CONSTRUCTION UPDATE REPORT

South Cook

Effective: 03/31/14 7:49 AM

LOCATION AND DESCRIPTION MUNICIPALITY
START DATE
EST. STOP DATE
COST (millions)
COMMENTS
US 30

Channelization and traffic signal modernization
Olympia Fields
4/2014
7/2014
$1066293.49
IMPACT ON TRAVEL: 60T19 Channelization and traffic signal modernization along US 30 in Olympia Fields.
112th Street and 115th St.

Sidewalks, curb and gutter.
Worth
9/2013
6/2014
$0.234
IMPACT ON TRAVEL: 63836 This project consists of PCC sidewalks, detectable warnings, pavement markings, curb and gutter removal and replacement, catch basins, pipe culverts and storm sewers, located on 112th Street from Oak Park Avenue to Nashville Avenue and 115th Street from Oak Park Avenue to Ridgeland Avenue in the Village of Worth.
207th St.

Sidewalks, street lighting, and signing,
Olympia Fields
4/2014
8/2014
$0.528
IMPACT ON TRAVEL: 63841 Project consists of 5' wide PCC sidewalks, detectable warnings, pavement markings, street lighting, signing, restoration and all other incidental items to complete the work on 207th Street from Governor's Highway to Olympian Way in the Village of Olympia Fields.
71st St.

Construction of a grade separation underpass
Bridgeview
7/2012
5/2014
$16.108
IMPACT ON TRAVEL: 63556 Project consists of the construction of a grade separation underpass at the existing CSX Railroad tracks, construction of retaining walls, 71st Street will be reconstructed and depressed under the new bridge with a portion of Ferdinand Avenue requiring reconstruction, utility relocation, storm sewers, detention pond expansion, curb and gutter, sidewalks, lighting and landscaping, from east of 78th Avenue to Beloit Avenue, in the Village of Bridgeview. (Please contact Timothy Whalen of AECOM at 312-938-0300 regarding questions).
75 locations

LED installation & traffic signals.
South Cook County
4/2014
10/2014
$0.1029
IMPACT ON TRAVEL: 60W81 LED installation, traffic signal modernization at a75 locations in South Cook County.
76th Avenue

Storm sewers, resurfacing.
Palos Heights
5/2013
5/2014
$0.888
IMPACT ON TRAVEL: 63747 This project consists of earth excavation, storm sewers and drainage structures, aggregate subgrade improvement, HMA binder and surface course, located on 76th Avenue from 131st Street to 127th Street in the City of Palos Heights.
80th Avenue

Resurfacing, patching, and sidewalks.
Tinley Park
5/2014
8/2014
$0.278
IMPACT ON TRAVEL: 63852 This project consists of HMA surface removal, patching, HIP recycling, HMA surface course, PCC sidewalks, detectable warnings, pavement markings and restoration located on 80th Avenue from 191st Street to South Village limits in the Village of Tinley Park.
Ashland Avenue

New storm sewer
Dixmoor, Riverdale
10/2013
11/2014
$0.268
IMPACT ON TRAVEL: 60R82 Installation of new storm sewer at the pump station on Ashalnd Avenue to the Little Calumet River in Dixmoor and Riverdale.
Ashland Avenue

Resurfacing, guardrail, traffic signals
Blue Island, Dixmoor, Riverdale
5/2012
5/2014
$2.787
IMPACT ON TRAVEL: 60P64 Improvements to Ashland Avenue consisting of milling, resurfacing, storm sewer installation, guardrail, traffic signals, striping and other work from Broadway Street to Thornton Road in Blue Island, Dixmoor and Riverdale.
Chicago Road

Resurfacing
Dolton, South Holland, Thornton
6/2013
4/2014
$2.239
IMPACT ON TRAVEL: 60B56 4.39 miles of resurfacing on Chicago Road from Lincoln Avenue to Wate Street in Dolton, South Holland and Thornton
Claire Boulevard

Resurfacing, curb & gutter
Robbins
10/2013
6/2014
$0.327
IMPACT ON TRAVEL: 63845 This project consists of HMA surface removal, curb and gutter removal and replacement, sidewalk removal and replacement, polymerized leveling binder, HMA surface course, structure adjustments and pavement markings located on Claire Boulevard from 139th Street to Kedzie Avenue in the Village of Robbins.
East Ave.

Resurfacing, crack control and patching.
Berwyn
8/2013
6/2014
$1.932
IMPACT ON TRAVEL: 63837 Project consists of HMA surface removal, HMA resurfacing with leveling binder, area reflective crack control and patching,on East Ave. From 31st Street to Cermak Road in the City of Berwyn.
Harwood Avenue

Resurfacing and channelization
Homewood


$0.297
IMPACT ON TRAVEL: 60T99 0.52 mile of channelization and resurfacing on Harawood Avenue from 183rd Street to Elm Road and from Elm Road to Dizie Highwaiy in Homewood.
I-290 Interchange

Two architectural monuments and landscaping
Hillside
5/2013
7/2014
$0.166
IMPACT ON TRAVEL: 63783 This project consists of construction of two architectural monuments including structural excavation, concrete foundations, brick and stone veneer, restoration and landscaping located at the I-290 interchange in the Village of Hillside.
I-80

Installation of fiber optic cable.
Tinley Park and Country Club Hills.
5/2013
7/2014
$0.595
IMPACT ON TRAVEL: 60V81 Installation of fiber optic cable and associated appurtenances along I-80 from east of 80th Ave. to I-294 in Tinley Park and Country Club Hills.
IL 83 (147th St.)

Roadway reconstruction, lighting and traffic signals
Midlothian, Dixmoor, Harvey, Posen
3/2013
10/2014
$0.22
IMPACT ON TRAVEL: 60M57 2.34 miles of roadway reconstruction, lighting and traffic signal installation on IL 83 (147th St.) from Kedzie Ave. to Western Ave. (Dixie Highway) in Midlothian, Harvey, Posen and Dixmoor.
IL 83 (Sibley Blvd.)

Resurfacing, traffic signal installation
harvey
6/2013
5/2014
$0.404
IMPACT ON TRAVEL: 60T92 Traffic signal installation timing/progression, resurfacing and other related work on IL 83 (Sibley Blvd.) at the intersection of Wallace St. in Harvey.
Jackson Avenue

Resurfacing, curb and gutter, patches and markings
South Chicago Heights
10/2013
5/2014
$0.264
IMPACT ON TRAVEL: 63844 This project consists of 0.71 mile of resurfacing including leveling binder and surface course , curb and gutter repair, patches and pavement markings located on Jackson Avenue from Sauk Trail to 26th Street in the Village of South Chicago Heights.
Kedzie Ave.

Removal and replacement of sidewalks
Merrionette Park
5/2014
6/2014
$97844.5
IMPACT ON TRAVEL: 63884 Removal and replacement of sidewalks located on Kedzie Ave. from Meadow Ln. to 118th St. and 115th St. from west of Troy Dr. to east of Whipple St. in the Village of Merrionette Park.
Maple Avenue

Resurfacing, driveways, patching and sewer.
Brookfield
5/2013
5/2014
$0.635
IMPACT ON TRAVEL: 63762 Project consists of resurfacing, intermittent replacement of defective curb and gutter, driveways, and sidewalks; combined sewer repairs, pavement patching, HMA surface removal, resurfacing with level binder and HMA surface course, pavement striping, restoring the parkways with topsoil and sod and all other incidental items to complete the work on Maple Avenue from 47th Street to Burlington Avenue in the Village of Brookfield.
New Ave.

Milled rumble strip and guardrail replacement.
Lockport, Romeoville, Lemont
4/2014
7/2014
$1529805.53
IMPACT ON TRAVEL: 60R86 Milled rumble strip and guardrail replacement on New Ave. from the Cook County Line to IL 171 (Archer Ave.)
Orchard Drive

Traffic signal replacement, drainage
Park Forest
4/2012
6/2014
$7.216
IMPACT ON TRAVEL: 63635 Project consists of curb and gutter removal and replacement, traffic signal removal and replacement, drainage improvements, sidewalk removal and replacement, HMA pavement, pavement marking, parkway restoration, and all other incidental items to complete the work on FAU Route 2836 (Orchard Drive) from Sauk Trail to US Route 30 in the Village of Park Forest.
Pulaski Road

Street lighting
Alsip
11/2012
6/2014
$0.867
IMPACT ON TRAVEL: 63726 This project consists of street lighting improvements, including aluminum street lights and mast arms and luminaires, located on Pulaski Road from 123rd Street to 115th Street in the Village of Alsip.
Southern Cook County

LED installation
Southern Cook County
5/2014
12/2014
$0.81
IMPACT ON TRAVEL: 60W85 LED installation at various locations in southern Cook County.
Thorn Creek

2 segments of bicycle trail, pedestrian signal heads, signals,
Glenwood, Chicago Heights
10/2013
12/2014
$4.637
IMPACT ON TRAVEL: 63769 Project consists of the construction of 2 segments of bicycle trail including drainage improvements, grading, seeding, bridge structures, retaining walls, pavement marking, pedestrian signal heads, erosion control, tree removal, traffic control and all other incidental items to complete the work on Thorn Creek Trail from 26th Street to 183rd Street within the City of Chicago Heights and the Village of Glenwood.
Timber Line Drive

Alignment of Timber Line Drive, pedestrian path, landscaping
Lemont
6/2013
7/2014
$0.674
IMPACT ON TRAVEL: 63804 Project consists of relocating the alignment and the reconstruction of Timber Line Drive, construct pedestrian pathways, lighting and landscaping, from 127th Street for 0.08 miles in Centennial Park, located in the Village of Lemont.
US 45

Widening to add lanes
Orland Park, Orland Hills, Tinley Park
10/2013
7/2015
$29.686
IMPACT ON TRAVEL: 60F05 2.80 miles of additional lanes, widening and reconstruction on US 45 from 159th St. to 179th St. in Orland Park, Orland Hills, and Tinley Park.
US 45 (LaGrange Rd.)

Adding lanes, retaining walls, signals, erosion control.
Orland Park
10/2013
7/2015
$26.92
IMPACT ON TRAVEL: 60M61 1.93 miles of additional lanes, retaining walls, medians, sidewalk, bike path, drainage systems, guardrails, retaining walls of various types, traffic signals, street lighting, erosion and sediment control, pavement marking, signing, landscaping, and traffic Control on US 45 (La Grange Rd.) from 143rd St. to 159th St. in Orland Park.
US 45 (LaGrange Rd.)

Adding lanes, retaining walls, resurfacing.
Orland Park, Palos Park
10/2013
7/2015
$32.92
IMPACT ON TRAVEL: 60M62 1.79 miles of additional lanes, drainage work retaining walls, bike path, drainage systems, guardrails, retaining walls of various types, traffic signals, street lighting, erosion and sediment control, pavement marking, signing, landscaping, and traffic control on US 45 (La Grange Rd.) from 131st St. to 143rd St. in Orland Park and Palos Park.
Various locations

Concrete barrier wall and bridge repairs.
District One/various counties
5/2014
6/2014
$0.3
IMPACT ON TRAVEL: 60W86 Concrete barrier wall and bridge repairs at various locations in various counties in District One.
Various locations in Cook, DuPage and Kane Counties

Wrong way signage and pavement marking on ramps
Bedford Pk., Melrose Pk., Calumet City, Elgin, Downers Grove, McCook, Lyons, Lombard, Bartlett, Palos Pk., Hanover Pk., Elmhurst, Lisle, Streamwood, Summit, Stone Park, Schaumburg, Oak Brook, Northlake, Sugar Grove
5/2014
7/2014
$172316
IMPACT ON TRAVEL: 60X31 Wrong way signage and pavement marking on ramps at various locations in Cook, DuPage and Kane counties.
Various locations in southern Cook County

LED installation
Blue Island, Calumet Pk., Chicago, Dolton, Alsip, Worth, Robbins, Riverdale, S. Holland, Harvey, Phoenix
6/2014
11/2014
$926328
IMPACT ON TRAVEL: 60X24 LED installation in various locations in southern Cook County
Various routes

Parkway restoration, resurfacing, and sewers.
Country Club Hills
10/2013
6/2014
$0.401
IMPACT ON TRAVEL: 63850 This project consists of HMA surface removal, pavement patching, leveling binder, HMA binder and surface courses, sidewalk repairs, curb and gutter repairs, structure adjustments, storm sewer installation, pavement markings and parkway restoration located on Various Routes within the City of Country Club Hills.