CONSTRUCTION UPDATE REPORT
DuPage
Effective: 06/04/09 5:29 PM
| LOCATION AND DESCRIPTION |
MUNICIPALITY START DATE EST. STOP DATE COST (millions) |
COMMENTS |
|
Along I-290 from Higgins Rd. to I-90/94. Milling and rumble strips. |
Cook & DuPage Counties. 5/2009 6/2009 $0.373 |
IMPACT ON TRAVEL:
60F76 Milling of the rumble strips on the shoulders along I-290 from Higgins Road to I-90/94 in Cook and DuPage Counties. |
|
Along Salt Creek Bike Trails, Culvert Installation, Retaining Walls, and Signing. |
Villa Park, Oak Brook 6/2007 6/2009 $3.89 |
IMPACT ON TRAVEL:
83714 Bituminous bike trails, construction of four prefabricated pedestrian truss bridges, retaining walls, culvert installation, and signing from the intersection of Villa Avenue and Second Street in Villa Park to the east end of Canterberry Lane in Oak Brook with the alignment generally following Salt Creek. |
|
Bailey Road over the West Branch of the DuPage River Superstructure replacement, bridge approach, sewers, ducat bank & vault package. |
Naperville 3/2008 4/2009 $2.807 |
IMPACT ON TRAVEL:
83961 Superstructure replacement and substructure widening with concrete bridge approach slabs, storm sewer replacement, hot mix asphalt pavement surfacing, curb and gutter, sidewalk, pavement markings, installation of a duct bank and vault package on Bailey Road over the West Branch of the DuPage River in Naperville. TRAFFIC ALERT: Please watch for signs before approaching bridge area. |
|
Blackhawk Drive Widening, curb and gutter, new roadway lighting. |
Westmont 6/2009 6/2010 $2.151 |
IMPACT ON TRAVEL:
63121 Reconstruction and widening including full depth HMA pavement, curb and gutter, sidewalk, installation of new roadway lighting, closed drainage system installation, utility adjustments, pavement markings and all other incidental items to complete the project on FAU Route 3003 (Blackhawk Drive) from Chicago Avenue to Ogden Avenue in the Village of Westmont. |
|
Chicago Avenue/Maple Avenue Signal interconnect insntallation. |
Lisle 6/2009 11/2009 $0.696 |
IMPACT ON TRAVEL:
63107 3.77 miles signal interconnect installation on Chicago Avenue/Maple Avenue between Charles Avenue and Patton Drive and on College Road between Maple Avenue and Green Trails Road near Lisle. |
|
DuPage County Installing bicycle racks. |
DuPage County 6/2009 11/2009 $0.137 |
IMPACT ON TRAVEL:
63096 Project consists of furnishing and installing bicycle racks within 24 agencies/municipalities in DuPage County. |
|
Elgin O'Hare Expressway from US 20 (Lake Street) to I-290 Guardrail & rumble strips. |
Schaumburg, Hanover Park, & Itasca 5/2009 7/2009 $0.896 |
IMPACT ON TRAVEL:
60F77 Removal and replacement of guardrail, placement of impact attenuators and shoulder rumble strips on Elgin O'Hare Expressway from US 20 (Lake Street) to I-290 in Schaumburg, Hanover Park and Itasca. OTHER COMMENTS: Also in Cook. |
|
Elgin-O'Hare Expressway Resurfacing, pavement striping. |
Itasca 6/2009 9/2009 $0.961 |
IMPACT ON TRAVEL:
60G56 2.25 miles of milling, HMA surface and striping on Elgin-O'Hare Expressway from west of IL Route 53 (Rohlwing Road) to I-290 in Itasca. |
|
Heritage Parkway Asphalt bike path/3 path segments. |
Woodridge 5/2009 7/2009 $0.102 |
IMPACT ON TRAVEL:
63113 0.25 mile of 8' wide off-street asphalt bike path consisting of 3 path segments on Heritage Parkway between Timber Trails Road and Woodward Avenue in Woodridge. |
|
IL 19 over Meacham Creek. Precast concrete box culvert. |
Medinah 6/2009 9/2009 $1.446 |
IMPACT ON TRAVEL:
60A90 Removal of the existing structure and replacement with a double 12' x 9' precast concrete box culvert carrying IL 19 over Meacham Creek in Medinah. |
|
IL 38 over Kress Creek Box culvert deck patching and overlay. |
Winfield Township 5/2009 7/2009 $0.397 |
IMPACT ON TRAVEL:
60D82 Box culvert deck patching and overlay on the structure carrying IL 38 over Kress Creek in Winfield Township. |
|
IL 53 Resurfacing |
Lombard 5/2009 6/2009 $0.523 |
IMPACT ON TRAVEL:
60E20 1.04 miles of resurfacing on IL 53 from St. Charles Rd. to Madison St. in Lombard. |
|
IL 53 (Columbian Avenue) Bridge repair. |
Lombard 5/2009 6/2009 $0.85 |
IMPACT ON TRAVEL:
60E88 Bridge joint repair and bearing replacement at the structure carrying IL 53 (Columbian Avenue) over Great Northern Bike Trail in Lombard. |
|
IL 53 over east branch of the DuPage River. Bridge construction. |
Glen Ellyn/Lombard 5/2009 11/2009 $2.554 |
IMPACT ON TRAVEL:
60B95 Removal of the existing bridge and replacement with a 3-span, 2 @ 35'-0", 1 @ 30'-0" concrete slab structure carrying IL Route 53 over east branch of DuPage River (SN 022-0181) approach pavement reconstruction and other work, located in Glen Ellyn and Lombard. |
|
IL 59 Bridge deck repairs. |
Winfield/Wayne Townships 5/2009 11/2009 $0.912 |
IMPACT ON TRAVEL:
60C90 Bridge deck repairs on the four structures carrying IL 59 over the Union Pacific RR, Burlington Northern Santa Fe RR, IL 38 and Kress Creek in Winfield and Wayne Townships. |
|
Lemont Road/Naperville Road Modernization of traffic signals locations with traffic signal interconnect work. |
Lemont and Darien 5/2009 10/2009 $0.358 |
IMPACT ON TRAVEL:
63081 Project consists of the modernization of nine traffic signal locations with traffic signal interconnect work. Improvement will take place on Lemont Road from 97th Street to 83rd Street and on Naperville Road from Danada Drive to Roosevelt Road near Lemont and Darien. |
|
North Avenue Parkway enhancement. |
Elmhurst 9/2008 6/2009 $1.775 |
IMPACT ON TRAVEL:
63027 Parkway enhancement, installation of brick pavers, planting parkway trees, decorative light fixtures, GFI outlets at parkway trees, curb and gutter removal and replacement and PCC base course from 2nd Street to approximately 200' south of North Avenue in the City of Elmhurst. |
|
Prairie Avenue Resurfacing, new traffic signals. |
Downers Grove 6/2009 8/2009 $1.491 |
IMPACT ON TRAVEL:
63135 Project consists of full reconstruction, milling and resurfacing with full depth patches, new traffic signals, pavement markings and all other items to complete the work on FAU Route 2991 (Prairie Avenue) from Forest Avenue to Fairview Avenue in the Village of Downers Grove. |
|
Salt Creek Greenway Trail Bike trails, signs, retaining walls, landscaping, pedestrian bridges. |
Villa Park 6/2009 11/2009 $3.873 |
IMPACT ON TRAVEL:
63154 6,414.8 m of aggregate and HMA bike trails and 70 meters of on-street bike
trail including culverts, signs, retaining walls, pedestrian bridges and landscaping for the Salt Creek Greenway Trail from the intersection of
Elizabeth Drive and Addison Road in Wood Dale to the intersection of Villa
Avenue and 2nd Street in Villa Park. |
|
Six intersections along IL 83 from Finley Rd. to Westmore Rd./Meyers Rd. Traffic signal modernization. |
Lombard 5/2009 8/2009 $0.155 |
IMPACT ON TRAVEL:
60F54 Traffic signal modernization at 6 intersections along IL 83 from Finley Rd. to Westmore Rd./Meyers Rd. in Lombard. |
|
Sunset Drive west of Lincoln Ave. to Addison Ave. Resurfacing, patching, landsaping, and storm sewers. |
Villa Park 8/2008 6/2009 $1.048 |
IMPACT ON TRAVEL:
63015 Project consists of pavement removal, earthwork, HMA binder and surface course, pavement patching, curb and gutter removal and replacement, landscaping, erosion control, storm sewer, pavement marking and all other incidental items to complete the work on Sunset Drive west of Lincoln Avenue to Addison Avenue in Villa Park. |
|
Thorndale Avenue over Salt Creek. New 5 lane pavement section, bridge replacement. |
DuPage County 4/2009 11/2009 $3.117 |
IMPACT ON TRAVEL:
63077 Project consists of reconstruction of the existing pavement to a new 5 lane section, which includes full depth HMA pavement, aggregate subgrade, drainage improvements, landscaping, pavement marking and signing, bridge replacement and all other incidental items to complete the work on Thorndale Avenue over Salt Creek. |
|
US 34 (Ogden Avenue) Resurfacing, curb & gutter, striping. |
Downers Grove 5/2009 9/2009 $2.549 |
IMPACT ON TRAVEL:
60A85 4.10 miles of milling HMA surface, curb and gutter, striping and other work on U.S. Route 34 (Ogden Avenue) from I-355 to Warwick Avenue in Downers Grove. |
|
Various location Intermittent resurfacing |
DuPage County 6/2009 8/2009 $2.555 |
IMPACT ON TRAVEL:
60G20 Intermittent resurfacing in various locations throughout DuPage County. |
|
Washington Street and 75th Street. Widening and reconstruction. |
Naperville 5/2009 5/2011 $24.336 |
IMPACT ON TRAVEL:
63024 Widening and reconstruction of Washington Street and 75th Street, complete replacement of the existing 75th Street bridge over the West Branch of the DuPage River with a 3-span W 24 x 104 steel girder structure, 155'-7 1/2" long, construction of a precast pedestrian tunnel crossing under Washington Street, north of 75th Street and construction of the extension of the DuPage River Trail along the west bank of the west branch of the DuPage River. Project also includes traffic signals, lighting, storm sewer and six retaining walls, all located in Naperville. TRAFFIC ALERT: Multilane highway with permanent lane closures - traffic will be reduced from 4 lanes to one lane each direction. Motorists should expect delay and use caution when workers are present. |
|
West of I-355 over the East Branch of the DuPage River. Pedestrian bridge. |
Glen Ellyn 1/2009 5/2009 $0.387 |
IMPACT ON TRAVEL:
63069 Construction of a new pedestrian bridge with new asphalt approaches with aggregate shoulders located 1,000 feet west of I-355 over the East Branch of the DuPage River in Glen Ellyn. |