CONSTRUCTION UPDATE REPORT
City of Chicago
Effective: 06/04/09 5:29 PM
| LOCATION AND DESCRIPTION |
MUNICIPALITY START DATE EST. STOP DATE COST (millions) |
COMMENTS |
|
103rd Street Bridge deck, lighting. |
Chicago 5/2009 10/2009 $2.053 |
IMPACT ON TRAVEL:
60366 Bridge deck removal and replacement, approach work and lighting for the structure carrying 103rd Street over I-57 in Chicago. |
|
111th Street Bridge deck replacement |
Chicago 11/2009 8/2010 $2.742 |
IMPACT ON TRAVEL:
62532 Bridge deck replacement for the structure carrying 111th Street over northbound and southbound I-57 and traffic signal modernization, resurfacing and lighting at two intersections, located in Chicago. |
|
112th Place over I-57 Bridge deck replacement. |
Chicago 6/2009 10/2009 $2.569 |
IMPACT ON TRAVEL:
62533 Bridge deck replacement for the structure carrying 112th Place over I-57, approach roadway resurfacing, underpass lighting and traffic signal modernization at two intersections located in Chicago. |
|
115th Street Deck replacement and underpass lighting |
Chicago 5/2009 10/2009 $2.917 |
IMPACT ON TRAVEL:
60371 Deck replacement and underpass lighting for the 115th St. Bridge over I-57 and approach roadway resurfacing, intersection improvements and traffic signal modernization along I-57 in Chicago. |
|
26th Street Bridge superstructure replacement. |
Chicago 5/2009 10/2010 $5.62 |
IMPACT ON TRAVEL:
62197 Removal and replacement of the superstructure of the bridge carrying 26th St. and I-55 Frontage Rd. B over the Franklin Connector in Chicago. |
|
31st Street from Cicero Avenue to Kostner Avenue. Resurfacing, bridge replacement, lighting and traffic signals. |
Chicago 4/2009 11/2009 $6.212 |
IMPACT ON TRAVEL:
62196 0.47 mile of roadway resurfacing and reconstruction, bridge deck replacement, lighting and traffic signal modernization on 31st Street from Cicero Avenue to Kostner Avenue in Chicago. |
|
Along I-290 Drainage modifications, barrier walls, patching. |
Chicago 6/2009 9/2009 $2.043 |
IMPACT ON TRAVEL:
60D93 Drainage modifications, storm sewer installation, new drainage structures, barrier walls, retaining wall, sign truss replacement, patching, shoulder work and striping along I-290 at the I-290 Eastbound Ramp and at Des Plaines Avenue in Chicago. |
|
Along I-90/94 (Dan Ryan) Landscaping and irrigation. |
Chicago 4/2009 5/2010 $0.573 |
IMPACT ON TRAVEL:
60A78 Landscaping and irrigation to create a gateway garden along I-90/94 (Dan Ryan) at 47th St. in Chicago. |
|
Along I-90/94 (Dan Ryan) Ornamental landscaping. |
Chicago 4/2009 5/2010 $0.471 |
IMPACT ON TRAVEL:
60A77 Replacing grassy area with ornamental landscaping to create a gateway garden along I-90/94 (Dan Ryan) at 63rd St. in Chicago. |
|
Along NB & SB I-94 (Dan Ryan) Landscaping |
Chicago 4/2009 5/2010 $0.513 |
IMPACT ON TRAVEL:
60A75 Installation of landscape and concrete items at designated gateways and corner gardens along NB and SB I-94 (Dan Ryan Exp.) and at 87th St. between State St. and Lafayette Ave. in Chicago. |
|
Along NB & SB I-94 (Dan Ryan) Landscaping |
Chicago 4/2009 5/2010 $0.62 |
IMPACT ON TRAVEL:
60A76 Installation of equipment, landscape and concrete items at designated gateways and corner gardens along NB and SB I-94 (Dan Ryan Exp.) and at 79th St. between State St. on the east side and Lafayette Ave. on the west side located in Chicago. |
|
Along NB & SB I-94 (Dan Ryan) Landscaping. |
Chicago 4/2009 5/2010 $0.59 |
IMPACT ON TRAVEL:
60A74 Installation of landscape and concrete items at designated gateways and corner gardens along NB and SB I-94 (Dan Ryan Exp.) and at 95th St. between State St. and Lafayette Ave. in Chicago. |
|
Along northbound I-94 from 31st st. to I-57 at IL-1 & to Martin Luther King Drive. Planting trees, shrubs, and perennial plants. |
Chicago 10/2008 11/2010 $1.747 |
IMPACT ON TRAVEL:
60A72 Planting various trees, shrubs and perennial plants along northbound I-94 (Dan Ryan Expressway) from 31st Street to I-57 at IL 1 (Halsted Street) and to Martin Luther King Drive (I-94/Bishop Ford Freeway) in Chicago. OTHER COMMENTS: Spring planting. |
|
Central Avenue Bridge deck replacement. |
Chicago 5/2009 10/2009 $2.671 |
IMPACT ON TRAVEL:
60640 Bridge deck replacement of the structure carrying Central Avenue over I-90 in Chicago. |
|
Cook County Intemittent resurfacing. |
Cook County 6/2009 8/2009 $0.855 |
IMPACT ON TRAVEL:
60G25 Intermittent resurfacing in various locations throughout Cook County. |
|
Dempster Street Resurfacing |
Skokie and Chicago 6/2009 11/2009 $1.737 |
IMPACT ON TRAVEL:
60E22 This project consists of resurfacing and related work on Dempster Street from U.S. Route 41 to McCormick Boulevard in Skokie and Chicago Avenue to Judson Avenue in Evanston for a total length of 2.01 miles. OTHER COMMENTS: Also in Skokie. |
|
I-90/94 (Dan Ryan) Gateway landscaping and irrigation. |
Chicago 4/2009 5/2010 $0.894 |
IMPACT ON TRAVEL:
60A79 Gateway landscaping and irrigation along I-90/94 (Dan Ryan) at 35th St. in Chicago. |
|
I-94 (Dan Ryan Exp) Planting various trees, shrubs and vines. |
Chicago 8/2008 12/2010 $1.424 |
IMPACT ON TRAVEL:
60A73 Planting various trees, shrubs and vines on southbound I-94 (Dan Ryan Exp.) from 31st St. to the I-57 interchange at Halsted Street and Bishop Ford Freeway to Martin Luther King Drive in Chicago. |
|
Northside Maintenance Yard at IL 43 & Il 19. Grading and drainage. |
Chicago 1/2009 6/2009 $0.244 |
IMPACT ON TRAVEL:
60E77 Grading and drainage at the Northside Maintenance Yard located at IL Route 43 (Harlem Avenue) and IL Route 19 (Irving Park Road) in Chicago. TRAFFIC ALERT: There is no impact to traffic. |
|
Ohio Street ramps on I-90/94 Resurfacing. |
Chicago 5/2009 7/2009 $0.248 |
IMPACT ON TRAVEL:
60F68 0.09 mile of milling and HMA surface on the Ohio Street ramps on I-90/94 (Kennedy Exp.) in Chicago. |
|
On Cicero Avenue from Irving Park Road to I-94 Resurfacing |
Chicago 5/2009 7/2009 $1.694 |
IMPACT ON TRAVEL:
60A50 1.69 miles of milling, HMA surface and other work on IL Route 50 (Cicero Avenue) from north of IL Route 19 (Irving Park Road) to I-94 (Edens Expressway) in Chicago. |
|
Pershing Road Bridge deck patching/protective shield. |
Chicago 5/2009 11/2009 $0.228 |
IMPACT ON TRAVEL:
60D78 Bridge deck patching and placement of permanent protective shield for the structure carrying 39th St. (Pershing Rd.) over South Racine Ave. and the Norfolk Southern Corporation RR in Chicago. |
|
Sayre Avenue Bridge over I-90 Bridge superstructure |
Chicago 6/2009 8/2010 $2.751 |
IMPACT ON TRAVEL:
60384 This project consists of 286 feet of bridge superstructure replacement, substructure repairs and underpass lighting for the Sayre Avenue Bridge over I-90 in Chicago. |
|
Structure carrying 115th St. (EB) over I-94 (Bishop Ford Exp.) Bridge beam and deck replacement. |
Chicago 10/2008 4/2009 $0.458 |
IMPACT ON TRAVEL:
60E12 Bridge beam replacement, partial deck replacement and beam straightening on the structure carrying 115th Street (eastbound) over I-94 (Bishop Ford Expressway) in Chicago. |
|
Touhy Avenue Milling and hot mix asphalt surfacing. |
Chicago/Park Ridge 6/2009 8/2009 $2.221 |
IMPACT ON TRAVEL:
60F48 3.04 miles of milling, hot mix asphalt surfacing and stiping on Touhy Avenue from Northwest Highway to North Central Avenue in Chicago and Park Ridge. OTHER COMMENTS: Also in Park Ridge |
|
Various routes. Cleaning and painting steel structures. |
Chicago 6/2009 11/2009 $0.879 |
IMPACT ON TRAVEL:
60G14 This contract consists of cleaning and painting various steel structures in Chicago. |
|
Western Avenue Resurfacing/utility adjustments. |
Chicago/Evergreen Park 5/2009 8/2009 $1.398 |
IMPACT ON TRAVEL:
60E29 1.52 miles of milling, patching, HMA surface, utility adjustment and other work on Western Ave. from 87th St. to 99th St. in Chicago and Evergreen Park. |