CONSTRUCTION UPDATE REPORT
Kane
Effective: 06/04/09 5:29 PM
| LOCATION AND DESCRIPTION |
MUNICIPALITY START DATE EST. STOP DATE COST (millions) |
COMMENTS |
|
Dunham Road over the Canadian National IL Central Railroad. Construction of wide flange steel beam bridges. |
Bartlett 4/2008 5/2009 $1.971 |
IMPACT ON TRAVEL:
83951 Construction of two adjacent three-span continuous rolled wide flange steel beam bridges that will carry future realigned Dunham Road over the Canadian National Illinois Central Railroad with bridge approaches west of Bartlett. |
|
Hankes Road between Braeburn Circle and IL 56. Resurfacing, shoulders, striping. |
Sugar Grove 10/2008 5/2009 $0.34 |
IMPACT ON TRAVEL:
63063 1.10 miles HMA surface removal and resurfacing including patching, shoulders, striping, reflective crack control and restoration on Hankes Road between Braeburn Circle and IL Route 56 in Sugar Grove. OTHER COMMENTS: Work to start Spring 2009. |
|
IL 25 (Broadway Avenue) Modernize traffic signals |
Aurora 6/2009 11/2009 $0.928 |
IMPACT ON TRAVEL:
60F99 Modernize traffic signals at 5 intersections along IL 25 (Broadway Avenue) from Indian Trail Road to Benton Street in Aurora. |
|
IL 25 (East Riverroad) Traffic signal modernization. |
Montgomery, St. Charles, Yorkville 6/2009 9/2009 $0.33 |
IMPACT ON TRAVEL:
60F98 Traffic signal modernization on IL 25 (East River Road) at Mill Street,
IL 38 at 14th Street/Bricher Road and IL 30 at IL 47/Baseline Road
in Montgomery, St. Charles and Yorkville, respectively. OTHER COMMENTS: Also in Kendall County. |
|
IL 31 from Prairie St. to New York St. Traffic signals and an interconnect system at 6 locations. |
Aurora 11/2008 8/2009 $0.778 |
IMPACT ON TRAVEL:
63053 Project consists of installing an interconnect system at 6 locations along IL 31 from Prairie Street to New York Street, which also includes traffic signal modifications at Benton Street, Downer Place, Galena Boulevard and New York Street in the City of Aurora. |
|
IL 31 south of Wing Street. Reconstruction, traffic signals, and sewers. |
Elgin 4/2009 11/2009 $1.431 |
IMPACT ON TRAVEL:
83943 Project consists of roadway reconstruction including resurfacing, widening, storm sewers, curb and gutters, modernizing and relocating traffic signals and all other incidental items to complete the work on IL Route 31 from approximately 1,000 feet south of Wing Street in the City of Elgin. |
|
IL 72 over I-90 Bridge deck. Bridge deck |
Gilberts 6/2009 9/2009 $0.67 |
IMPACT ON TRAVEL:
60D72 Bridge deck overlay on the structure carrying IL 72 over I-90 in Gilberts. |
|
Intersection of Randall Road and Keslinger Road. Advance warning signals. |
Geneva 4/2009 5/2009 $0.42 |
IMPACT ON TRAVEL:
63048 Work shall consist of the installation of advance warning signals at the intersection of Randall Road and Keslinger Road in Geneva. |
|
Municipal Drive/Galena Boulevard Resurfacing, widening, and resurfacing. |
Sugar Grove 9/2008 7/2009 $6.908 |
IMPACT ON TRAVEL:
63023 Widening, and extending with new construction and resurfacing Municipal Drive from the intersection of South Municipal Drive and Bastian Drive extending north to the intersection of Municipal Drive and Galena Boulevard. Galena Boulevard will be widened, extended with new construction and resurfaced from Municipal Drive to east of IL 47. The intersection of U.S. 30 at Municipal Drive and IL 47 at Galena Boulevard will also be improved, in Sugar Grove |
|
North arm of Brewster Creek on New Stearns. Construction of beam bridge with a concrete deck. |
South Elgin 4/2008 5/2009 $1.785 |
IMPACT ON TRAVEL:
83978 Construction of a single span wide flange beam bridge, with a poured concrete deck, a two span wide flange beam bridge, with a poured concrete deck over the north arm of Brewster Creek and the construction of roadway embankment in South Elgin. |
|
Oak Street (Pedestrian Bridge) Pre-fabricated pedestrian bridge structure. |
North Aurora 5/2009 9/2009 $0.232 |
IMPACT ON TRAVEL:
63097 Project consists of installation of bridge abutments, furnishing and installing a pre-fabricated bridge structure, installation of a concrete path with aggregate shoulders, site restoration and all other incidental items to complete the work on Oak Street (pedestrian bridge), 1,660 feet west of Randall Road to approximately 1,050 feet west of Randall Road over unnamed tributary in the Village of North Aurora. |
|
Randall Road at Silver Glen Road Bicycle/Pedestrian bridge. |
Township of St. Charles 4/2009 11/2009 $2.122 |
IMPACT ON TRAVEL:
83984 Project consists of the construction of a bicycle/pedestrian bridge over Randall Road at Silver Glen Road, structure is an eight span, 661' - 6 1/4" steel girders and beams with a reinforced concrete deck with concrete filled metal shell pile foundations, mechanically stabilized earth retaining walls with minor enhancements to the existing path and the extension of sewers located in the Township of St. Charles. |
|
Randall Road from Red Haw Lane to Silver Glen & IL 72 to Binnie Road. Traffic signals and cameras. |
South Elgin, Carpentersville 8/2008 8/2009 $1.749 |
IMPACT ON TRAVEL:
63011 Project consists of the installation of a fiber optic closed loop system including conduit, fiber optic cable, handholes, traffic signal equipment modifications, permanent traffic signal installation, video detection systems, uninterruptible power system, cameras and all other incidental items to complete the work on Randall Road from Red Haw Lane to Silver Glen and from IL 72 to Binnie Road in South Elgin and Carpentersville. |
|
Stearns Road New alignment from McLean Blvd to IL 25 |
Kane County 6/2009 5/2011 $23.349 |
IMPACT ON TRAVEL:
63075 Project consists of constructing Stearns Road on a new alignment from McLean Boulevard to IL Route 25 and the widening and resurfacing of IL Route 25 from the Chicago Central and Pacific Railroad to the IL Route 25 bridge over Brewster Creek, detention basins are proposed along the south side of new Stearns Road, new structures will be built to carry new Stearns Road over the Fox River and the north arm of Brewster Creek. |
|
Structure on US 30 Bridge deck patching/deck overlay |
Big Rock 6/2009 9/2009 $0.52 |
IMPACT ON TRAVEL:
60E63 Bridge deck patching and deck overlay on the structure carrying US 30 over the east and west branches of Big Rock Creek in Big Rock. |
|
US 20 (Lake Street) from Weld Road to Bluff City Blvd/Shales Parkway Guardrail & rumble strips |
Elgin 5/2009 6/2009 $0.378 |
IMPACT ON TRAVEL:
60F74 Removal and replacement of guardrail, placement of impact attenuators and shoulder rumble strips along US Route 20 (Lake Street) from Weld Road to Bluff City Blvd/Shales Parkway in Elgin. OTHER COMMENTS: Also in Cook |
|
US 30 Milling, resurfacing. |
Montgomery 6/2009 8/2009 $1.066 |
IMPACT ON TRAVEL:
60F27 2.78 miles of milling, hot mix asphalt surface and striping on US Route 30 from IL Route 47 to Orchard Road in Montgomery. OTHER COMMENTS: Also in Kendall County |
|
US 30 Bridge deck overlay. |
Montgomery 5/2009 7/2009 $0.476 |
IMPACT ON TRAVEL:
60D83 Bridge deck overlay on the structure carrying US 30 over River St. in Montgomery. OTHER COMMENTS: Also a part of Kendall County. |
|
US 30/IL 47 Milling, resurfacing. |
Sugar Grove 6/2009 8/2009 $2.174 |
IMPACT ON TRAVEL:
60G12 3.55 miles of milling, hot mix asphalt surfacing and striping on US 30/IL 47 from US 30/IL 56 to Kendall County Line and the ramps at IL 47 in Sugar Grove. |
|
Various routes Intermittent resurfacing |
Kane County 6/2009 8/2009 $0.5 |
IMPACT ON TRAVEL:
60G22 This contract consists of intermittent resurfacing located on various routes located in Kane County. |
|
Wheeler Road between Il 47 and Dugan Road. resurfacing, striping. |
Sugar Grove 10/2008 5/2009 $0.59 |
IMPACT ON TRAVEL:
63062 1.87 miles HMA surface removal and resurfacing including pavement patching, shoulders and striping on Wheeler Road between IL Route 47 and Dugan Road in Sugar Grove. OTHER COMMENTS: Work to start Spring 2009. |
|
Wood Street over the Burlington Northern Railroad & Indian Creek. Bridge rehabilitation |
Aurora 4/2009 12/2009 $3.19 |
IMPACT ON TRAVEL:
63080 Project consists of the removal of the existing four span steel girder bridge and construction of a three span bridge on two piers and integral abutments, raising the road profile to accommodate the Railroad, and all other incidental items to complete the work on Wood Street over Burlington Northern Railroad and Indian Creek in Aurora. |