SPRINGFIELD, IL -- The Illinois Department of Transportation received bids on April 26, 2002 for various road and bridge improvement projects throughout the state. Also included were 16 aeronautics projects and one water resource project.

Following is a list of the projects by county and the apparent low bidders:

1. Bureau County, I-80, District 2, Removal and replacement of the bridge deck wearing surfaces along with new expansion joints on structures along Interstate 80 north of Sheffield. Completion Date August 31, 2002. Ladd Construction Co., Ladd, $1,034,553.

2. Cook County, Central Avenue, District 1, 0.80 mile of milling and bituminous concrete surface on Central Avenue from Elston Avenue to Devon Avenue in Chicago. 25 Working Days. Plote Construction, Inc., Elgin, $472,242.

3. Cook County, IL 1 (Halsted Street), District 1, 4.46 miles of milling and bituminous concrete surface on IL 1 (Halsted Street) from 87th Street to 123rd Street in Chicago. Completion Date October 31, 2002 Plus 05 Working Days. K-Five Construction Corp., Lemont, $3,223,011.

4. Cook County, Green Bay Road, District 1, 0.03 mile of drainage correction consisting of partial removal of pavement, milling and bituminous concrete surface on Green Bay Road located south of Tower Road in Winnetka. 30 Working Days. Alliance Contractors, Inc., Woodstock, $112,796.

5. Cook County, Kean Avenue, District 1, 0.83 km of milling and bituminous concrete surface on Kean Avenue from 119th Street to IL 83 (Calumet Sag Rd.) near Palos Park. 20 Working Days. Johnson Blacktop, Inc., Elburn, $127,954.

6. Cook-DuPage Counties, I-290, District 1, 6.72 km of removal and replacement of the existing median with temporary bituminous pavement and construction of a temporary structure along the Higgins Road Bridge all located on I-290 from IL 72 (Higgins Road) to Devon Avenue in Schaumburg and Elk Grove Village. Completion Date October 31, 2002 Plus 20 Working Days. Harry W. Kuhn, Inc., Wheaton, $7,931,487.

7. WITHDRAWN

8. DuPage County, I-290 (Thorndale Avenue), District 1, 0.29 mile of milling and bituminous concrete surface on I-290 at Thorndale Avenue in Itasca. Completion Date June 28, 2002 Plus 05 Working Days. Harry W. Kuhn, Inc., Wheaton, $352,582.

9. Henry County, South Street, District 2, bituminous concrete widening and resurfacing on South Street from Midland Road to US 34/ IL 28 Midland Road will be realigned to "tee" into South Street. Located in Kewanee. 75 Working Days. Advanced Asphalt Co., Princeton, $1,354,988.

10. Lake County, US 45, District 1, Intersection improvement at US 45 and Dada Drive consisting of variable width widening, milling and bituminous concrete surface and realignment and reconstruction of approximately 700' of pavement on Sunshine Avenue and approximately 600' of pavement on Grant Avenue all in Gurnee. Completion Date September 06, 2002 Plus 05 Working Days. Campanella and Sons, Inc., Wadsworth, $660,383.

11. Lake County, IL 83, District 1, 0.80 mile of milling and bituminous concrete surface on IL 83 from Rollins Road to Hook Drive and from Nielson Drive to Engle Dr in Round Lake Beach. 30 Working Days. Peter Baker & Son Co., Lake Bluff, $185,218.

12. Marion County, I-57, District 7, Pavement patching, bituminous concrete binder and surface courses, 12 ft and 8 ft width bituminous shoulders, pipe underdrains and guardrail on I-57 from Salem south 5.64 miles to 0.8 mile north of IL 161. Also, included is the reconstruction of the Post Oak Rest Areas located approximately 2 miles south of US 50 in Salem. Completion Date November 26, 2002. Howell Paving, Inc. & General Contractors, Inc., Mattoon, $5,844,709.

13. Winnebago-Ogle Counties, I-39, District 2, 20.70 miles of patching, bituminous concrete resurfacing and bridge rehabilitation on Interstate 39 from the Lee County line to 0.4 mile north of Baxter Road, north of New Milford. Completion Date November 15, 2002. Bob Propheter Construction, LLC, Sterling, $19,296,419.

14. Cook County, Joe Orr Road & I-94, District 1, Beam replacement on the structure carrying Joe Orr Road over IL 394 in Lynwood and the structure carrying I-94 over Dolton Avenue in Dolton. 20 Working Days. Thos. M. Madden Co., Carol Stream, $193,281.

15. Cook County, Lake Cook Road, District 1, Beam replacement and beam straightening on the structure carrying Lake-Cook Road over US 41 (Edens Expressway) in Highland Park and Northbrook. 20 Working Days. Sumit Construction Co., Inc., Skokie, $188,491.

16. Cook County, Harrison Street, District 1, Beam replacement and beam straightening on the structure carrying Harrison Street over northbound I-90/94 (Dan Ryan Expressway) in Chicago. 15 Working Days. Lorig Construction Co., Des Plaines, $121,644.

17. Cook County, IL 68 (Dundee Rd.), District 1, Deck beam replacement on the structure carrying IL 68 (Dundee Road) over Union Pacific Railroad in Palatine. 40 Working Days. Thos. M. Madden Co., Carol Stream, $311,436.

18. Peoria County, I-74, District 4, Removal and reconstruction of the North Street structure located 0.1 km north of Interstate 74 in Peoria. Completion Date November 01, 2002. Halverson Construction Co., Inc., Springfield, $2,040,961.

19. Will County, US 45/52, District 1, Deck beam replacement on the structure carrying US 45/52 over small stream near Peotone. 30 Working Days. P.T. Gerro Construction Co., Joliet, $192,503.

20. Cook County, US 12 (Rand Road), District 1, Traffic signal modernization at the intersections along US 12 (Rand Road) from Wolf Road to IL 58 (Golf Road) in Des Plaines. 45 Working Days. Meade Electric Co., Inc., McCook, $105,138.

21. Cook County, IL 68, District 1, Traffic signal installation at the intersection of IL 68 (Dundee Road) and Sterling Avenue at Wheeling. 35 Working Days. Home Towne electric, Inc., Lake Villa, $63,258.

22. Crawford-Fayette Counties, Various Routes, District 7, The installation of flashing beacon systems at the following intersections: (1) IL 185 with Janette Drive and (Zent Road) at the north edge of Vandalia (2) IL 1 with IL 33 east of Robinson and (3) at Trimble Road with Robinwood Drive at the north edge of Robinson. 20 Working Days. J.H. Moore, Inc., Effingham, $29,390.

23. DeKalb County, US 34, District 2, Installation of traffic signals at the intersection of US 34 with Gletty Road in Sandwich. 30 Working Days. Virgil cook & Son, Inc., DeKalb, $129,120.

24. Effingham-Clay Counties, Various Routes, District 7, Highway lighting at the following intersections: (1) IL 128 with Mocassin Road 3.60 miles south of Beecher City (2) US 40 with IL 128, 2.50 miles southwest of Altamont (3) US 45 with Dutch Lane 1.0 mile south of Effingham and (4) US 50 with Clay City Road in Clay City Completion Date December 31, 2002. J.H. Moore, Inc., Effingham, $75,430.

25. Winnebago County, IL 251, District 2, Replacement of the existing lighting system at the interchange of IL 251 with Whitman Street in Rockford. 75 Working Days. Utility Dynamics Corp., Oswego, $371,625.

26. Cook County, Various Routes, District 1, Curb and gutter removal and replacement at various locations. 20 Working Days. Sumit Construction Co., Inc., Skokie, $179,959.

27. Cook-DuPage Counties, Various Routes, District 1, Bridge painting at 5 locations in Cook and DuPage Counties. 60 Working Days. Eagle Painting and Maintenace Co., Lansing, $217,180.

28. DuPage County, I-290 (Eisenhower Expwy), District 1, Bridge painting at 4 locations along I-290 (Eisenhower Expressway) from IL 83 to York Road in DuPage County. 75 Working Days. ERA-Valdivia Contractors, Inc., Chicago, $185,160.

29. Cook-DuPage Counties, I-290 (Eisenhower Expwy), District 1, Bridge painting at 5 locations along I-290 (Eisenhower Expressway) from North Avenue to Electric Avenue in Cook and DuPage counties. 75 Working Days. Venus Painting Co., Lake Station, IN, $338,760.

30. Jasper County, IL 33, District 7, Construction of concrete box culvert extensions at 12 locations on IL 33 between Newton and Willow Hill. 50 Working Days. Perry County Construction Co. Herrin, $155,362.

31. Lake-Kane-Cook Counties, Various Routes, District 1, Bridge painting at 5 locations in Lake, Kane and Cook Counties. 55 Working Days. Central Painting, Inc., Valparaiso, IN, $228,368.

32. LaSalle County, I-39, District 3, Cleaning and painting the structure carrying TR 309A over Interstate 39 one mile north of US 6 near LaSalle. 30 Working Days. Venus Painting Co., Lake Station, IN, $85,521.

33. McHenry County, Various Routes, District 1, Removal and replacement of damaged raised reflective pavement markers and castings at various locations. Completion Date October 31, 2002. Superior Road Striping, Inc., Bensenville, $118,180.

34. Richland County, US 50, District 7, The addition of left turn lanes on US 50 at the intersection with IL 250 one mile west of Noble. 50 Working Days. Howell Paving, Inc. & Wabash Asphalt Co., Inc., Mattoon, $424,014.

35. Various Counties, Various Routes, District 1, Wetland management consisting of planting, mowing and weed spraying at 7 various locations in the district. Completion Date October 15, 2002. No Bids Received.

36. Various Counties, Various Routes, Districts 6 & 7, The repair of thermoplastic preformed plastic, preformed thermoplastic, epoxy, hot spray thermoplastic and polyurea pavement marking lines, letters and symbols and the removal of existing pavement markings on various routes throughout Districts 6 and 7. Completion Date June 30, 2003. A.C. Pavement Striping Co., Des Plaines, $552,027.

37. Vermilion County, Unmarked Route, District 5, 2.84 miles of resurfacing and parking improvements on the roads in Middle Fork Fish and Wildlife Area northwest of Danville. 60 Working Days. O'Neil Bros., Urbana, $1,333,750.

38. Williamson County, CH 2, District 9, reconstructing the expansion joints at both pin and link locations with silicone joints, deck repairs, scarification of the deck and a microsilica concrete overlay on the structure carrying CH 2 over I-57 just west of Johnson City. 60 Working Days. E.T. Simonds Construction Co., Carbondale, $208,490.

39. Champaign County, CH 17, District 5, 4.4 miles of resurfacing CH 17 from CH 19 to US 45 southwest of Tolono. 40 Working Days. Champaign Asphalt Co., Champaign, $717,540.

40. Cook County, Forest Avenue, District 1, 0.35 mile of milling and resurfacing, driveway, sidewalk, curb and gutter and pavement marking on Forest Avenue from First Street to Longcommon Road in Riverside. 25 Working Days. James D. Fiala Paving Co., Inc., Bolingbrook, $263,794.

41. Cook County, Wilmette Avenue, District 1, 0.86 mile bituminous pavement reconstruction, combination concrete curb and gutter, drainage structures, traffic signals and pavement markings on Wilmette Avenue from Ridge Avenue to Green Bay Road in Wilmette. Completion Date November 22, 2002 Plus 10 Working Days. Glenbrook Excavating and Concrete, Inc. Prairie View, $2,102,455.

42. Cook County, Sibley Blvd. & State Line Rd, District 1, 0.11 mile of pavement reconstruction, combination concrete curb and gutter, storm sewers, drainage structures, lighting, traffic signals and pavement marking on Sibley Boulevard from Douglas Avenue to east of State Line Road and on State Line Road from Memorial/Rimbach north to State Street in Calumet City. 65 Working Days. Callaghan Paving, Inc., Burr Ridge, $832,608.

43. Cook County, Unmarked Route, District 1, 1.53 miles bituminous resurfacing, concrete curb and gutter, drainage structures, concrete and brick sidewalks, street lighting and pavement marking on Chicago Avenue from Austin Boulevard to Harlem Avenue (IL 43) in Oak Park. 50 Working Days. Plote construction, Inc., Elgin, $1,289,884.

44. DeWitt County, CH 14, District 5, pavement resurfacing, reconstruction, shoulders and guardrail on CH 14 from IL 10 to IL 54 south of DeWitt. 80 Working Days. Freesen, Inc., Springfield, $1,229,951.

45. Effingham County, Police Station Road, District 7, 1.74 miles of bituminous surfacing and aggregate shoulders on Police Station Road from US 45 east for 1.7 miles. 35 Working Days. Howell Asphalt Co. & Howell Paving, Inc., Mattoon, $393,548.

46. Effingham County, Grove Avenue, District 7, 0.15 mile of the reconstruction of one city block and new construction of one city block to include two 13-ft wide lanes with combination curb and gutter, storm sewers and sidewalks. 55 Working Days. J.B. Esker and Sons, Inc., Teutopolis, $315,920.

47. Effingham County, Unmarked Route, District 7, 0.75 mile reinforced concrete pavement, combination concrete curb and gutter, drainage structures, landscaping, highway lighting and pavement marking on Technology Drive from east of Althoff Drive to east of Willenborg Street; and the extension of Network Centre Drive to Technology Drive; and on Willenborg Street north and south of Technology Drive in Effingham. 130 Working Days. Mautz & Oren, Inc., Effingham, $1,190,000.

48. Iroquois County, CH 43, District 3, 3.859 miles of aggregate base course widening and bituminous resurfacing on CH 43 from CH 40 to the south city limits of Watseka. 30 Working Days. Iroquois Paving Corp., Watseka, $863,940.

49. Iroquois County, CH 15, District 3, 4.015 miles of bituminous resurfacing of CH 15, from US 52 to Beaverville. 15 Working Days. Iroquois Paving Corp., Watseka, 539,730.

50. Madison County, Pierce Lane, District 8, 0.74 mile of pavement reconstruction and vertical realignment on (Pierce Lane from IL 3 to north of Enos Lane in Godfrey. Work includes PCC pavement, precast concrete box culvert, concrete modular retaining walls, storm sewers, traffic signals, concrete curb and gutter, sidewalk and pavement marking. 155 Working Days. Keller Construction, Inc., Glen Carbon, $1,564,933.

51. McHenry County, Huntington Drive, District 1, pavement widening, resurfacing and reconstruction on Huntington Drive and Harnish Drive from Hanson Road easterly to IL 31 in Algonquin. Work includes lighting, drainage and pavement marking. 80 Working Days. Peter Baker & Son Co., Lake Bluff, $1,299,909.

52. Montgomery County, State & Sallee streets, District 6, pavement reconstruction on State Street from Ferdon Street to Sallee Street; and resurfacing on Sallee Street from State Street to Washington Street in Litchfield. Completion Date October 11. Kinney Contractors, Inc., Raymond, $1,144,933.

53. Ogle County, Ridge Road, District 2, 5.77 miles of 5" recycled hot mix asphalt base by milling the existing surface and injecting emulsified asphalt into the mix and a 22' wide bituminous surface mix, with 4' shoulders on Ridge Road, from Pines Road to the north village limits of Grand Detour. 35 Working Days. Bob Propheter Construction, LLC, Sterling, $750,843.

54. Pike County, Old IL 79, District 6, 0.47 mile of leveling binder and bituminous concrete surface course and 3 ft width aggregate wedge shoulders on Old IL 79 approximately 6 miles south of Fall Creek. 15 Working Days. Diamond Construction Co., Quincy, $61,034.

55. Randolph County, Broad Street, District 8, 0.31 mile of reconstruction, widening, concrete driveway, aprons, curb and gutter, sidewalks and related improvements on Broad Street from Cherry Street to Sixth Street in Evansville. 50 Working Days. Illinois Excavators, Inc., Ruma, $322,984.

56. Rock Island County, I-280, District 2, 4.56 miles of patching and bituminous concrete resurfacing on Interstate 280 from the Mississippi River to Airport Road in Milan. Completion Date October 15, 2002 Plus 05 Working Days. Brandt Construction Co., Milan, $3,985,006.

57. Saline County, Old IL 13, District 9, Bituminous surface removal and bituminous concrete resurfacing on Old IL 13 from the intersection with the new IL 13 alignment in Harrisburg west 5.93 miles to Lighthouse Road. 20 Working Days. Southern Illinois Asphalt Co., Inc., Marion, $336,322.

58. Sangamon County, Ridge Avenue, District 6, Pavement patching, bituminous surface removal, leveling binder and bituminous concrete surface course and 3 ft width aggregate shoulders on Ridge Avenue in Springfield from Dirksen Parkway southwest 0.35 mile to the Illinois Central Railroad. 15 Working Days. Merrill's Contractors, Inc., Springfield, $84,992.

59. Sangamon County, Lincoln Street, District 6, 0.89 mile of pavement patching, bituminous surface removal, bituminous concrete resurfacing and 2 ft width aggregate wedge shoulders on Lincoln Street in Riverton from just west of Old US 36 west to 7th Street. Completion Date July 29, 2002. Merrill's Contractors, Inc., Springfield, $87,972.

60. Sangamon County, I-55, District 6, 7.61 miles of pavement patching, bituminous surface removal, bituminous concrete resurfacing, 10 ft and 8 ft width bituminous shoulders and repairs to 7 structures along I-55 from 0.4 mile north of I-72 east of Springfield north to 0.5 mile north of Sherman including work at the Clear Lake Avenue and South Grand Avenue interchanges. Also, included is the resurfacing Sangamon Avenue and the replacement of the two structures carrying Sangamon Avenue over the I.C. Railroad. Completion Date November 26, 2002. Illinois Valley Paving Co. & Truman L. Flatt & Sons, Inc., Springfield, $11,719,161.

61. Schuyler County, County Farm & Horney Branch, District 6, 1.12 miles of pavement widening and resurfacing, new pavement and aggregate shoulders on County Farm Road from US 67 west to Horney Branch Road and Horney Branch Road west of Rushville. 70 Working Days. W.L. Miller Co., Hamilton, $599,625.

62. Shelby County, Neoga Road, District 5, 1.8 miles of pavement reconstruction on Neoga Road from one mile west of Trowbridge Road west to 3 miles northeast of Stewardson. 130 Working Days. A.J. Walker Construction Co., Mattoon, $1,563,288.

63. St Clair County, Carol Street, District 8, 0.54 mile of bituminous paving, concrete curb and gutters, and concrete driveway aprons on Carol Street from Mousette Lane to IL 157 in Cahokia. 30 Working Days. Mounds Construction Co., Inc., Collinsville, $116,437.

64. Whiteside County, Pilgrim Road, District 2, 2.523 miles of 2.5" bituminous resurfacing with an aggregate shoulder wedge along Pilgrim Road from Lyndon Road to Yorktown Road, 3 miles west of Coleta. Completion Date August 30, 2002. Northwest Illinois Construction Co., Rock Falls, $235,253.

65. Winnebago County, Latham And Ralston Road, District 2, 1.90 miles of bituminous resurfacing, adjusting inlet, manholes and other related work on Latham Road and on Ralston Road from IL 2 to IL 251 near Machesney Park. 30 Working Days. Rockford Blacktop Construction Co., Loves Park, $339,613.

66. Adams County, Planville Road, District 6, Construction of a 2 span, precast, prestressed concrete deck beam bridge and approaches carrying Planville Road over Tourmeal Creek, 4.0 miles west of Liberty. 55 Working Days. Sparks & Wiewel Construction Co., Quincy, $229,734.

67. Bureau County, US 6, District 2, Removal and replacement of a double box culvert on US 6 located approximately 1.3 miles east of IL 26 in Princeton. 20 Working Days. Ladd Construction Co., Ladd, $188,619.

68. Christian County, CH 8, District 6, removal of existing structure and construction of a 4 span, precast, prestressed concrete deck beam bridge and approaches carrying CH 8 over Lake Taylorville, 3.5 miles west of Owaneco. 50 Working Days. SW-MAC Construction, Ltd., Staunton, $706,116.

69. Cook County, 143rd Street, District 1, Construction of a new dry land bridge carrying 143rd Street over a sewer east of US 45 in Orland Park. Completion Date August 31, 2002 Plus 05 Working Days. Thos. M. Madden Co., Carol Stream, $594,847.

70. DuPage County, Gartner Road, District 1, complete superstructure replacement with a three span, continuous wide flange steel beam superstructure with a composite concrete deck and approaches carrying Gartner Road over West Branch of DuPage River in Naperville. Completion Date October 15, 2002 Plus 10 Working Days. D. Construction, Inc., Coal City, $820,583.

71. Effingham County, Crystal Club Road, District 7, removal of existing structure and construction of a three span, precast, prestressed concrete deck beam bridge and approaches carrying Crystal Club Road over Salt Creek one mile west of Teutoplis 35 Working Days. Perry County Construction Co., Carterville, $231,458.

72. Fayette County, US 51, District 7, removal and replacement of the superstructures, approach pavement and guardrail at the bridges carrying US 51 over the Kaskaskia River at the Conrail Railroad in Vandalia. 130 Working Days. Halverson Construction Co., Inc., Springfield, $2,761,367.

73. Fayette County, TR 518, District 7, removal of existing structure and the construction of a single span, precast prestressed concrete deck beam bridge and aggregate approaches carrying TR 518 over Little Moccasin Creek, two miles east of Wrights Corner. 25 Working Days. Perry County Construction Co., Carterville, $83,601.

74. Gallatin County, Saline Mine Road, District 9, Construction of a single span, precast, prestressed, concrete deck beam bridge carrying CH 8, Saline Mine Road, over tributary to Ohio River, 3.5 miles south of Shawneetown. 30 Working Days. Dees, Inc., West Frankfort, $175,224.

75. Jackson-Perry Counties, North Mudline Road, District 9, Construction of a two span, precast, prestressed concrete deck beam bridge with aggregate approaches carrying CH2 (North Mudline Road) over tributary to Beaucoup Creek approximately 1.5 miles south of IL 13/127. 50 Working Days. Summers Crane and Construction, Inc., Benton, $353,472.

76. Lee County, Lost Nation Road, District 2, replacing the bridge deck beams and repair the substructure elements, railing and guardrail on the structure carrying Lost Nation Road over Franklin Creek, 3 miles N.E. of Dixon. Completion Date July 31, 2002. Ladd Construction Co., Ladd, $236,351.

77. Piatt County, TR 39, District 5, removal of existing structure and construction of a single span, precast, prestressed concrete deck beam bridge and aggregate approaches carrying TR 39 over Goose Creek approximately 2 miles northeast of Deland. 25 Working Days. Schmidt Construction, Inc., Mt. Zion, $108,663.

78. Stephenson County, IL 73, District 2, Removal and replacement of the structure carrying IL 73 over a tributary to Yellow Creek in Pearl City. 65 Working Days. Civil Constructors, Inc. of Illinois, Freeport, $390,903.

79. White County, TR 413, District 7, Construction of a 3 span, precast concrete bridge slab, aggregate surface course and earthwork carrying TR 413 over Sandy Slough 2.5 miles east of New Haven. 30 Working Days. Summers Crane and Construction, Inc., Benton, $172,432.

80. Winnebago County, Riverside Boulevard, District 2, replacement of pin and link connections, sidewalk removal, reinforced concrete deck and a jersey barrier type parapet on a six span bridge carrying Riverside Boulevard over the Rock River in Loves Park. 150 Working Days. Sjostrom & Sons, Inc., Rockford, $1,229,550.

81. Winnebago County, IL 251, District 2, Removal and replacement of the structure carrying IL 251 over Spring Creek located in Rockford. Completion Date August 16, 2002. Rockford Blacktop Construction Co., Loves Park, $1,297,266.

82. Winnebago County, Blomberg Road, District 2, removal of existing structure and construction of a three span, steel I-beam structure and approaches carrying Blomberg Road over Kishwaukee River, approximately 3 miles south of Cherry Valley. 180 Working Days. Belvidere Construction Co., Belvidere, $1,087,257.

83. Woodford County, CH 5, District 3, Construction of a 3 span, precast, prestressed concrete deck beam bridge carrying CH 5 over branch of Panther Creek, 0.5 mile north of Secor. 30 Working Days. Stark Excavating, Inc., Bloomington, $183,008.

84. Cook County, Schaumburg Road, District 1, modernization of pedestrian signals at 11 locations on Schaumburg Road from Knollwood Drive to Meacham Road in Schaumburg. Work also includes pavement marking, sidewalk and reoptimization of traffic signal timing. 45 Working Days. Hawk Enterprises, Inc. of Indiana, Crown Point, IN, $182,350.

85. Cook County, Willow Springs Road, District 1, Traffic signal modernization at the intersections along Willow Springs Road from 75th Street to German Church Road in Willow Springs. 35 Working Days. Lyons Electric Co., Inc., Lyons, $108,700.

86. Cook County, IL 58 (Golf Road), District 1, Traffic signal modernization at the intersection of IL 58 (Golf Road) and Mt. Prospect Road in Des Plaines. 35 Working Days. Home Towne Electric, Inc., Lake Villa, $146,993.

87. Cook County, US 12/45 & IL 72, District 1, Traffic signal modernization at the intersection of US 12/45 and IL 72 in Rosemont. 35 Working Days. Home Towne Electric, Inc., Lake Villa, $110,983.

88. Cook County, Halsted Street, District 1, new street lighting along Halsted Street, from Joe Orr Road to Holbrook Road in Chicago Heights. 55 Working Days. Hawk Enterprises, Inc., of Indiana, Crowne Point, IN, $405,911.

89. DuPage County, Butterfield & York Rds, District 1, intersection improvement at York Rd at Lexington Street; and traffic signal modernization on Butterfield Road and Commonwealth Lane in Elmhurst. Work includes roadway widening, resurfacing, storm sewers and pavement marking. Completion Date September 30, 2002 Plus 10 Working Days. Johnson Blacktop, Inc., Elburn, $1,045,893.

90. Ford County, IL 115, District 3, Installation of two flashing beacons on existing stop signs at the intersection of IL 115 and IL 54 in Roberts (two locations). 20 Working Days. J.H. Moore, Inc., Effingham, $11,197.

91. Lake County, IL 21, District 1, Traffic signal modernization at the intersection of IL 21 at IL 60 (Town Line Road) in Vernon Hills. 35 Working Days. Home Towne Electric, Inc., Lake Villa, $122,507.

92. Madison County, I-255, District 8, The replacement of light poles along I-255 and I-270 at IL 111 at Pontoon Beach. 20 Working Days. J.F. Edwards Construction Co., Geneseo, $133,245.

93. McLean County, College Avenue, District 3, widening and rehabilitating the existing pavement, installing new traffic signals and equipment, and other miscellaneous work at the intersection of College Avenue FAU Route 6352 and University Street in Normal. Completion Date August 14, 2002 Plus 05 Working Days. Stark Excavating, Inc., Bloomington, $320,401.

94. Sangamon County, MacArthur Blvd & South Grand Ave, District 6, Interconnect and traffic signal modernization of the traffic signals along MacArthur Boulevard from Highland Avenue to South Grand Avenue and on South Grand Avenue from MacArthur Boulevard to Walnut and Holmes Avenue in Springfield. 90 Working Days. Egizii Electric, Inc., Springfield, $334,061.

95. Will County, ILL 53, District 1, installation of ornamental light poles and luminaries on Historic Route 66 (IL 53 Bridge) over the East Channel of the Kankakee River in Wilmington. 15 Working Days. Van-Mack Electric, Joliet, $31,405.

96. Champaign-Vermilion Counties, Various Routes, District 5, 9.65 miles of routing and sealing of longitudinal joints and traverse crack various locations in Champaign and Vermilion Counties. 35 Working Days. Valley Improvement Construction Co., Bluffs, $168,448.

97. Livingston County, IL 23, District 3, Removal and replacement of the wearing surface on the structure carrying IL 23 over Long Point Creek 3.5 miles south of IL 17 near Long Point. 25 Working Days. Len Trovero Construction, LaSalle, $79,420.

98. Cook County, Lemoyne And Hirsch Streets, District 1, removal and replacement of curb and gutter and PCC sidewalk, drainage structures and related work on LeMoyne Street from Wolf Road to 43rd Street; on Hirsch Street from Carl to Mannheim Road; and on Dodd/Morse Drive from Victoria Road to Harold Avenue in Northlake. 45 Working Days. Triggi Construction, Inc., West Chicago, $386,766.

99. Marion County, Various Routes, District 7, 0.27 mile of removal and replacement of bituminous concrete wearing surface at 6 locations on IL 161 between Centralia and I-57; 0.35 mile of bituminous concrete surface and binder courses and 3 ft width aggregate shoulders on Kinoka Road north of Patoka; and 0.60 mile of bituminous surface removal and bituminous concrete resurfacing on Old US 51 in Patoka. 25 Working Days. Howell Paving, Inc., & General Contractors, Inc., Mattoon, $112,544.

100. Peoria County, I-74, District 4, Supplying tangent piles for the construction of retaining walls along I-74 from Knoxville through Adams Street in Peoria. Completion Date January 06, 2003. P.H. Drew, Inc., Indianapolis, IN, $1,655,258.

101. DeWitt-Piatt-Macon Counties, Various Routes, District 5, 12.2 miles of routing and sealing longitudinal joints and tranverse cracks at various locations in DeWitt, Macon and Piatt Counties. 35 Working Days. Valley Improvement Construction Co., Bluffs, $273,572.

102. Coles-Douglas-Edgar Counties, Various Routes, District 5, 39.3 miles of routing and sealing longitudinal joints and tranverse cracks various locations in Coles, Douglas and Edgar Counties. 30 Working Days. Valley Improvement Construction Co., Bluffs, $102,000.

103. Various Counties, Various Routes, District 6, repair of thermoplastic, hot spray, thermoplastic a polyurea pavement marking lines, letters and symbols and the removal of existing pavement markings on various throughout District 6. Completion Date November 30, 2002. A.C. Pavement Striping Co., Des Plaines, $5778,814.

104. Various Counties, Various Routes, District 7, Variable width bituminous concrete overlays at the following locations: (1) on I-70 between the Kaskaskia and Camp Creek Bridges east of Vandalia (2) on IL 33 in Wheeler and (3) on US 50 west and east of the Richland/Lawrence County line. 40 Working Days. Howell Asphalt Co. & Howell Paving, Inc., Mattoon, $399,777.

105. Various Counties, Various Routes, District 7, replacing reflectorized guardrail markers, bridge rail markers, barrier wall markers and terminal markers on various routes throughout District 7. Completion Date December 31, 2002. Hodges Fence Erectors, Edgewood, $17,030.

106. Effingham-Fayette-Jefferson Counties, I-57, I-64, I-70, District 7, Pavement patching at 6 locations on interstates 57/70, 57,70 and 64 in Effingham, Fayette and Jefferson Counties. 75 Working Days. Kinney Contractors, Inc., Raymond, $244,621.

107. Various Counties, Various Routes, District 8, replacing reflectorized guardrail markers, bridge rail markers, barrier wall markers and terminal markers on various routes throughout District 8. Completion Date December 31, 2002. Hodges Fence Erectors, Edgewood, $41,708.

108. Various Counties, Various Routes, Repairing or replacing damaged or deteriorated overhead sign structure components and supports on various throughout Districts 1, 2, 4, 7 and 8. Completion Date May 31, 2003. T.M.F. Construction Co., Springfield, $497,980.

109. Various Counties, Various Routes, Statewide, repairing or replacing damaged sign components, furnishing, or furnishing and installing new signs and supports or replacing damaged overhead sign structure components and end supports on various routes statewide. Completion Date June 30, 2003. T.M.F. Construction Co., Springfield, $795,323.

110. Vermilion County, Various Routes, District 5, Cleaning and painting of seven structures located on various routes in Vermilion County. 110 Working Days. Venus Painting Co., Lake Station, IN, $298,000.

111. Champaign County, US 150, District 5, 2.14 km of bituminous concrete widening and resurfacing with bi-directional lanes on US 150 from University Avenue to IL 1 in Urbana. Includes improvements to the intersections and railroad approach Completion Date October 31, 2003 Plus 10 Working Days. Cross Construction, Inc., Urbana, $3,229,801.

112. Cook-DuPage Counties, I-55, District 1, 7.10 miles of milling and bituminous concrete surface on I-55 from Lemont Road to I-294 in Burr Ridge, Indian Head Park and Darien. Completion Date June 15, 2003 Plus 10 Working Days. K-Five Construction Corp. & Central Blacktop Co., Inc., Lemont, $6,124,828.

113. DuPage County, I-55 Frontage Roads, District 1, 7.93 miles of milling and bituminous concrete surface on I-55 Frontage Roads at 4 locations in Damien, Lemont, Willowbrook and Burr Ridge 50 Working Days. Central Blacktop Co., Inc., LaGrange, $1,300,515.

114. DuPage County, IL 38, District 1, 3.22 miles of milling and bituminous concrete surface on IL 38 from Finley Road to Villa Avenue in Lombard and Villa Park. 50 Working Days. Plote Construction, Inc., Elgin, $1,627,059.

115. Jersey County, Otterville Road, District 8, 3.583 miles of bituminous resurfacing, widening of aggregate shoulders, drainage corrections and related work on Otterville Road from Otterville to IL 3. 110 Working Days. Charles E. Mahoney Co., Belleville, $1,394,503.

116. JoDaviess County, US 20 (EB), District 2, 0.142 mile of upgrading the existing roadway by providing a right turn lane on US 20 eastbound as well as widening the returns on Frentress Lake Road located near East Dubuque. 25 Working Days. Fisher Excavating, Inc., Freeport, $273,798.

117. Kendall County, US 34, District 3, 2.33 km of reconstruction of US 34 from east of the Douglas Road intersection of US 30 in Oswego. Includes construction from two lanes to four thru lanes and a bi-directional lane. Completion Date June 15, 2003 Plus 15 Working Days. James Cape & Sons Co., Hoffman Estates, $5,589,706.

118. Logan County, Bl I-55 (Kickapoo Street), District 6, 1.65 miles of pavement patching, bituminous surface removal, variable width PCC base course, bituminous concrete resurfacing and combination concrete curb and gutter on Kickapoo Street in Lincoln from Lincoln Parkway to Keokuk Street. Also included is the modernization of the traffic signals at the intersection of Kickapoo Street and Keokuk Street. Completion Date October 15, 2002. Illinois Valley Paving Co., Springfield, $793,332.

119. WITHDRAWN

120. Madison County, Relocated IL 159, District 8, 3.27 kilometers of new pavement construction for relocated IL 159 and the construction of a nature/bike trail from Center Grove Road to Vandalia Street in Edwardsville and Glen Carbon. Also, included is traffic signal work at the intersections of relocated IL 159 with Schwarz and Vandalia Street. Completion Date July 31, 2004. Thiems Construction Co., Inc., Edwardsville, $6,189,574.

121. Ogle County, IL 72, District 2, 7.42 miles of bituminous concrete resurfacing and a culvert replacement on IL 72 between Mount Morris Road and IL 2, west of Byron. 85 Working Days. Bob Propheter Construction, LLC, Sterling, $1,532,482.

122. Peoria County, IL 8 & Farmington Rd., District 4, 3.1 miles of surface maintenance of IL 8 from west of Pottstown Road Main Street in Peoria, including 1,800 feet on Farmington Road. 25 Working Days. R.A. Cullinan & Son, Inc., Tremont, $667,381.

123. Peoria County, Airport Road, District 4, Improvement consists of a four lane PCC pavement median, storm sewers, combination concrete curb and gutter and pavement marking on Airport Road from Garfield Avenue to Smithville Road near Greater Peoria Airport. 225 Working Days. P.J. Hoerr, Inc., Peoria, $1,898,755.

124. Peoria County, Airport Road, District 4, 0.332 kilometers of grading, clearing, storm sewers, traffic signals and a four lane PCC pavement on Airport Road and Garfield Avenue in Peoria. 160 Working Days. P.J. Hoerr, Inc., Peoria, $1,103,998.

125. Pike County, IL 96, District 6, Pavement patching, bituminous surface removal, bituminous concrete resurfacing, 1 ft width bituminous shoulders and 3 ft width aggregate wedge shoulders on IL 96 from Pleasant Hill northwest 12 miles to Dutch Creek. Completion Date October 04, 2002. Diamond Construction Co., Quincy, $1,474,787.

126. Rock Island County, 23rd Avenue, District 2, pavement removal and replacement, curb and gutter, sidewalks, driveway and storm sewers on 23rd Avenue from 44th Street to 48th Street in Moline. 120 Working Days. Walter D. Laud, Inc., Carbon Cliff, $1,339,942.

127. Saline County, US 45, District 9, On US 45 from south of Public Street in Muddy and extending 4.41 miles northeast to north of Trolley Road in Eldorado. Construction of two additional through lanes, the removal of eight existing structures and the construction of six new structures, pavement patching and the resurfacing of the existing pavement. Completion Date November 15, 2003. E.T. Simonds Construction Co., Carbondale, $13,827,786.

128. Stephenson-Winnebago Counties, IL 75, District 2, 19.0 miles of bituminous concrete resurfacing at two locations on IL 75 between Freeport and IL 70 near Freeport. 15 Working Days. Civil Constructors, Inc. of Illinois, Freeport, $220,051.

129. Vermilion County, IL 1, District 5, Intersection improvement at the intersection of IL 1 and Bismarck Road north of Danville. Completion Date October 01, 2002 Plus 10 Working Days. University Construction, Urbana, $2,022,106.

130. Vermilion County, IL 49, District 5, 0.40 mile of patching on IL 49 north of TR 69 near Ellis. 15 Working Days. University Construction, Urbana, $268,998.

131. Will-DuPage Counties, I-55, District 1, 9.30 miles of milling and bituminous concrete surface on I-55 from IL 126 to Lemont Road in Bolingbrook, Romeoville Woodbridge, Darien, Lemont, Downers Grove and Lockport. Completion Date August 29, 2002 Plus 05 Working Days. Harry W. Kuhn, Inc., Wheaton, $5,400,172.

132. Will County, Van Dyke Boulevard, District 1, 0.51 miles of pavement reconstruction, widening, resurfacing, storm sewers and landscaping on Van Dyke Boulevard from 143rd Street north to West Norman Drain in Plainfield. Completion Date November 15, 2002. Geneva Construction Co., Aurora, $891,072.

133. Winnebago County, I-39 & US 20, District 2, 0.75 mile of milling and bituminous concrete resurfacing on the I-39 northbound off ramp onto US 20 Bypass westbound, the Harrison Avenue ramp onto I-39 northbound/US 20 westbound near Rockford. 15 Working Days. Bob Propheter Construction, LLC, Sterling, $115,576.

134. Winnebago County, US 20 frontage road. District 2, 1.0 mile of bituminous resurfacing of the north frontage road along US 20 between Weldon Road and Falconer Road, west of Rockford. 15 Working Days. Rock Road Companies, Inc., Janesville, WI, $97,699.

135. Bureau County, I-80, District 2, Removal and replacement of three structures carrying Interstate 80 over Kin Creek, Barbara Ditch and Abbott Ditch near Mineral. 175 Working Days. Brandt Construction Co., Milan, $3,154,733.

136. Carroll, IL-Jackson, IA Counties, US 52/IL 64, District 2, Removal of the paint and painting of the steel elements on the structure carrying US 52/IL 64 over the Mississippi River at Savanna. Completion Date December 31, 2002 Plus 05 Working Days. Atlantic Painting Co., Inc. & Eagle Painting and Maintenance Co., Oak Lawn, $1,309,000.

137. Henry County, IL 78, District 2, Removal and replacement of the structure carrying IL 78 over an unnamed creek located south of IL 92 north of Hooppole. 50 Working Days. Valley Construction Co., Rock Island, $349,413.

138. Iroquois County, US 45, District 3, Removal and replacement of the structure carrying US 45 over Spring Creek located 0.3 mile south of Del Rey Road near Del Rey. Completion Date December 15, 2002 Plus 15 Working Days. Tobey's Construction & Cartage, Inc., Herscher, $1,019,712.

139. Knox County, Prairie Street, District 4, The removal and replacement of the existing superstructure, modifications to the existing abutments and 43 lineal feet of approach roadway reconstruction at the bridge carrying Prairie Street over Cedar Creek in Galesburg. 30 Working Days. Hillyer, Inc., Macomb, $200,736.

140. Knox County, Unmarked Route, District 4, removal and replacement of existing bridge superstructure with a precast, prestressed concrete deck beam and bituminous concrete overlay on Chambers Street between Peck Street and E Grove Street Cedar Creek in Galesburg. 40 Working Days. Hillyer, Inc., Macomb, $240,949.

141. Ogle County, IL 64, District 2, Removal and replacement of the structure carrying IL 64 over Elkhorn Creek located east of Brookville. Completion Date November 15, 2002 Plus 05 Working Days. Belvidere Construction Co., Belvidere, $937,760.

142. Peoria County, CH 40, District 4, Construction of 10' x 9' double box culvert, approach roadway realignment and other collateral work carrying CH 40 over Prince Run Creek, 0.5 mile south of Princeville. 75 Working Days. P.J. Hoerr, Inc., Peoria, $347,943.

143. Sangamon County, Old IL 4, District 6, The removal of the existing single span structures carrying Old IL 4 over Panther Creek located 1.0 mile and 1.2 miles north Auburn and the replacement with four cell 3.0 m x 3.6 m concrete box culverts. Completion Date October 04, 2002. Sparks & Wiewel Construction Co., Quincy, $1,655,495.

144. Madison County, IL 159, District 8, Traffic signal modifications at the intersection of IL 159 and Wickliff Avenue in Collinsville. 30 Working Days. Electrico, Inc., Columbia, $56,409.

145. Tazewell-Woodford Counties, Various Routes, District 4, Installation of new LED sections in existing signal heads in Creve Coeur, East Peoria, Metamora, Morton, North Pekin, Pekin and Washington. 40 Working Days. Advanced Electric Co., Canton, $172,004.

146. Carroll County, US 52/IL 64, District 2, full depth bituminous patching near the intersection of US 52/IL 64 and IL 73 south of Lanark. 15 Working Days. Civil Constructors, Inc. of Illinois, Freeport, $17,744.

147. Cook-DuPage-McHenry Counties, Various Routes, District 1, Scour countermeasures at 7 various locations. 55 Working Days. D. Construction, Inc., Coal City, $443,095.

148. Clark County, Archer Avenue, District 5, Construction of period type lighting, storm sewers and reconstruct of sidewalks along Archer Avenue from 4th Street to Michigan in Marshall. 65 Working Days. Feutz Contractors, Inc., Paris, $594,350.

149. WITHDRAWN

150. Edgar County, Clinton Road, District 5, 8.03 miles patching on Clinton Road from TR 227B to the Indiana State Line. 20 Working Days. G.M. Sipes Construction, Inc., Rushville, $176,753.

151. Effingham County, US 40, District 7, One mile west of Effingham on US 40 the work will consist of constructing a corrugated steel pipe culvert with steel end sections. 15 Working Days. Perry County Construction Co., Herrin, $25,611.

152. Henry County, IL 17, District 2, 0.5 mile of pavement patching, milling and bituminous resurfacing on IL 17 and on the IL 17 service road at the intersection with Interstate 74. 20 Working Days. Advanced Asphalt Co., Princeton, $271,452.

153. JoDaviess County, US 20, District 2, 10.1 miles of pavement patching on US 20 between East Dubuque and IL 84. 15 Working Days. Civil Constuctors, Inc. of Illinois, Freeport, $57,429.

154. McDonough County, IL 61, District 4, .03 mile of concrete pavement with subbase granular French drain and pipe underdrains on IL 61 located 1.9 miles south of Colmar. 20 Working Days. R.A. Cullinan & Son, Inc., Tremont, $100,789.

155. Peoria County, I-74, District 4, Demolition of a house (1416 N. Linn St.) near I-74 in Peoria. 15 Working Days. N.E. Finch Co., Peoria, $18,700.

156. Peoria-Tazewell Counties, Various Roads, District 4, Demolition of three houses; 10226 N. Knoxville Avenue, 1623 N. Valley Avenue includes a garage and 1976 E. Washington Street in Peoria and East Peoria. 25 Working Days. N.E. Finch Co., Peoria, $33,750.

157. Rock Island County, 27th Street, District 2, Cleaning and painting the 27th Street bridge over the Rock River in Moline. Completion Date August 31, 2002 Plus 05 Working Days. ERA-Valdivia Contractors, Inc., Chicago, $125,000.

158. Rock Island County, Friedens Road & IL 5 frontage road, District 2, 1.4 miles of patching and resurfacing on Friedens Road (a frontage road) and on IL 5 Frontage Road near the interchange of Interstate 80 and IL 5. 15 Working Days. Brandt Construction Co., Milan, $152,585.

159. Rock Island County, I-74 frontage roads, District 2, 0.76 mile of patching and bituminous resurfacing on 19th Street, 27th Street and 7th Avenue in Moline. 40 Working Days. Valley Construction Co., Rock Island, $431,441.

160. Tazewell County, I-74, District 4, Supplying tangent and HP piles for the construction of various structures located along Interstate 74 from the Illinois River to Pinecrest Drive in East Peoria. Completion Date January 07, 2003. Halverson Construction Co., Inc., Springfield, $370,300.

161. Tazewell County, Various Routes, District 4, 10.88 miles of routing and sealing on Interstate 74 from the bridge over the railroad tracks east of Morton to mile marker 105, IL 9 from Pekin to Chestnut Street in Tremon,t and IL 29 from Manito Road to Hurt Road. 15 Working Days. Valley Improvement Construction Co., Bluffs, $80,067.

162. Various Counties, Various Routes, Districts 2 & 3, Repairing various widths of thermoplastic, preformed plastic, preformed thermoplastic, epoxy, hot spray thermoplastic and polyurea pavement marking lines, letters and symbols and the removal of existing markings on various routes throughout Districts 2 and 3. Completion Date June 30, 2003. A.C. Pavement Striping Co., Des Plaines, $529,852.

163. Various Counties, Various Routes, District 4, Washing of six bridges at four different locations on various routes over the Illinois River. 25 Working Days. Tom Crist Paint Co., Inc., Calumet City, $270,000.

164. Various Counties, Various Routes, Districts 8 & 9, The repairing of various widths of thermoplastic, preformed plastic, preformed thermoplastic, epoxy, hot spray thermoplastic and polyurea pavement marking lines, letters and symbols and the removal of existing pavement markings on various routes in Districts 8 and 9. Completion Date June 30, 2003 Working Days. A.C. Pavement Striping Co., Des Plaines, $633,586.

165. Peoria-Henderson Counties, Various, District 4, Cleaning and painting of the structural steel on 5 structures on various routes. 65 Working Days. No Bids Received.

166. Various Counties, Various Routes, District 4, Scour mitigation at various structures in Knox, Peoria and Tazewell Counties 120 Working Days. Otto Baum Co., Inc., Morton, $1,686,188.

167. Various Counties, Various Routes, Districts 4 & 5, Repairing various widths of thermoplastic, preformed plastic, preformed thermoplastic, epoxy, hot spray thermoplastic and polyurea pavement marking lines, letters and symbols and the removal of existing markings on various routes throughout District 4 and 5. Completion Date June 30, 2003. A.C. Pavement Striping Co., Des Plaines, $533,461.

168. Edwards-Wabash-Clay Counties, Various Routes, District 7, 0.75 mile of bituminous surface removal and bituminous concrete resurfacing on Old IL 130 in Grayville; 0.68 mile bituminous concrete surface course and 3 ft width aggregate shoulders on Old IL 15 north of Browns; 0.64 mile of bituminous concrete surface and 3 ft width aggregate shoulders on Old IL 15 approximately 1.5 miles west of Albion; 0.09 mile of bituminous surface removal and bituminous concrete resurfacing on US 45 west of Flora; and 0.20 mile of bituminous surface removal and bituminous concrete resurfacing on US 50 west of Flora. 35 Working Days. Howell Paving, Inc. & Wabash Asphalt Co., Inc., Mattoon, $245,060.

169. Various Counties, Various Routes, District 7, The routing, cleaning and sealing of transverse and longitudinal reflected cracks and joints in the existing pavements on various routes throughout District 7. 65 Working Days. Valley Improvement Construction Co., Bluffs, $427,264.

170. Various Counties, Various Routes, District 7, The placement of a bituminous surface treatment, class A-1 at 9 locations on various routes throughout District 7. 25 Working Days. Mt. Carmel Sand & Gravel Co., Inc., Mt. Carmel, $51,999.

171. Various Counties, Various Routes, District 9, The cleaning and painting portions of the structural steel on eleven bridges on various routes throughout District 9. 105 Working Days. Tom Crist Paint Co., Inc., Calumet City, $743,000.

172. Whiteside County, Garden Plain Road, District 2, 10.4 miles of intermittent bituminous resurfacing on Garden Plain Road between IL 84 and US 30 in Morrison. 15 Working Days. Northwest Illinois Construction Co., Rock Falls, $312,332.

173. Winnebago County, IL 2, District 2, Drainage correction/storm sewer improvements at IL 2 and Kelley Creek 0.1 mile south of IL 75 in South Beloit. 40 Working Days. Stenstrom Excavation & Blacktop, Inc., Rockford, $234,747.

174. Winnebag0 County, I-39, District 2, Cleaning and painting of three structures on Interstate 39, northbound over US 20, southbound ramp over US 20 from westbound US 20 and southbound on-ramp over Linden Road from eastbound US 20. Completion Date August 31, 2002 Plus 05 Working Days. Venus Painting Co., Lake Station, IN, $292,000.

175. Winnebago County, IL 2, District 2, Cleaning and painting bridges at two locations: IL 2 over the Rock River near Rockton and Interstate 39 (northbound) Linden Road at the US 20 Bypass interchange. Completion Date August 15, 2002 Plus 05 Working Days. Venus Painting Co., Lake Station, IN, $395,220.

176. Champaign-Vermilion Counties, US 150, District 5, 7.5 miles of bituminous resurfacing on US 150 from Main Street in Saint Joseph to IL 49 in Saint Joseph and Ogden. Completion Date September 30, 2002. Champaign Asphalt Co., Champaign, $1,519,001.

177. Montgomery County, IL 16, District 6, .70 km of pavement removal and replacement with bituminous concrete pavement, storm sewers, curb and gutter, and sidewalks along IL 16 from west of 18th St. to Miller St. in Schram City, Illinois Valley Paving Co., Springfield, $2,219,435.

178. St. Clair County, I-70/55, District 8, shoulder removal and repacement with pavement widening, pavement marking and signing to connect IL 203 with the new Martin Luther King exit ramp along westbound I-70/55 in East St. Louis, Mounds Construction Co., Inc., Collinsville, $234,772.

179. Henry County, IL 92, District 2, maintenance on the Joslin Wetland at the southeast corner of IL 92 and the Rock River, Dalziel enterprises, Inc., Moline, $53,650.

180. Shelby County, Thompson Mill Road, District 5, adding sprinkler system to the Thompson Mill Covered Bridge on TR 389A east of Cowden. Egizii Electric, Inc., Springfield, $320,506.

1A. Lansing Municipal Airport, Lansing, Cook County, Construct, Light and Mark Runway 18/36 (4000' x 75'); Partial Parallel Taxiway And Connecting Taxiways (Phase 2); Install Airfield Lighting Vault Building And Equipment; Install PAPI System Runway 18/36. Callaghan Paving, Inc., Burr Ridge, $2,167,821.

2A. Quad-City International Airport, Moline, Rock Island County, GA Ramp Expansion - Phase 1. Brandt Construction Co., Milan, $367,627.

3A. Southern Illinois Airport, Carbondale, Jackson County, Hangar 6 Apron Rehabilitation. E.T. Simonds Construction Co., Carbondale, $201,542.

4A. DELETED

5A. Decatur Airport, Decatur, Macon County, Install Security Fencing In Frontal Area. Hodges Fence Erectors, Edgewood, $237,561.

6A. Pinckneyville-DuQuoin Airport, Pinckneyville, Perry County, Rehab. & Expand Apron, Replace Beacon. E.T. Simonds Construction Co., Carbondale, $324,845.

7A. Aurora Municipal Airport, Aurora, Kane County, Construct Partial Parallel Taxiway to Runway 9/27; Rehabilitate Terminal (Contract 1). Alliance Contractors, Inc., Woodstock, $966,318.

8A. Southern Illinois Airport, Carbondale, Jackson County, Runway 6/24 Overlay. E.T. Simonds Construction Co., Carbondale, $285,579.

9A. Pekin Municipal Airport, Pekin, Tazewell County, Rehabilitate and Mark Runway 9/27. R.A. Cullinan & Son, Inc., Tremont, $985,359.

10A. Greater Peoria Regional Airport, Peoria, Peoria County, Rehabilitate T-Hangar Taxiways. R.A. Cullinan & Son, Inc., Tremont, $273,562.

11A. Tri-Township Airport, Savanna, Carroll County, Rehabilitate Runway 13/31, Taxiway And Apron. Civil Constructors, Inc. of Illinois, Freeport, $506,790.

12A. Kewanee Municipal Airport, Kewanee, Henry County, , Bituminous Overlay to Runway 1/19. Advanced Asphalt Co., Princeton, $424,777.

13A. DELETED

14A. Freeport-Albertus Airport, Freeport, Stephenson County, Rehabilitate, Mark And Groove Runway 6/24. Civil Constructors, Inc. of Illinois, Freeport, $919,804.

15A. Whiteside County Airport, Sterling, Whiteside County, Rehabilitate and Mark the North Terminal Apron. Bob Propheter Construction, LLC, Sterling, $399,511.

16A. DeKalb-Taylor Municipal Airport, DeKalb, DeKalb County, Reconstruction Of Taxiway "B". Rockford Blacktop Construction Co., Loves Park, $443,812.

1W. Lake County, Site L-10 Storage Yard, , Construct an 8 acre storage yard with seawall and boat ramp located off of Grass Lake Road, south of Oak Avenue and north of Elm Tree Road and adjacent to Grass Lake. The work includes but is not limited to the following major items of work: 10.56 acres of tree removal, 40,631 cubic yards of earth excavation, 4,850 sq ft of permanent steel sheet piling, 152 cu yds of concrete structures, 1,450 sq yds of reinforced concrete pavement, 8", 582 tons of asphalt paving, 5,545 sq yds of aggregate base course,Type B, 12", 1,065 ft of storm sewer (various sizes), and 4,698 ft of chain link fence, 6’high (Completion date of July 31, 2002 with 85 guaranteed working days). Lake County Grading Co. of Libertyville, Inc., Libertyville, $1,170,505.

###