Preparation Stage – Fall 2005 – Winter 2006
-
Water main construction
-
Utility adjustments
Season One – 2006 Norfolk
Southern Railroad to the Stone Arch Bridge Work begins
March 20, 2006. (Work suspends late fall 2006).
Stage One - March 2006
-
Close the center turn lane and passing lanes and
build the main storm sewer line.
-
Construct the median in the center turn lane at
the Norfolk Southern Railroad crossing.
-
Traffic will use the driving lanes.
Stage Two - April – July 2006
 
Stage Three - August – November 2006
 
Stage Four - November 2006
Season Two – 2007 Pine Street
to the Norfolk Southern Railroad
Stage One - March 2007
Stage Two A – April - June 2007
Norfolk Southern Railroad to Franklin Street
 
-
Build the north half of Main Street.
-
Build North Walnut Street improvement
-
One lane of traffic for each direction of
traffic will be provided on the south half of Main Street.
Stage Two B – June – July 2007
Franklin Street to the Pine Street
 
Stage Three A – July 2007
Pine Street to Franklin Street
 
Stage Three B – July - November 2007
Franklin Street to the Norfolk Southern Railroad
 
Stage Four – November 2007 Pine Street
to the Norfolk Southern Railroad
|