CONSTRUCTION UPDATE REPORT

McHenry

Effective: 07/08/08 2:00 PM

LOCATION AND DESCRIPTION MUNICIPALITY
START DATE
EST. STOP DATE
COST (millions)
COMMENTS
Haligus Road

Hot mix asphalt pavement patching, resurfacing, and markings.
Lakewood
4/2008
6/2008
$0.327
IMPACT ON TRAVEL: 83979 1.58 miles hot mix asphalt pavement patching and resurfacing and pavement marking on Haligus Road from Lakewood Road to the north village limits of Lakewood.
Haligus Road from Algonquin Rd. to Reed Rd.

New roadway and widening, storm and drainage, temporary traffic signal installation.
Huntley
9/2007

$1.386
IMPACT ON TRAVEL: 83919 New roadway construction and existing roadway widening, storm and drainage structures, hot mix asphalt base, binder and surface courses, and temporary traffic signal installation on Haligus Road from Algonquin Road to Reed Road in Huntley.
Hanson Road from County Line Road to Edgewood Dr.

Pavement construction, sewers, bike path, and markings.
Algonquin
5/2008
9/2008
$0.664
IMPACT ON TRAVEL: 63001 Project consists of full-depth pavement construction of hot mix asphalt binder and surface courses, earth excavation and embankment, storm sewer installation, aggregate base course, curb and gutter, bike path, driveway, and pavement markings on Hanson Road from County Line Road to Edgewood Drive in the Village of Algonquin.
IL 173 over Piscasaw Creek

Roadway and bridge reconstruction
Chemung
8/2007
12/2008
$4.932
IMPACT ON TRAVEL: 60B83 Roadway and bridge reconstruction on IL 173 over Piscasaw Creek from White Oaks Road to Oak Grove Road located in Chemung.
TRAFFIC ALERT: Traffic is reduced to ONE lane throughout the project with use of temporary signals. Becks Road is closed at IL 173; please follow detour signs.
IL 176

Beam and bearing fabrication.
Marengo
12/2007
8/2008
$0.499
IMPACT ON TRAVEL: 60D29 Beam and bearing fabrication for the structure carrying IL 176 over the south branch of the Kishwaukee River located 0.56 miles east of Millstream Road in Marengo.
IL 176 over south branch of Kishwaukee River.

Bridge structure replacement and box culvert.
Unincorporated McHenry County east of Marengo.
4/2008
10/2008
$3.969
IMPACT ON TRAVEL: 62340 Removal and replacement of a steel plate girder bridge, and cast in place box culvert carrying IL 176 over the south branch of the Kishwaukee River and over the overflow site in unincorporated McHenry County east of Marengo.
TRAFFIC ALERT: Road is closed. Truck detour route is in effect. A small vehicle detour using Millstream Road, Garden Valley Road and North Union Road is in place.
IL 176 over the Kishwaukee River.

Bridge replacement.
Seneca Township
4/2008
11/2008
$2.088
IMPACT ON TRAVEL: 62336 Removal and replacement of existing bridge and profile adjustment for the structure carrying IL 176 over the Kishwaukee River beginning east of Franklinville Road continuing easterly into Seneca Township.
TRAFFIC ALERT: There will be one lane of traffic utilizing temporary signals throughout the duration of the project.
IL 176 over the south branch of Kishwaukee River.

Beam & bearing fabrication.
East of Franklinville Rd, east of Marengo
5/2008
8/2008
$0.93
IMPACT ON TRAVEL: 60D58 Beam and bearing fabrication for the structure carrying IL Route 176 over the south branch of Kishwaukee River located just east of Franklinville Road east of Marengo.
IL 23 over Coon Creek.

Precast, prestressed concrete deck beams.
Riley Tornship
7/2008
8/2008
$0.212
IMPACT ON TRAVEL: 60D92 Replacement of precast, prestressed concrete deck beams on the structure carrying IL Route 23 over Coon Creek located 0.6 miles south of I-90 in Riley Township
IL 31 @ Crystal Lake Avenue.

Intersection improvements.
Crystal Lake
5/2008
8/2008
$0.761
IMPACT ON TRAVEL: 60D52 0.26 mile of intersection improvements on IL 31 at Crystal Lake Avenue consisting of patching, milling and traffic signal modernization in Crystal Lake.
Intersection of US 12 & IL 31

Resurfacing of US 12 & bridge deck overlay of structure on US 12
Richmond
9/2007
8/2008
$2.184
IMPACT ON TRAVEL: 60A91 Intersection improvement at US 12 and IL 31, resurfacing of US 12 from IL 31 to IL 173, and bridge deck overlay of the structure carrying US 12 over North Branch Nippersink Creek all located in Richmond.
US 14 from Blue Jay Rd to Marawood Lane.

Shoulder widening and rumble strip installation.
Dunham and Hartland Townships.
5/2008
7/2008
$1.109
IMPACT ON TRAVEL: 60D37 Shoulder widening and rumble strip installation on US 14 from 125 feet west of Blue Jay Road to 177 feet east of Marawood Lane in Dunham and Hartland Townships.
US 14 just east of Blue Jay Rd. & west of IL 176.

Shoulder widening and rumble strip installation.
Crystal Lake & Woodstrock
5/2008
6/2008
$0.696
IMPACT ON TRAVEL: 60D38 Shoulder widening and rumble strip installation along US 14 approximately 660 feet east of Blue Jay Road and 935 feet west of IL 176 in Crystal Lake and Woodstock.
Various routes in McHenry County

Pavement patching.
McHenry County
5/2008
8/2008
$2.414
IMPACT ON TRAVEL: 60E36 Pavement patching improvement along various routes in McHenry County.