental Feature
and what exactly is being evaluated. A one-page Final
Report may be sufficient for a simple item; such as, a
bridge expansion joint. A more complex Experimental
Feature; such as, an open-graded drainage base may
require a more substantial report.
The Final Report should include or refer to the Work
Plan, be specific as to the performance of the product,
the ease of construction, and recommended use or non-use
of the Experimental Feature.
The Final Report should be sent to BMPR’s Engineer of
Products Evaluation, who will review it prior to
submittal to the FHWA by the Research Coordination
Engineer.
|