CONSTRUCTION UPDATE REPORT

North Cook

Effective: 01/28/10 8:31 AM

LOCATION AND DESCRIPTION MUNICIPALITY
START DATE
EST. STOP DATE
COST (millions)
COMMENTS
IL 19 (Irving Park Road)

Resurfacing, patching, sidewalks.
Streamwood
9/2009
5/2010
$0.411
IMPACT ON TRAVEL: 63213 0.68 mile pavement resurfacing including surface removal, patching, leveling binder, HMA surface, curb and gutter, PCC sidewalks, and pavement marking on Irving Park Road from Madison Drive to Bartlett Road in Streamwood.
9th Avenue

Resurfacing, patching, pavement striping and landscaping.
Maywood
5/2010
7/2010
$0.415
IMPACT ON TRAVEL: 63255 0.44 mile resurfacing including patching, surface removal, HMA surface, curb and gutter, driveways, striping, structure adjustments and landscaping on 9th Avenue from Roosevelt Road to Bataan Drive in Maywood.
Ballard Road

Resurfacing, striping.
Des Plaines, Glenview, Niles, Park Ridge
5/2010
8/2010
$0.756
IMPACT ON TRAVEL: 60H73 1.45 miles of milling, HMA surface, striping and other work on Ballard Road east of Rand Road to west of Greenwood Avenue in Des Plaines, Glenview, Niles, and Park Ridge.
Bridge carrying IL 58 (Golf Road ) over Poplar Creek.

Precast, prestressed Concrete deck beam.
Hoffman Estates
12/2009
9/2010
$0.919
IMPACT ON TRAVEL: 60F91 Precast, prestressed concrete deck beam replacement for the bridge carrying IL Route 58 (Golf Road) over Poplar Creek in the Village of Hoffman Estates.
Canfield Road

Resurfacing, patching, and pavement marking.
Norridge
6/2009
6/2010
$0.219
IMPACT ON TRAVEL: 63120 Project includes the resurfacing of Canfield Road from Lawrence Avenue to Foster Avenue, HMA surface removal, adjusting frames and grates, patching and pavement marking, located in the Village of Norridge.
Central Avenue

Pavement resurfacing, patching, and curb and gutter.
Glenview
10/2009
4/2010
$0.516
IMPACT ON TRAVEL: 63190 1.2 miles pavement resurfacing including surface removal, patching, combination curb and gutter, HMA surface and pavement marking on Central Avenue from Huber Lane to Harlem Avenue in Glenview.
Dundee Avenue

Resurfacing, patching, and pavement marking.
Barrington
5/2010
7/2010
$0.273
IMPACT ON TRAVEL: 63231 0.90 mile resurfacing including pavement removal, patching, HMA surface and pavement marking on Dundee Avenue between Lake Cook Road and IL Route 59 in Barrington.
Franklin Avenue

Resurfacing, patching, sidewalk, curb and gutter.
Franklin Park
4/2010
8/2010
$0.328
IMPACT ON TRAVEL: 63254 This project consists of (0.28 mile) of HMA surface removal, HMA leveling binder and surface course, pavement patching, area reflective crack control treatment, sidewalk, curb and gutter removal and replacement, thermoplastic pavement markings on FAU Route 3553 (Franklin Avenue) from Ruby Street to Rose Street in Franklin Park.
Frontage Road bridges over Palatine Road.

Bridge reconstruction.
Wheeling
6/2009
3/2010
$1.756
IMPACT ON TRAVEL: 60F60 Bridge reconstruction at the Frontage Road bridges over Palatine Road adjacent to the Canadian National Power Railroad, this contract includes bridge deck removal and replacement, furnishing and erecting of precast concrete beams, approach work, striping and other work, located in Wheeling.
Green Bay Road at Wilmette Ave., Central Ave, & Lake Ave.

Reconstruction, widening, traffic signals, & new railroad signals.
Wilmette
7/2008
6/2010
$1.37
IMPACT ON TRAVEL: 83999 Project consists of widening and resurfacing, traffic signal modifications at three intersections of Green Bay Road at Wilmette Avenue, Central Avenue and Lake Avenue, barrier medians, drainage modifications and new railroad signals to be installed by the Union Pacific Railroad all located in the Village of Wilmette.
OTHER COMMENTS: Intermittent day time lane closures.
Harvard Street

Resurfacing, sidewalk, watermain, pedestrian lighting, and landscaping.
Forest Park
6/2009
5/2010
$2.852
IMPACT ON TRAVEL: 63148 Project consists of full depth pavement removal, aggregate base with HMA binder and surface course, curb and gutter removal and replacement, sidewalk removal and replacement, watermain replacement, storm sewer, pedestrian lighting and landscaping on Harvard Street from east of Des Plaines Avenue to Harlem Avenue, located in the Village of Forest Park.
IL 19 (Irving Park Road)

Decorative Roadway Lighting
Streamwood.
4/2009
5/2010
$0.557
IMPACT ON TRAVEL: 63068 0.41 mile new decorative roadway lighting along IL Route 19 (Irving Park Road) from IL Route 59 to Madison Drive in Streamwood
IL 19 (Irving Park Road)

Resurfacing
Schiller Park
7/2009
5/2010
$0.535
IMPACT ON TRAVEL: 62666 0.86 mile of milling, HMA surface and striping on IL Route 19 from Des Plaines River Road to IL Route 171 (Cumberland Avenue) in Schiller Park and Chicago.
TRAFFIC ALERT: Striping to start in Spring.
IL 19 (Irving Park Road)

Traffic signal modernization and lighting.
Hanover Park
8/2009
10/2010
$1.119
IMPACT ON TRAVEL: 60G39 Traffic signal modernization and lighting on IL Route 19 (Irving Park Road) from west of Westview Plaza entrance to east of Kingsbury Drive in Hanover Park.
IL 21 (Milwaukee Avenue)

Widening and resurfacing, storm sewers, lighting and planting.
Niles
5/2009
8/2010
$4.564
IMPACT ON TRAVEL: 63094 Widening and resurfacing of IL Route 21 (Milwaukee Avenue) from Albion Avenue to Neva Avenue to include HMA surface removal, PCC base course, HMA binder and surface course, watermain and storm sewer and a streetscape improvement to include decorative pedestrian lighting, plantings and brick pavers from Harts Road to Neva Avenue, in Niles.
IL 21 from south of Willow Rd. to north of Sanders Rd. & over the Des Plaines River.

Reconstruction (add lanes), traffic signal, and bridge work.
Prospect Hts, Glenview, Mt. Prospect, & the Forest Preserve District
6/2008
7/2010
$13.325
IMPACT ON TRAVEL: 62387 1.37 miles of roadway reconstruction, adding lanes, traffic signal modernization and lighting on IL 21 from south of Willow Road to north of Sanders Road and replacement of the bridge carrying IL 21 over the DesPlaines River, all located in Prospect Heights, Glenview, Mount Prospect and the Forest Preserve District of Cook county.
TRAFFIC ALERT: Multilane highway with permanent lane closures - traffic will be reduced from 4 lanes to one lane each direction. Motorists should expect delays and use caution when workers are present.
IL 43/US 14 from US 14/IL 58

Resurfacing, and striping
Morton Grove and Niles
12/2009
6/2010
$1.566
IMPACT ON TRAVEL: 60H56 1.69 miles of milling, HMA surface and striping on IL 43/US 14 from US 14/IL 58 to north of US 14 and south of US 14 to Milwaukee Avenue within the Villages of Morton Grove and Niles.
IL 53

Resurfacing, patching, shoulder work, landscaping pipe underdrains.
Rolling Meadows
11/2009
8/2009
$2.6
IMPACT ON TRAVEL: 63243 3.0 miles resurfacing including patching, HMA overlay, shoulder work, landscaping, pipe underdrains, sidewalks and curb and gutter on IL Route 53 east and west frontage Roads from IL Route 62 to Kirchoff Road in Rolling Meadows.
IL 72

Milling and hot mix asphalt surface, striping and bridge deck work.
Des Plaines/Rosemont
6/2009
5/2010
$1.968
IMPACT ON TRAVEL: 60F40 1.82 miles of milling, HMA surface, striping and bridge deck patching and overlay work on IL 72 from Wolf Road to US 12/45 (Mannheim Road) and the bridge carrying IL 72 over Willow Creek in Des Plaines and Rosemont.
IL 72

Intersection improvements and traffic signal modernization.
Hoffman Estates
8/2009
5/2010
$0.825
IMPACT ON TRAVEL: 60E64 0.20 mile of intersection improvements and traffic signal modernization on IL Route 72 approximately 538’ west of Moon Lake Boulevard/Governor's Lane to east of Moon Lake Blvd/Governors Lane in Hoffman Estates.
Jackson Boulevard

Resurfacing, storm sewer, water main, pedestrian lighting and landscaping.
Forest Park
6/2009
5/2010
$1.182
IMPACT ON TRAVEL: 63134 Improvement consists of HMA pavement removal, aggregate base course preparation and repairs, HMA binder and surface course, curb and gutter replacement, storm sewer, water main, pedestrian lighting and landscaping on Jackson Boulevard from Des Plaines Avenue to Illinois Route 43 (Harlem Avenue) located in the Village of Forest Park.
Lehigh Road

Resurfacing, patching, curb and guttter, driveway, pavement markings.
Morton Grove
4/2010
6/2010
$0.393
IMPACT ON TRAVEL: 63237 This project consists of removing the existing surface course, pavement patching, intermittent curb and gutter replacement driveway restoration, HMA level binder and surface course, thermoplastic pavement markings and all other incidental items to complete the work on FAU Route 2786 (Lehigh Road) from Oakton Street to Lincoln Avenue in the Village of Morton Grove.
Montrose Avenue

Resurfacing, patching, and curb and gutter
Norridge
5/2010
7/2010
$0.244
IMPACT ON TRAVEL: 63256 This project consists of HMA surface removal, resurfacing with leveling binder and HMA surface course, replacement of defective curb and gutter, patching and all other incidental items to complete the work on FAU Route 2729 (Montrose Avenue) from east of Cumberland Avenue to Canfield Avenue in the Village of Norridge.
Natural Gas Piipeline Company of America Bike Path

10 foot wide bike path, culvert, pavement markings.
Hanover Park
4/2010
6/2010
$0.284
IMPACT ON TRAVEL: 63211 Project consists of (0.92 miles) 10 foot wide bituminous bike path, box culvert, paint and thermoplasitc pavement markings on the NGPL (Natural Gas Pipeline Company of America) Bike Path from Kingsbury Lane to West Branch of DuPage River in Hanover Park.
North Suburban Library Systems's parking lot/over Buffalo Creek

Shared-use Path/pedestrian truss bridge
Wheeling
9/2009
5/2010
$0.233
IMPACT ON TRAVEL: 63217 0.14 mile of a 10' wide asphalt shared-use path with a prefabricated pedestrian truss bridge adjacent to the North Suburban Library System’s parking lot to Hawthorne School crossing over Buffalo Creek between Dundee Road and Glendale Road in the Village of Wheeling.
Overlook Drive

Resurfacing, pavement markings
Golf
9/2009
5/2010
$0.21
IMPACT ON TRAVEL: 63191 Project consists of HMA pavement and base course removal, HMA binder course, HMA surface course, thermoplastic pavement markings and all other incidental items to complete the work on FAU 1311 (Overlook Drive) from Waukegan Road to Golf Road in the Village of Golf.
Sheridan Road

Resurfacing, water main replacement, and landscaping.
Evanston
9/2009
6/2010
$2.368
IMPACT ON TRAVEL: 63189 Pavement removal and resurfacing including relief sewer installation, water main replacement, curb and gutter replacement, pavement patching, landscaping, pavement markings and all other incidental items to complete the work on Sheridan Road from South Boulevard to Main Street in the City of Evanston.
Touhy Avenue

Resurfacing
Lincolnwood and Skokie
5/2010
7/2010
$0.627
IMPACT ON TRAVEL: 60H66 0.35 mile of milling, HMA surface and other work on Touhy Avenue approximately 45 feet w of IL 50 (Cicero Ave.) to w of US 41 (Lincoln Ave.) & w of Lawndale Ave in Lincolnwood and Skokie.
Tower Road

Resurfacing, sidewalks, curb and gutter and pavement markings.
Winnetka
4/2010
6/2010
$0.384
IMPACT ON TRAVEL: 63241 0.80 mile resurfacing including pavement grinding, patching, HMA surface,sidewalks, curb and gutter and pavement marking on Tower Road from Hibbard Road to Sheridan Road (excluding intersections at Green Bay and Sheridan Roads) in Winnetka.
Twiggs Park between Simpson St. and Green Bay Road.

10' wide bituminous bike path/sidewalks/lightpoles.
Evanston
3/2009
3/2010
$0.341
IMPACT ON TRAVEL: 63089 Project consists of the reconstruction of 2,168 feet of a 10-foot wide bituminous bike path, construct two connecting spurs to existing limestone paths and 5-foot wide sidewalks, installation and relocation of light poles, sidewalk removal and replacement and drainage improvements within Twiggs Park located between Simpson Street and Green Bay Road in Evanston.
US 12 (Rand Road), IL 53/68 (Dundee Road)

Lighting and traffic signal modernization.
Palatine
6/2009
5/2010
$2.159
IMPACT ON TRAVEL: 60F87 Lighting and traffic signal modernization on US 12 (Rand Road) from Old Hicks Road to West Frontage Road/IL 53 West Ramp and on IL 53/68 (Dundee Road) from Lynda Drive to IL 53 West Ramp in Palatine.
US 12/45 (Mannheim Road) over Franklin Ave. and Canadian Pacific RR.

Beam fabrication.
Franklin Park
11/2009
8/2010
$3.837
IMPACT ON TRAVEL: 60I21 Beam fabrication for the structure on US Routes 12/45 (Mannheim Road) over Franklin Avenue and Canadian Pacific Railway in Franklin Park.
Various locations in Cook and Lake Counties.

Pavement patching.
Cook and Lake County
8/2009
4/2010
$0.589
IMPACT ON TRAVEL: 60G28 Intermittent pavement patching at various locations in Cook and Lake Counties on interstate ramps and mainline.
OTHER COMMENTS: Also in Lake County.
Various locations in Cook County

Cleaning and painting steel structures
Various
5/2009
5/2010
$0.79
IMPACT ON TRAVEL: 60F02 Cleaning and painting steel structures at various locations in Morton Grove, Chicago, Niles, Jefferson & West Chicago Townships.
Various locations.

Cleaning and painting existing steel structures.
Algonquin, New Lenox, Chicago, Wilmington, McHenry, Wauconda, Naperville, Hanover and Custer Townships.
9/2009
10/2010
$0.809
IMPACT ON TRAVEL: 60F04 This contract consists of cleaning and painting existing steel structures in various locations in the Villages of Algonquin and New Lenox; and in the cities of Chicago, North Chicago, West Chicago, and Wilmington; and in McHenry, Wauconda, Naperville, Hanover and Custer Townships.
OTHER COMMENTS: Various Counties for mentioned locations.
Various routes in various locations.

Traffic signal modernization.
Various locations
6/2009
6/2010
$0.659
IMPACT ON TRAVEL: 60G04 Traffic signal modernization at 8 intesections on various routes in various locations.
Waukegan Road

Roadway lighting
Morton Grove
4/2010
8/2010
$0.434
IMPACT ON TRAVEL: 63099 New roadway lighting to be installed on Waukegan Road from Main Street to Dempster Street including the installation of foundation, poles, luminaires, unit duct, lighting controller, restoration and all other incidental items to complete the project in the Village of Morton Grove.
Wolf Road

Installation of concrete median, curb and gutter, sidewalks, lighting, traffic signals, and push buttons.
Northlake
4/2010
8/2010
$0.271
IMPACT ON TRAVEL: 63222 This project consists of the installation of concrete median, combination concrete curb and gutter, PCC sidewalks, concrete base course, HMA binder and surface course, lighting, traffic signal modifications, pedestrian push button controllers and thermoplastic pavement markings on FAU Route 2690 (Wolf Road) from Country Club Drive to Whitehall Avenue in Northlake.