CONSTRUCTION UPDATE REPORT
DuPage
Effective: 02/07/12 4:26 PM
| LOCATION AND DESCRIPTION |
MUNICIPALITY START DATE EST. STOP DATE COST (millions) |
COMMENTS |
|
22nd Street Widening to add aditional lanes, traffic signal modernization |
Oakbrook and Oakbrook Terrace 8/2010 11/2011 $14.768 |
IMPACT ON TRAVEL:
60D12 1.29 miles of roadway reconstruction and widening, additional lanes, traffic signal modernization, interconnect and lighting on 22nd Street from IL 56 (Butterfield Road) to IL 83 (Kingery Highway) in Oakbrook and Oakbrook Terrace. |
|
55th Street Resurfacing, curb and gutter |
Downers Grove Township 4/2012 10/2012 $4.407 |
IMPACT ON TRAVEL:
63609 Project consists of PCC widening and HMA resurfacing of 55th Street, the complete removal and replacement of 400 ft of 55th Street with full depth HMA on existing horizontal alignment including combination concrete curb and gutter, PCC sidewalk, widening and resurfacing of 500 ft of Clarendon Hills Road and 900 feet of Cass Avenue, traffic signal removal and replacement at the 55th Street and Cass Avenue intersection and new traffic signals installed at the 55th Street and Clarendon Hill Road intersection in Downers Grove Township. |
|
75th Street Widening, resurfacing, sewers, traffic and roadway lighting |
Woodridge, Downers Grove, Darien 3/2012 10/2012 $11.168 |
IMPACT ON TRAVEL:
63632 Work will consists of roadway widening, resurfacing, construction of storm sewers, combination curb and gutter, sidewalk removal and replacement, traffic signal modernization and roadway lighting from I-355 to Lyman Avenue, which is located in the village of Woodridge, the village of Downers Grove and the city of Darien. |
|
91st Street Resurfacing and patching |
Burr Ridge 7/2011 4/20112/2011 $0.135 |
IMPACT ON TRAVEL:
63560 Project consists of HMA surface removal, HMA patching, HMA binder and surface courses, thermoplastic pavement marking and all other incidental items to complete the work on 91st Street from Madison Street to County Line Road in Burr Ridge. |
|
Ardmore Avenue Bridge rehabilitation |
Villa Park 10/2011 6/2012 $1.786 |
IMPACT ON TRAVEL:
63601 Project consists of bridge removal and replacement (17" depth) over the Chicago Central & Pacific Railroad, removal and replacement of the pavement approach, earth excavation, construction of concrete pavement, curb and gutter, pavement markings, erosion control and all other incidental items to complete the work on Ardmore Avenue, just south of IL Rte. 64 in Villa Park. OTHER COMMENTS: Bridge closed, follow posted detour. |
|
Devon Avenue Resurfacing, landscaping |
Lisle 7/2011 11/2011 $0.145 |
IMPACT ON TRAVEL:
63537 Project consists of earthwork, PCC sidewalks, curb and gutter removal and replacement, driveway pavement removal and replacement, drainage structure and storm sewer installation, drainage structure adjustments, segmental concrete block walls, installation of pipe handrails, placement of thermoplastic pavement markings, landscape restoration and all other incidental items to complete the work on Devon Avenue from Ogden Avenue to Middleton Avenue and at Schiesser Elementary School in Lisle. |
|
I-290 over Il 64 Bridge repair |
Elmhurst, Addison 4/2012 6/2012 $0.336 |
IMPACT ON TRAVEL:
60P79 Concrete repair of the structures carrying I-290 over IL 64 (North Ave.) in Elmhurst, over Mill Rd. in Addison and over Hillside Rd. in Proviso. OTHER COMMENTS: Also in Cook |
|
I-55 Guardrail installation at various locations |
Plainfield, Romeoville, Bolingbrook, Lemont, Burr Ridge and Darien. 9/2011 12/2011 $0.241 |
IMPACT ON TRAVEL:
60P47 Guardrail installation at various locations along I-55 from U.S. Route 6 to I-294 in Plainfield, Romeoville, Bolingbrook, Lemont, Burr Ridge and Darien in Will and DuPage Counties. OTHER COMMENTS: also in Will. |
|
IL 38 Widening, resurfacing, roadway lighting and traffic signals. |
Elmhurst 5/2012 10/2012 $1.785 |
IMPACT ON TRAVEL:
63610 Reconstruct the intersection at York Street and IL Rte. 38, pavement widening, resurfacing, storm sewer, roadway lightingand traffic signal modernization, located in the city of Elmhurst. |
|
IL 53 Reconstruction of additional lanes, bridge, and traffic signals. |
Itasca, Addison 9/2011 8/2013 $45.475 |
IMPACT ON TRAVEL:
60477 4.10 miles of roadway reconstruction, additional lanes, dry land bridge construction, traffic signal modernization and interconnect on IL Route 53 from Army Trail Road to the Elgin O'Hare Expressway in Itasca and Addison. |
|
IL 53 Pavement widening and bridge replacement. |
Itasca 1/2010 4/2012 $3.649 |
IMPACT ON TRAVEL:
62881 Pavement widening and reconstruction and bridge replacement of the structure carrying IL Route 53 over Spring Brook Creek located 0.7 mile south of IL Route 19 in the Village of Itasca. |
|
IL 56 Reconstruction, widening, resurfacing, traffic signals |
Warrenville 5/2011 11/2012 $26.019 |
IMPACT ON TRAVEL:
62420 3.13 miles of roadway reconstruction, widening, resurfacing and installation of storm sewers and traffic signals on IL Rte. 56 from west of IL Rte. 59 to east of Winfield Road in Warrenville to provide a four lane divided road with a barrier median. |
|
IL 56 (Butterfield Road) Pump station rehabilitation |
DuPage County 8/2011 12/2013 $2.075 |
IMPACT ON TRAVEL:
82726 Pump station rehabilitation of Pump Station No. 48 along IL 56 (Butterfield Road) in DuPage County. |
|
IL 64 (North Avenue) Building Demolition |
West Chicago 11/2011 5/2012 $0.32 |
IMPACT ON TRAVEL:
60L58 Building demolition on IL 64 (North Avenue) for the reconstruction of the portion from Kautz Road to IL 59 in West Chicago. |
|
IL 83 Installation of scour countermeasures. |
Villa Park, Elmhurst 1/2012 3/2012 $0.99 |
IMPACT ON TRAVEL:
60R01 Installation of scour countermeasures at the bridge carrying IL 83 over Salt Creek in Villa Park and Elmhurst. |
|
IL 83 (Kingery Highway) over IL 38 (Roosevelt Road) Bridge rehabilitation |
Oakbrook Terrace 8/2011 11/2011 $0.345 |
IMPACT ON TRAVEL:
60L52 Substructure repairs, beam repairs, diaphragm repairs and deck joint repairs to the structures carrying IL 83 (Kingery Highway) over IL 38 (Roosevelt Road) in Oakbrook Terrace. |
|
Joliet Street over Kress Creek Replace box culvert |
West Chicago 5/2012 8/2012 $0.47 |
IMPACT ON TRAVEL:
63561 Remove and replace in–kind an 8 foot by 12 foot dual cell box culvert carrying Joliet Street over Kress Creek and associated roadway work, located in the City of West Chicago. |
|
Kuhn Road Bike path, landscaping |
Caroll Stream 5/2012 7/2012 $0.449 |
IMPACT ON TRAVEL:
63590 Project consists of construction of an HMA bike path, landscaping, striping and all other incidental items to complete the work on Kuhn Road from Klein Creek to Lies Road in the village of Carol Stream. |
|
Madison Street Widening, resurfacing, curb and gutters, signalizaiton. |
Burr Ridge 4/2012 10/2012 $1.09 |
IMPACT ON TRAVEL:
63581 Project consists of widening, milling, resurfacing, adding median islands, adding curb and gutters, pavement striping, drainage improvements, providing signalization, and all other incidental items to complete the work on Madison Street at the intersection with Joliet Road in the village of Burr Ridge. |
|
Newport Boulevard Resurfacing, curb and gutter, sidewalks |
Bartlett 10/2011 6/2012 $0.965 |
IMPACT ON TRAVEL:
63604 Project consists of HMA removal, HMA binder and surface courses, Class D patches, sidewalk removal and replacement, detectable warnings, curb and gutter removal and replacement, thermoplastic pavement markings and all other incidental items to complete the work on Newport Boulevard between Stearns Road and Devon Avenue in the village of Bartlett. |
|
Old Great Western Trail Railroad Construction of 3 bridges and a pedestrian path. |
Lombard 5/2012 77/2012 $4.418 |
IMPACT ON TRAVEL:
63568 Project consists of the construction of three bridges and a pedestrian path and the project is located along the Old Great Western Trail Railroad between Grace Street and St. Charles Road in the Village of Lombard. |
|
Roselle Road Resurfacing and traffic signals, |
Roselle 11/2011 7/2012 $0.738 |
IMPACT ON TRAVEL:
63611 Project consists of pavement widening, HMA surface removal, resurfacing, traffic signal installation, replacement of curb and gutter, new curb inlets, thermoplastic pavement markings and reflectors, and all other incidental items to complete the work on Roselle Road at the intersection with Walnut Road in Roselle. |
|
Spring Road Resurfacing |
Elmhurst 8/2011 6/2012 $0.685 |
IMPACT ON TRAVEL:
63588 Project consists of roadway improvements including HMA milling, leveling binder, HMA surface course, Class D patches, curb and gutter replacement, sidewalk replacement, recessed epoxy pavement markings and all other incidental items to complete the work on Spring Road from Harrison Street to Vallette Street in the city of Elmhurst. |
|
US 34 @ North Aurora Road/Raymond Drive Intersection improvement |
Naperville 4/2012 7/2012 $0.501 |
IMPACT ON TRAVEL:
60L22 Intersection improvement for US 34 @ North Aurora Road/Raymond Drive in Naperville. |
|
Vallette Street Resurfacing, milling, and patches |
Elmhurst 5/2011 12/2011 $0.785 |
IMPACT ON TRAVEL:
63377 Improvement consists of 1.04 miles PCC pavement milling, HMA milling, leveling binder, Class D patches, HMA surface course, curb and gutter removal and replacement, sidewalk removal and replacement and recessed epoxy pavement marking on FAU 3824 (Vallette Street) from Spring Road to Poplar Avenue in Elmhurst. |
|
Various Scour countermeasures at 4 locations |
DuPage, kendall, Will Counties 11/2011 6/2012 $0.297 |
IMPACT ON TRAVEL:
60L65 Installation of scour countermeasures at four locations in DuPage, Kendall and Will counties. |
|
Various Traffic signal interconnect, pedestrian signals and loop detectors. |
Hanover Park, Naperville, Carol Stream, and Woodridge 11/2010 9/2011 $0.78 |
IMPACT ON TRAVEL:
63484 Traffic signal interconnect, pedestrian signals, and loop detectors on 75th Street in the Cities of Naperville and Woodridge from Ranchview Drive to Janes Avenue, and on County Farm Road from Birchbark Trail to Schick Road in Carol Stream, and on Army Trail Road from Spring Valley Road to Merbach Drive in Hanover Park. |
|
Various Resurfacing |
DuPage County 8/2011 12/2011 $1.189 |
IMPACT ON TRAVEL:
60N98 Intermittent pavement resurfacing at various locations in DuPage County. |
|
Various Sidewalk, curb and gutter |
Westmont 7/2011 12/2011 $0.408 |
IMPACT ON TRAVEL:
63132 Construct sidewalk, curb and gutter removal and replacement, driveway pavement removal and replacement at various locations in Westmont. |
|
Various areas bike path Bike path, signage |
Downers Grove 8/2010 6/2011 $0.146 |
IMPACT ON TRAVEL:
63451 Project consists of a HMA bike path, signage, ground restoration and all other incidental items to complete the work in various areas within the Village of Downers Grove. |
|
Various locations Noise Wall repairs |
Clarendon Hills, Itasca, Lansing, Roselle and Elk Grove 8/2010 4/2012 $0.151 |
IMPACT ON TRAVEL:
60H88 Noise Wall repairs at various locations in Clarendon Hills, Itasca, Lansing, Roselle and Elk Grove. OTHER COMMENTS: Also in Cook County. |
|
Various locations Bridge deck sealing |
Chicago, Hillside, Maywood, Oak Park, Bellwood, Forest Park, Elmhurst 5/2012 8/2012 $0.515 |
IMPACT ON TRAVEL:
60P61 Bridge deck sealing on various structures at various locations on Congress Parkway, Central Loop south overheads and I-290 overheads in Chicago, Hillside, Maywood, Oak Park, Bellwood, Forest Park and Elmhurst. OTHER COMMENTS: Also in Cook County in Chicago |
|
Various routes Building demolition |
Glen Ellyn, Hawthorn Woods, Elgin 5/2012 7/2012 $0.123 |
IMPACT ON TRAVEL:
60P53 Building demolition at various locations in various counties located in District One. Locations are:
Location #1: 22W312 IL Route 53, Glen Ellyn, IL 60137
Location #2: 3S540 Osage Drive, Glen Ellyn, IL 60137
Location #3: 7 Lisa Lane, Hawthorn Woods, IL 62234
Location #4: 568 Elm Grove Drive, Elgin, IL 60123
Location #5: 1113 Birchdale Drive, Elgin, IL 60123 OTHER COMMENTS: also in Lake and Kane County |
|
Various routes Patching, resurfacing |
Elmhurst, Westmont, Lombard, Hinsdale, Downers Grove, Clarendon Hills. 9/2011 12/2011 $1.9 |
IMPACT ON TRAVEL:
60P34 3.5 miles of patching, resurfacing and striping along various routes in Elmhurst, Westmont, Lombard, Hinsdale, Downers Grove and Clarendon Hills. |
|
Villa Avenue Resurfacing, lighting, signing, water main, streetscape. |
Villa Park 5/2011 11/2011 $4.234 |
IMPACT ON TRAVEL:
63379 Project consists of pavement reconstruction, resurfacing, curb and gutter, sidewalk, pavement marking, lighting, signing, storm sewers, water main, sanitary sewers, streetscape and all other incidental items to complete the work on FAU Rte. 2652 (Villa Avenue) from Madison Street to St. Charles Road in the Village of Villa Park. OTHER COMMENTS: Detour posted for one way southbound only. |
|
Washington Street and 75th Street. Widening and reconstruction. |
Naperville 5/2009 9/2011 $24.336 |
IMPACT ON TRAVEL:
63024 Widening and reconstruction of Washington Street and 75th Street, complete replacement of the existing 75th Street bridge over the West Branch of the DuPage River with a 3-span W 24 x 104 steel girder structure, 155'-7 1/2" long, construction of a precast pedestrian tunnel crossing under Washington Street, north of 75th Street and construction of the extension of the DuPage River Trail along the west bank of the west branch of the DuPage River. Project also includes traffic signals, lighting, storm sewer and six retaining walls, all located in Naperville. TRAFFIC ALERT: Multilane highway with permanent lane closures - traffic will be reduced from 4 lanes to one lane each direction. Motorists should expect delay and use caution when workers are present. |
|
Wesley Street and Manchester Road over the Union Pacific Railroad New bridge and new roadway reconstruction. |
Wheaton 10/2009 12/2011 $9.272 |
IMPACT ON TRAVEL:
83908 Project consists of the removal of several structures, including retaining walls and the construction of a single-span structure with reinforced concrete deck and composite steel girders on integral abutments, the reconstruction of roadway pavement with the addition of a new traffic signal and the rehabilitation of the Illinois Prairie Path Bridge on Wesley Street and Manchester Road over the Union Pacific Railroad all located in the City of Wheaton. |
|
West Avenue Roadway improvements, milling and resurfacing |
Elmhurst 8/2011 5/2012 $0.938 |
IMPACT ON TRAVEL:
63585 Project consists of roadway improvements including PCC pavement milling, HMA milling, leveling binder, HMA surface course, Class D patches, curb and gutter replacement, sidewalk replacement, proposed sidewalk, recessed epoxy pavement markings and all other incidental items to complete the work on West Avenue from First Street to Lake Street in the City of Elmhurst. |