CONSTRUCTION UPDATE REPORT

DuPage

Effective: 05/02/08 2:50 PM

LOCATION AND DESCRIPTION MUNICIPALITY
START DATE
EST. STOP DATE
COST (millions)
COMMENTS
39th Street from Main St. to Fairview Ave.

Resurfacing
Downers Grove
5/2008
7/2008
$0.352
IMPACT ON TRAVEL: 83935 0.58 mile grinding, level binder resurfacing, bituminous surface course, concrete curb replacement, utility adjustments, detector loop replacement and pavement marking on 39th Street from Main Street to Fairview Avenue in Downers Grove.
59th Street between Fairview Ave & Williams St.

Reconstruction and widening.
Westmont
5/2008
10/2008
$0.827
IMPACT ON TRAVEL: 83985 Reconstruction and widening of 59th Street including full-depth hot mix asphalt pavement, curb and gutter, closed drainage system, sidewalk, reconstructed driveway aprons, new roadway lighting, pavement markings, and all other incidental items to complete the work between Fairview Avenue and Williams Street in the Village of Westmont.
83rd St. from South Frontage Rd. to County Line Road.

Concrete block retaining wall, sidewalk, and sod restoration.
Burr Ridge
5/2008
9/2008
$0.31
IMPACT ON TRAVEL: 83996 Project consists of the installation of sidewalk, curb and gutter removal and replacement, driveway pavement removal and replacement, segmental concrete block retaining wall, sod restoration and all other incidental work to complete the project on 83rd Street from South Frontage Road to County Line Road in the Village of Burr Ridge.
Along Salt Creek

Bike Trails, Culvert Installation, Retaining Walls, and Signing.
Villa Park, Oak Brook
6/2007
7/2008
$3.89
IMPACT ON TRAVEL: 83714 Bituminous bike trails, construction of four prefabricated pedestrian truss bridges, retaining walls, culvert installation, and signing from the intersection of Villa Avenue and Second Street in Villa Park to the east end of Canterberry Lane in Oak Brook with the alignment generally following Salt Creek.
Bailey Road over the West Branch of the DuPage River

Superstructure replacement, bridge approach, sewers, ducat bank & vault package.
Naperville
3/2008
11/2008
$2.807
IMPACT ON TRAVEL: 83961 Superstructure replacement and substructure widening with concrete bridge approach slabs, storm sewer replacement, hot mix asphalt pavement surfacing, curb and gutter, sidewalk, pavement markings, installation of a duct bank and vault package on Bailey Road over the West Branch of the DuPage River in Naperville.
TRAFFIC ALERT: Please watch for signs before approaching bridge area.
Fullerton Ave. from Addison Rd to Villa Ave

Roadway reconstruction, traffic signals, drainage system, & landscaping.
Addison
5/2008
12/2008
$3.348
IMPACT ON TRAVEL: 83993 Project consists of roadway reconstruction, curb and gutter removal and replacement, full depth hot mix asphalt pavement, and enclosed drainage system, traffic signals, lighting, updated water main lateral crossings, pavement markings, landscaping restoration on Fullerton Avenue from Addison Road to Villa Avenue in the Village of Addison.
Grace Street from Fullerton Ave. to IL 64.

Resurfacing, pataching, drainage structures & markings.
Addison
5/2008
10/2008
$1.311
IMPACT ON TRAVEL: 83990 Project consists of the installation of new water main, curb and gutter repair, hot mix asphalt surface removal and resurfacing, pavement patching; adjustment of drainage structures, thermoplastic pavement markings on Grace Street from Fullerton Avenue to Illinois 64 in the Village of Addison.
Hawthorne Ln, Powis Rd and Pilsen Rd, Arbor Ave

Reconstruction
West Chicago
6/2007
11/2008
$10.38
IMPACT ON TRAVEL: 83873 Improvement consists of the reconstruction of Hawthorne Ln, Powis Rd and Pilsen Rd, resurfacing a portion of Hawthorne Ln and Arbor Ave and the construction of a shared use path along Hawthorne Ln in West Chicago
IL 19 from Walnut St. to Emmerson Ave.

Milling and hot mix asphalt resurfacing
Itasca
5/2008
6/2008
$0.18
IMPACT ON TRAVEL: 60A48 0.32 mile of milling and hot mix asphalt surface on IL 19 from Walnut Street to Emmerson Avenue in Itasca.
IL 38 ramp to southbound IL 83

Milling and hot mix asphalt surfacing.
Oakbrook Terrace
5/2008
7/2008
$0.66
IMPACT ON TRAVEL: 60D42 0.13 mile of milling and Hot Mix Asphalt surface on the eastbound IL 38 ramp to southbound IL 83 continuing southeasterly through Oakbrook Terrace.
IL 59 @ Batavia Road

Intersection improvements/traffic signals
Warrenville
5/2008
7/2008
$0.603
IMPACT ON TRAVEL: 60D51 Intersection improvements consisting of milling, hot mix asphalt surface and modernization of traffic signals on IL 59 at Batavia Road in Warrenville.
IL 83

Fiber optics communications network
Burr Ridge/Willowbrook
8/2007
5/2008
$0.397
IMPACT ON TRAVEL: 60A92 Fiber optics communications network on IL 83 from Bluff Road to Central Avenue in Burr Ridge and Willowbrook.
Janes Avenue from 71st St. to Lorraine Avenue.

Resurfacing, landscaping with irrigation, sidewalk.
Woodridge
5/2008
7/2008
$0.688
IMPACT ON TRAVEL: 83995 Project consists of concrete pavement removal and replacement with HMA pavement, milling and resurfacing, landscaped median with irrigation, curb and gutter removal and replacement, sidewalk and all other incidental items to complete the work on Janes Avenue from 71st Street to Lorraine Avenue in the Village of Woodridge.
Lively Blvd from Devon Ave to Touhy Ave

Reconstruction
Elk Grove Village
5/2007

$4.56
IMPACT ON TRAVEL: 83883 - Improvement consists of the reconstruction of Lively Blvd from Devon Ave to Touhy Ave in Elk Grove Village. Work will consist of pavement removal, construct storm sewers, Hot Mix Asphalt binder and surface courses, curb and gutter, PCC driveway, traffic signal improvements and lighting.
OTHER COMMENTS: Also in Cook
Madison Street

Milling and resurfacing, patching, curb & gutter.
Villa Park
10/2007
5/2008
$0.366
IMPACT ON TRAVEL: 83945 Reconstruction is complete -possible lane closure for cleanup.
Schick Road

Pavement resurfacing, curb and sidewalks, drainage, striping, and hot mix asphalt.
Bloomingdale
7/2007
5/2008
$0.74
IMPACT ON TRAVEL: 83901 Pavement resurfacing is complete - possible lane closure for cleanup.
Timber Edge Drive over Salt Creek

Bridge Rehabilitation
Oakbrook Terrace
3/2008
10/2008
$1.079
IMPACT ON TRAVEL: 83965 Project consists of sub and superstructure replacement and reconstruction including pavement removal, resurfacing of the approaches, aggregate subgrade, binder and surface course, concrete shoulders, sidewalk removal and replacement on Timber Edge Drive over Salt Creek in the City of Oakbrook Terrace.
Various

Pavement patching.
Various various
5/2008
8/2008
$1.861
IMPACT ON TRAVEL: 60E37 Pavement patching improvement along various routes in DuPage County.
Various locations in District One.

Structural repair of concrete on existing structures.
Various
4/2008
6/2008
$0.324
IMPACT ON TRAVEL: 60C36 Structural repair of concrete on existing structures at various locations in District One.
OTHER COMMENTS: Also in Cook County.
Various streets

Bikeway signage and striping.
Downers Grove
5/2008
6/2008
$0.82
IMPACT ON TRAVEL: 83972 14.30 miles bikeway signage and striping on various streets within the Village of Downers Grove.
Westmore-Meyers Road from Roosevelt Rd. to St. Charles Rd.

Roadway resurfacing
Lombard
8/2007
9/2008
$2.826
IMPACT ON TRAVEL: 83904 Roadway resurfacing, pavement patching, sidewalk & driveway, modernization of traffic signals with video detection, and markings on Westmore-Meyers Road from Roosevelt Road to St. Charles Rd in the Village of Lombard.
Williams Street between 63rd St & 59th St.

Reconstruction and Widening, drainage, & new roadway lighting.
Westmont
5/2008
9/2008
$0.772
IMPACT ON TRAVEL: 83986 Reconstruction and widening of Williams Street including full-depth hot mix asphalt pavement, new curb and gutter, closed drainage system installation, new sidewalk, reconstructed driveway aprons, installation of new roadway lighting between 63rd Street and 59th Street in the Village of Westmont.
Woodridge Drive

Resurfacing
Woodridge
5/2008
7/2008
$0.534
IMPACT ON TRAVEL: 83976 Project consists of resurfacing 5,433 feet of Woodridge Drive between 83rd Street and 75th Street including curb and gutter removal and replacement, patching, sidewalk removal and replacement, pavement markings and all other incidental items to complete the project in the Village of Woodridge.