Invoice Archive
Contract Number
&
Estimate Numbers are listed below
Go to Current Estimate for this Contract Number
|
Contractor Invoice
Previous Report 06/11/2010
| DOT Vendor: |
C13200 |
|
Contract: |
66908 |
| IL Project: |
|
From Date: |
05/29/2010 |
| Route: |
FAI 80 |
|
|
|
| Section: |
06-7BR&BR-1,7VB-M,6BR&6,7ETC |
To Date: |
06/11/2010 |
| Project: |
BRF-NHI-0802/065/062 |
State Job: |
C-93-049-09 |
| Letting Date: |
11/06/2009 |
Dist/Cnty: |
03 - 011 (BUREAU )
|
| Airport: |
06-7BR&BR-1,7VB-M,6BR&6,7ETC |
State Job: |
C-93-049-09 |
| Scope: |
FAI-80, FROM E OF I-180 TO W OF IL 89.
|
|
|
|
Payee: |
D CONSTRUCTION INC |
1488 S BROADWAY COAL CITY , IL 60416
|
|
|
|
|
|
|
| Percent Completed: 23.63% |
Contract Awarded
Amount |
Additions |
Deductions |
Total Adjusted
Contract Value |
Total Amount
Due to Date |
| 22,241,876.65 |
145,988.50 |
26,650.75 |
22,361,214.40 |
5,283,483.25 |
|
Total retainage incld this est held by IDOT:
|
|
|
0.00
|
| Total
due after retainage: |
|
|
5,283,483.25 |
| Total
paid this estimate: |
|
|
5,283,483.25 |
|
Previous payments to contractor: |
|
|
-4,753,000.35 |
|
Payment to contractor this estimate: |
|
| 530,482.90 |
| |
|
Voucher # CC27015 | Date: 06/15/2010 |
|
1
of 1
|
530,482.90 |
|
---------------------------------------------------------------------------------------------------------------------------------------------- |
|
|
|
Pay Estimate Number: 05 |
Total: |
530,482.90 |
Report of Resident Engineer
Completed Work-In Place
For This Estimate Only
|
|
|
PAY ITEM |
QUANTITY |
PAYMENT |
|
Number |
Description |
Awarded |
Net of Adds/
Deducts |
Total Adjusted |
Completed Prior Est. |
Completed to Date |
This Estimate |
$ Unit Price |
$ This Estimate |
| X7010805 |
TR C-PROT 701401 SPL |
1.000 |
0.000 |
1.000 |
0.330 |
0.350 |
0.020 |
1.00 |
0.02 |
| X8410118 |
MAINT TEMP LIGHT SYS |
1.000 |
0.000 |
1.000 |
0.120 |
0.160 |
0.040 |
10,000.00 |
400.00 |
| Z0013798 |
CONSTRUCTION LAYOUT |
1.000 |
0.000 |
1.000 |
0.120 |
0.160 |
0.040 |
70,000.00 |
2,800.00 |
| 50200100 |
STRUCTURE EXCAVATION |
2,497.000 |
0.000 |
2,497.000 |
139.740 |
497.780 |
358.040 |
22.00 |
7,876.88 |
| 50300225 |
CONC STRUCT |
1,969.000 |
0.000 |
1,969.000 |
0.000 |
264.600 |
264.600 |
590.00 |
156,114.00 |
| 50300280 |
CONCRETE ENCASEMENT |
61.000 |
0.000 |
61.000 |
12.480 |
18.040 |
5.560 |
300.00 |
1,668.00 |
| 50800205 |
REINF BARS, EPOXY CTD |
863,780.000 |
0.000 |
863,780.000 |
0.000 |
27,015.320 |
27,015.320 |
1.40 |
37,821.45 |
| 51201600 |
FUR STL PILE HP12X53 |
4,486.000 |
0.000 |
4,486.000 |
354.000 |
1,994.000 |
1,640.000 |
45.00 |
73,800.00 |
| 51201800 |
FUR STL PILE HP14X73 |
13,393.000 |
0.000 |
13,393.000 |
0.000 |
3,572.600 |
3,572.600 |
58.00 |
207,210.80 |
| 51202305 |
DRIVING PILES |
17,879.000 |
0.000 |
17,879.000 |
218.200 |
4,391.460 |
4,173.260 |
0.01 |
41.73 |
| 51203600 |
TEST PILE ST HP12X53 |
8.000 |
0.000 |
8.000 |
1.000 |
4.000 |
3.000 |
3,500.00 |
10,500.00 |
| 51203800 |
TEST PILE ST HP14X73 |
20.000 |
0.000 |
20.000 |
0.000 |
6.000 |
6.000 |
3,500.00 |
21,000.00 |
| 51205200 |
TEMP SHT PILING |
523.000 |
0.000 |
523.000 |
0.000 |
210.000 |
210.000 |
25.00 |
5,250.00 |
| 70100420 |
TRAF CONT-PROT 701411 |
1.000 |
0.000 |
1.000 |
0.330 |
0.350 |
0.020 |
1.00 |
0.02 |
| 70103700 |
TRAF CONT COMPL |
1.000 |
0.000 |
1.000 |
0.330 |
0.350 |
0.020 |
300,000.00 |
6,000.00 |
|
Total: |
$530,482.90 |
|
|